This federal contract award with ID 1282B123D0007|1282B124F0096 was made by the U.S. Department of Agriculture (USDA) Forest Service Rocky Mountain Region to Tk3, LLC, a minority-owned and woman-owned small business. The $414,731.56 firm fixed price contract is for trail restoration, clearing, and infrastructure work under the Infrastructure Investment and Jobs Act (IIJA) major program. The work includes light and heavy trail restoration, trailway clearing and logging, drain dip construction,...
This is a firm fixed-price definitive contract awarded by the U.S. Department of Agriculture (USDA) Forest Service, Rocky Mountain Region, to Tk3, LLC, a minority-owned small business. The contract, valued at $1,168,804.00, is to construct a special rock embankment to restore vehicle access on Road 504 at Mile Post 4.2 as part of the Great American Outdoors Act (GAOA) project. The work involves excavation, sorting, and stockpiling or hauling of material, as well as placement of special rock...
This federal contract award is for the replacement of the Cedar Creek Driveway Trail Bridge in Sheridan, Wyoming. The work involves removing the existing bridge structure and installing a new 61-foot glulam stringer trail bridge with timber sill on a geocell pad, including aggregate surfacing and riprap placement. The $384,980 firm fixed price contract was awarded to Tk3, LLC, a minority-owned, self-certified small disadvantaged business, woman-owned small business, and Native American-owned...
Taylor Construction, Inc. was awarded a $23,470.97 firm fixed price delivery order against the Shoshone National Forest Roads Indefinite Delivery/Indefinite Quantity (IDIQ) contract by the U.S. Department of Agriculture Forest Service Rocky Mountain Region. This delivery order is for rehabilitation of the Kitty Creek Bridge located in Cody, Wyoming, with work to be completed by August 31, 2023. No set-aside designation was applied to this award. The Forest Service Rocky Mountain Region manages...
Taylor Construction, Inc. was awarded a $230,221.43 firm fixed price delivery order against the Shoshone National Forest Roads Indefinite Delivery/Indefinite Quantity (IDIQ) contract by the US Department of Agriculture Forest Service Rocky Mountain Region. The delivery order is for deferred maintenance on Forest Service Road 130 providing access to Lilly Lake in Cody, Wyoming, with work to be completed by October 30, 2022. The contract has a total small business set aside designation. The...
Taylor Construction, Inc. was awarded a $36,716 delivery order against the Department of Agriculture Forest Service's Indefinite Delivery Indefinite Quantity contract for the Rocky Mountain Region Roads program. The delivery order is for debris removal services at the Lightning Ridge Sunlight Picnic Ground Bridge in Cody, Wyoming, to be completed by September 18, 2023. The Forest Service will provide funding for the firm fixed price order, which will support debris clearing efforts on National...
Taylor Construction, Inc. has been awarded a $39,300.93 firm fixed price delivery order against the Department of Agriculture Forest Service Rocky Mountain Region's SHOSHONE NF ROADS IDIQ contract vehicle. This task order calls for approximately 23.4 miles of roadway reconditioning on level 3 roads in the Washakie Ranger District of the Shoshone National Forest near Lander, Wyoming, as well as 22.9 miles of roadway maintenance on the Wind River Ranger District. The work is set aside for total...
This $161,646.00 firm fixed price delivery order was awarded by the U.S. Forest Service's Northern Region to Thomas Dean & Hoskins Inc., doing business as TD And H Engineering, on September 11, 2023. The contract is for survey and design services for four Aquatic Organism Passage (AOP) crossings on National Forest creeks and streams as part of the Infrastructure Investment and Jobs Act (IIJA) program. The work is to be completed by April 15, 2024. This award is not associated with a...
Taylor Construction, Inc. was awarded a $80,226.12 firm fixed price delivery order against the Department of Agriculture Forest Service Rocky Mountain Region's Indefinite Delivery Indefinite Quantity contract for Shoshone National Forest Roads reconstruction work. The work will be completed in Cody, Wyoming by December 31, 2022 and involves reconstruction efforts for the Swamp Lake Timber Sale. No set-aside designation was applied to this award to complete road reconstruction associated with...
Taylor Construction, Inc. has been awarded a $16,985.47 firm fixed price delivery order against the Department of Agriculture Forest Service Rocky Mountain Region's Shoshone National Forest Roads Indefinite Delivery Indefinite Quantity contract. This road maintenance work on the Clarks Fork Ranger District of the Shoshone National Forest in Cody, Wyoming must be completed by October 31, 2022 and will support the agency's Shoshone National Forest Roads program. No set-aside designation was...