Delivery Order 47PE0119D0005-47PE0520F0049
Award Date 2/12/20
Potential Completion Date 8/14/20
Potential Value $99K
Federal Agency
Ultimate Awardee
Not listed NAICS Category
Federal Contract Vehicle
- Not listed
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition after exclusion of sources
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Gulfport, MS 39501, USA
Solicitation Procedures
Multiple Award, Fair Opportunity
Number Of Offers Received
1
Legislative Mandate
Not listed National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- This is a firm fixed-price delivery order contract awarded by the U.S. General Services Administration (GSA) Region 4 to Belinda Stewart Architects, P.A., a woman-owned small business and SBA-certified HUBZone firm. The contract, valued at $2,579,103.95, is for architectural and engineering services to design building repairs to the Mississippi River Commission building in Vicksburg, Mississippi, including asbestos inspection. The contract does not utilize a set-aside designation. Belinda...
- Belinda Stewart Architects, Pa, an SBA-certified HUBZone small business, was awarded a $105,131.97 firm fixed price delivery order against an unidentified multiple award contract vehicle. The delivery order is for an architectural and engineering window study to support renovations at the U.S. Federal Courthouse in Oxford, Mississippi. Work will be performed in Lafayette Springs, Mississippi, with completion required by May 27, 2021. The awarding agency, the General Services Administration's...
- This delivery order, awarded by the General Services Administration Public Buildings Service Region 4, is for architectural and engineering (A/E) services to design repairs to the entryway ramp inside the U.S. Courthouse in Jackson, Mississippi. Belinda Stewart Architects, P.A., a HUBZone-certified small business located in Eupora, Mississippi, will provide the A/E services, with most work performed at their home office. The firm fixed price contract value is $150,404.77 to complete the design...
- The General Services Administration's Region 4 awarded a $96,139.60 delivery order contract to Belinda Stewart Architects, PA, a woman-owned small business and SBA-certified HUBZone firm based in Eupora, Mississippi, for construction administration services related to Americans with Disabilities Act (ADA) ramp and new elevator construction at the Thad Cochran U.S. Courthouse in Jackson, Mississippi. The contract is structured as a firm fixed-price delivery order with an ultimate completion...
- Belinda Stewart Architects, PA, a woman-owned small business and SBA-certified HUBZone firm based in Eupora, Mississippi, received a delivery order valued at $533,575.09 under a firm fixed-price contract to provide architectural and engineering services for the Hugo Black Feasibility Study in Birmingham, Alabama. The work, which commenced on September 2, 2024, was recently modified to extend the period of performance through December 31, 2025, at no additional cost. Services are being...
- The Administrative Office of the U.S. Courts awarded a $402,834.55 firm fixed-price delivery order to Belinda Stewart Architects, PA on November 21, 2024, to extend the period of performance for the Hugo Black Hardening Building Services project at the Hugo L. Black U.S. Courthouse in Birmingham, Alabama. The contract, which carries no set-aside designation despite the contractor's SBA certifications as a woman-owned small business and HUBZone firm, is scheduled for ultimate completion by May...
- The General Services Administration Public Buildings Service Region 4 awarded a $7,398 firm fixed price delivery order to Electricworks Inc. to repair damage caused by Tropical Storm Claudette at the Dan M. Russell Federal Courthouse in Gulfport, Mississippi. Electricworks Inc., an SBA Certified 8A Program Participant, will provide repair services for damage to the courthouse from the storm with work expected to be completed by February 28, 2022. The delivery order was awarded on August 2,...
- The Administrative Office of the U.S. Courts awarded a delivery order valued at $452,642.45 to Belinda Stewart Architects, Pa on September 13, 2024, to provide security upgrades for the Frank M. Johnson Federal Building and U.S. Courthouse in Montgomery, Alabama. This Firm Fixed Price delivery order extends the period of performance through May 29, 2026, as part of the facility's hardening project. Belinda Stewart Architects, Pa, a woman-owned small business and SBA-certified HUBZone firm...
- This delivery order, awarded by the Administrative Office of the U.S. Courts, is for $3,375.11 to add additional power to an emergency circuit to serve new uninterruptible power supply (UPS) units at the Russell Federal Courthouse in Gulfport, Mississippi. Electricworks Inc., an SBA 8(a) Program certified small business, will perform the work as the prime contractor. The firm fixed price order is associated with a larger indefinite delivery/indefinite quantity contract vehicle held by the...
- The General Services Administration Public Buildings Service Region 4 awarded a $12,092.60 firm fixed price delivery order to Electricworks Inc. to repair hurricane damage at the DAN M RUSSELL U. S. FEDERAL COURTHOUSE COMPLEX in Gulfport, Mississippi under a multiple award contract vehicle. Electricworks Inc., an SBA Certified 8A Program Participant, will perform partition repairs by the January 30, 2022 completion date to address needs resulting from Hurricane Ida. No set-aside designation...
- 47PE0119D0005Indefinite Delivery Contract
- 47PE0119D0005-47PE0520F0049Delivery Order
The General Services Administration Public Buildings Service Region 4 awarded a $99,070.93 firm fixed price delivery order contract to Belinda Stewart Architects, Pa for architectural and engineering design services for a lightning protection system at the Dan M. Russell U. S. Federal Courthouse Complex located in Gulfport, Mississippi. As a HUBZone certified small business, Belinda Stewart Architects will provide the design and engineering required to install lightning protection at the courthouse facility, with work expected to be completed by August 14, 2020. No set-aside designation was applied to this contract action.
Generated 1/3/24, 3:38 PM
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
GSA, PBS Region 4 A&E Services IDIQ (Synopsis Issued 10/19/2018; Solicitation Issued 11/07/2018; Offer Due Date 12/7/2018; Technical Evaluations 12/10/2018 through 12/14/2018; Pricing Phase; 12/20/2018; Award; 05/24/2019) | 47PE0119R0001 | General Services Administration Public Buildings Service Region 4 | Award Notice 1/1 | 10/19/18, 4:47 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| PA0002 | Other Administrative Action | $0 | 9/30/20 | |
| PS0001 | Supplemental Agreement for work within scope | $0 | 5/5/20 | |
| Not listed | Not listed | $99.1k | 2/12/20 |