Sela 23A, napoleon avenue covered canal, carondelet to constance street, orleans parish, LA
Ended Definitive Contract Awarded Last action
- Contract number
- W912P813C0052
- Awardee
-
BOH Bros. Construction Co., L.L.C. UEI NS3XKMA3JWY7
- Awarding agency
-
ENDIST New Orleans
US Army Corps of Engineers, Department of Defense
- Obligated
- $39,238,419
Award facts
- Opportunity
-
- W912P813R0031 Solicitation number
- SELA-23a - Southeast Louisiana Urban, Flood Control Project, Napoleon Avenue Covered Canal, Carondelet St. To Constance St. , Orleans Parish, Louisiana (ED-12-005) Award Notice · Posted May 23, 2013
- Contract value 100% obligated
- $39,238,419.33 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Funding agency
- US Army Corps of Engineers Department of the Army, Department of Defense
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 4 offers Negotiated Proposal / Quote
- Pricing
- Firm Fixed Price
- Place of performance
- New Orleans, LA 70115, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Definitize Change Order | $525,000 | |
| Supplemental Agreement for work within scope | $50,032 | |
| Change Order | $71,900 | |
| Supplemental Agreement for work within scope | $13,900 | |
| Change Order | $30,780 | |
| Funding Only Action | -$349,478 | |
| Supplemental Agreement for work within scope | -$20,250 | |
| Supplemental Agreement for work within scope | $0 | |
| Funding Only Action | -$273,998 | |
| Definitize Change Order | $11,900 | |
| Definitize Change Order | $140,143 | |
| Other Administrative Action | -$5,280 | |
| Definitize Change Order | $128,500 | |
| Supplemental Agreement for work within scope | $0 | |
| Definitize Change Order | $21,000 | |
| Definitize Change Order | -$5,100 | |
| Funding Only Action | -$63,741 | |
| Definitize Change Order | $0 | |
| Change Order | $3,441 | |
| Definitize Change Order | $68,250 | |
| Definitize Change Order | $2,870 | |
| Supplemental Agreement for work within scope | $0 | |
| Definitize Change Order | $1,270 | |
| Definitize Change Order | $512,510 | |
| Definitize Change Order | $11,838 | |
| Definitize Change Order | $101,184 | |
| Definitize Change Order | $4,737 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Definitize Change Order | $85,796 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $48,560 | |
| Supplemental Agreement for work within scope | $22,680 | |
| Original award | $38,099,976 |
Show all 35
Quick answers
Who was awarded contract W912P813C0052?
W912P813C0052 was awarded to BOH Bros. Construction Co., L.L.C. by ENDIST New Orleans (US Army Corps of Engineers) on September 26, 2013.
How much is contract W912P813C0052 worth?
The government has obligated $39,238,419 on W912P813C0052.
Which agency awarded contract W912P813C0052?
ENDIST New Orleans (US Army Corps of Engineers) awarded W912P813C0052, with funding from US Army Corps of Engineers (Department of the Army).
Was contract W912P813C0052 competed?
The extent of competition for W912P813C0052 was full and open competition. The government received 4 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award