The work in this project consists of developing a trailhead upper parking lot and expanding and rehabilitating an existing lower trailhead parking lot at harts pass off of forest service road 5400600.…
Ended Awarded Last action
- Contract number
- 1240BJ21F0053
- Awardee
-
Batchelor Excavation, LLC UEI X5QFVSCNL4F8
- Awarding agency
-
Forest Service
Department of Agriculture
- Obligated
- $265,232
Award facts
- Contract value 100% obligated
- $265,232.29 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- Funding agency
- Region 6 - Pacific Northwest Region Forest Service, Department of Agriculture
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Set-aside
- No set-aside
- Competition
- Full and Open Competition after exclusion of sources · 2 offers Multiple Award, Fair Opportunity
- Pricing
- Firm Fixed Price
- Place of performance
- Wenatchee, WA 98801, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Other Administrative Action | $0 | |
| Change Order | $27,976 | |
| Exercise an Option | $40,327 | |
| Original award | $196,930 |
About this award
This federal contract award, with an ID of 1205M620D0004|1240BJ21F0053, was issued by the U.S. Department of Agriculture Forest Service's Region 6 - Pacific Northwest Region to the prime contractor Batchelor Excavation, LLC, doing business as J Batchelor Excavating. The work consists of developing a trailhead upper parking lot and expanding and rehabilitating an existing lower trailhead parking lot at Harts Pass off of Forest Service Road 5400600. The contract is a firm fixed price delivery order with a ceiling value of $265,232.29 and an ultimate completion date of September 30, 2023.
This task order was placed against the Forest Service R6 Road Construction indefinite delivery/indefinite quantity (IDIQ) contract vehicle, which Batchelor Excavation holds to provide excavation services, road construction, infrastructure repair, and heavy equipment rentals in support of the Forest Service's forestry management, wildfire suppression, and emergency response programs in the Pacific Northwest and other western states. The contract does not have a set-aside designation.
Description
The work in this project consists of developing a trailhead upper parking lot and expanding and rehabilitating an existing lower trailhead parking lot at harts pass off of forest service road 5400600. Contractor shall be responsible for providing all
Quick answers
Who was awarded contract 1240BJ21F0053?
1240BJ21F0053 was awarded to Batchelor Excavation, LLC by Forest Service (Department of Agriculture) on August 4, 2021.
How much is contract 1240BJ21F0053 worth?
The government has obligated $265,232 on 1240BJ21F0053.
Which agency awarded contract 1240BJ21F0053?
Forest Service (Department of Agriculture) awarded 1240BJ21F0053, with funding from Region 6 - Pacific Northwest Region (Forest Service).
Is contract 1240BJ21F0053 an order under another contract?
Yes. 1240BJ21F0053 is a delivery order under 1205M620D0004, an indefinite delivery contract, on Forest Service R6 Road Construction.
Was contract 1240BJ21F0053 competed?
The extent of competition for 1240BJ21F0053 was full and open competition after exclusion of sources. The government received 2 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award