Pre-design phase services for the richford, VT BIL lpoe project. Includes unpriced option clins for design and construction services.

Active Awarded Last action

Contract number
47PB0023F0183
Awardee
Awarding agency
Obligated
$6,319,544

Award facts

Opportunity
  • 47PB0023R0018 Solicitation number
Contract value 97% obligated
$6,484,421.65 Current and potential, with all options
Completion date 62% complete
Current and potential, with all options
Contracting staff
NAICS code
541310 Architectural Services
Set-aside
No set-aside
Competition
Full and Open Competition · 5 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
New York, NY 10013, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Funding Only Action PA0017 · Correct accounting strings (part 2 ) update clin 0019's obligation to 100% on AL7. $23,744
Other Administrative Action PA0016 · DE-obligate clin 0019, which is obligated against AL5 -$23,744
Supplemental Agreement for work within scope PS0015 · Provide FF & e design services $228,650
Supplemental Agreement for work within scope PS0014 · This MOD PS0014 for RFP# 12 alta title services and RFP# 13 GEO tech at t he richmond lpoe, vermont. $55,768
Supplemental Agreement for work within scope PS0012 · This modification is to incorporate the PBS core building standards and replace the P100 facilities standards. This change is in the amount of $14,067.50. $14,068
Change Order PS0011 · Adding additional scope of work (design through pccs) with CCD extension to assist with lpoe project $4,228,606
Supplemental Agreement for work within scope PS0008 · Provide a/e services for wind engineering and vertical transportation consulting. $130,037
Other Administrative Action PS0010 · Concept design phase a/e services for the richford, VT lpoe. $0 extension MOD to extend POP end date to october 8, 2025, and the ultimate completion date to… $0
Other Administrative Action PA0009 · This contract action changes the contracting officer $0
Other Administrative Action PA0007 · This administrative MOD PA007 corrects the completion date for the concept schemes. $0
Supplemental Agreement for work within scope PS0006 · Provided three concept design schemes for richford lpoe VT $1,006,094
Supplemental Agreement for work within scope PS0005 · This modification incorporates CBP design standard and provides addition AL testing $84,588
Supplemental Agreement for work within scope PS0004 · The purpose of this modification is to provide structural coring, testing, and patching of the richford, VT lpoe building as specified in clin 0014, "structural… $33,718
Supplemental Agreement for work within scope PS0003 · The purpose of this modification is to provide structural analysis of the richford, VT lpoe building with focus on the concrete foundation and structural… $81,297
Supplemental Agreement for work within scope PS0002 · Based on the most recent ROE and scheme updates, the contractor shall survey an additional area, to include topographic and boundary surveys, as proposed on… $8,470
Other Administrative Action PA0001 · This administrative modification changes the contracting officer from blake robbins to emily jackson. There is no additional cost for this change. All other… $0
Original award $448,250
Show all 17

About this award

The General Services Administration issued a delivery order to Smith-Miller + Hawkinson Architects, LLP on July 20, 2023, for pre-design phase services on the Richford, Vermont Land Port of Entry project under the Bipartisan Infrastructure Law, with a ceiling value of $6,484,421.65 and unpriced options for design and construction services.

The order is issued under a GSA Public Buildings Service multiple-award IDIQ contract covering architectural and engineering services for federal building projects with estimated construction costs of $8 million or greater in Regions 1 and 2 (Northeast and Caribbean). Smith-Miller + Hawkinson Architects is a woman-owned small business. Place of performance is New York, NY. Ultimate completion date is November 8, 2028. The order is priced on a firm fixed price basis.

Quick answers

Who was awarded contract 47PB0023F0183?

47PB0023F0183 was awarded to Smith-Miller + Hawkinson Architects, LLP by Region 1 (Public Buildings Service) on July 20, 2023.

How much is contract 47PB0023F0183 worth?

The government has obligated $6,319,544 on 47PB0023F0183. Its current value, with exercised options, is $6,484,422.

Is contract 47PB0023F0183 an order under another contract?

Yes. 47PB0023F0183 is a delivery order under 47PC0321D0002, an indefinite delivery contract.

Was contract 47PB0023F0183 competed?

The extent of competition for 47PB0023F0183 was full and open competition. The government received 5 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award