This is the award for operations & maintenance services at the john H. Kerr reservoir for USACE - wilmington district.

Ended Definitive Contract Awarded Last action

Contract number
W912PM21C0002
Awardee
Awarding agency
Obligated
$13,784,142

Award facts

Contract value 97% obligated
$14,212,765.75 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Funding agency
Department of the Army Department of Defense
NAICS code
561210 Facilities Support Services
Set-aside
Competitive 8(a)
Competition
Full and Open Competition after exclusion of sources · 5 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Boydton, VA 23917, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Funding Only Action P00070 -$32,082
Other Administrative Action P00069 $1,000
Exercise an Option P00068 · JHK operation and maintenance 52.217-8 january option extension. $161,740
Other Administrative Action P00066 · OY4 peak level 1 O & M services $0
Exercise an Option P00067 · JHK operation and maintenance 52.217-8 january option extension. $175,740
Exercise an Option P00065 · One month extension in accordance with far 52.217-8. $175,740
Exercise an Option P00064 · Extend the term of the contract by 1 month in accordance with far 52.217-8. $150,740
Other Administrative Action P00063 · JHK powerhouse pipe insulation MOD $35,252
Funding Only Action P00062 · JHK tractor repair MOD $7,565
Funding Only Action P00061 · JHK O & M funding modification $485,733
Funding Only Action P00060 · JHK tailrace septic replacement services $25,014
Funding Only Action P00059 · Modification to add funding $529,733
Supplemental Agreement for work within scope P00058 · OY4 peak level 1 O & M services $68,498
Other Administrative Action P00057 · Modification for HVAC replacement at VAC $14,493
Funding Only Action P00056 · Funding for may and june $520,733
Funding Only Action P00055 · OY4 peak level 1 O & M services - march and april funding $450,607
Supplemental Agreement for work within scope P00054 · John H. Kerr MOD for tanner center flooring $24,734
Funding Only Action P00053 · DE-obligation of excess funds. -$74,914
Supplemental Agreement for work within scope P00052 · MOD 52 for the purchase and install of longwood entrance signs $14,595
Exercise an Option P00051 · OY4 peak level 1 O & M services $728,961
Other Administrative Action P00050 · Modification to add pump replacement, air handler for VAC and wildlife spraying and reforestation. $80,565
Funding Only Action P00049 · Funding for option year 3 JUL - OCT $856,541
Other Administrative Action P00048 · OY3 peak level 1 O & M services $218,965
Other Administrative Action P00047 · Modification to add pump lift stations for north bend park. $61,519
Other Administrative Action P00046 · Modification to add gravel and wildlife openings $30,215
Funding Only Action P00045 · Modification to fund march - june 2024 for JHK O & M services. $853,389
Supplemental Agreement for work within scope P00044 · JHK O & M services MOD to add sewer repairs, HVAC repairs, and tree removal. $705,533
Other Administrative Action P00043 · Modification to correct option year 3. $0
Supplemental Agreement for work within scope P00042 · Repair the well pump at north bend park at john H. Kerr reservoir in boydton, virginia. $17,674
Exercise an Option P00041 $633,933
Funding Only Action P00040 · OY2 peak level 1 O & M services $360,731
Funding Only Action P00039 · Modification to DE-obligate excess funds. -$61,552
Funding Only Action P00038 · Modification to add funding for the months of july & august for the john H. Kerr DAM and reservoir, operations and maintenance $429,387
Supplemental Agreement for work within scope P00037 · Modification for in-scope work of spraying and reforestations of the wildlife management areas at john H. Kerr DAM and reservoir. $78,418
Supplemental Agreement for work within scope P00036 · Modification for the tree/stump removal, landscaping, and erosion at island creek, john H. Kerr DAM and reservoir $0
Change Order P00035 · Modification for the reduction of off peak and peak services during the closure of north bend park located john H. Kerr DAM and reservoir. $0
Supplemental Agreement for work within scope P00034 · John H. Kerr DAM and reservoir operations and maintenance modification for the repair of the forestry shed doors. $16,988
Funding Only Action P00033 · March - june funding modification for the john H. Kerr DAM and reservoir operations and maintenance $774,904
Funding Only Action P00032 · John H. Kerr lake O & M services deobligation -$68,128
Funding Only Action P00031 · Funding only modification for john H. Kerr DAM and reservoir, january-february funding. $307,645
Exercise an Option P00030 · John H. Kerr O & M option year 2 exercised $333,645
Supplemental Agreement for work within scope P00029 · Modification for the reforestation of 29 acres at merifield wildlife management area at john H. Kerr DAM and reservoir. $5,478
Supplemental Agreement for work within scope P00028 · MOD P00028, purchase and installation of gravel, forestry and wildlife habitat spraying, and creation of wildlife openings. $117,871
Other Administrative Action P00027 · Modification for the purchase and install of 1 new HVAC. $6,209
Supplemental Agreement for work within scope P00026 · Modification for the installation of water cutoff valves and led lighting $127,767
Supplemental Agreement for work within scope P00025 · Emergency sewer pump repairs at john H. Kerr. $23,462
Funding Only Action P00024 · Modification to add funding for july - october, john H. Kerr O & M services. $773,715
Supplemental Agreement for work within scope P00023 · Level 2 services, pumping of lift stations - john H. Kerr O & M services. $32,148
Exercise an Option P00022 · Exercise option clin 1004 AB for additional pumping of lift stations $8,086
Supplemental Agreement for work within scope P00021 · JHK O & M contract edits to level 1 services $9,493
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

The Department of the Army awarded a $14.2 million definitive contract to Fedserv Inc. for operations and maintenance services at the John H. Kerr Reservoir on November 30, 2020, under a competitive 8(a) set-aside.

Place of performance is Boydton, VA. The contract covers sustainment of government facilities including campgrounds, day use areas, and wildlife management lands across the John H. Kerr Dam and Reservoir Project, encompassing over 50,000 acres of reservoir and 55,000 acres of surrounding land with 900 miles of shoreline. Services span four campgrounds operated across three counties in Virginia and North Carolina, plus additional day use facilities. The contract is firm fixed-price with a base year plus four option years, with ultimate completion scheduled for February 28, 2026. NAICS code 561210 applies.

Quick answers

Who was awarded contract W912PM21C0002?

W912PM21C0002 was awarded to Fedserv Inc. by ENDIST Wilmington (US Army Corps of Engineers) on November 30, 2020.

How much is contract W912PM21C0002 worth?

The government has obligated $13,784,142 on W912PM21C0002. Its current value, with exercised options, is $14,212,766.

Which agency awarded contract W912PM21C0002?

ENDIST Wilmington (US Army Corps of Engineers) awarded W912PM21C0002, with funding from Department of the Army (Department of Defense).

Was contract W912PM21C0002 competed?

The extent of competition for W912PM21C0002 was full and open competition after exclusion of sources. The government received 5 offers. It was set aside: Competitive 8(a).

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award