Construction joint cryptologic center

Ended Definitive Contract Awarded Last action

Contract number
W9128F23C0019
Awardee
Awarding agency
Obligated
$31,235,271

Award facts

Opportunity
Contract value 49% obligated
  • $62,219,568.88 Current, with exercised options
  • $63,915,568.88 Potential, with all options
Completion date 100% complete
  • Current, with exercised options
  • Potential, with all options
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Aurora, CO 80011, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00026 $176,170
Additional Work (new agreement, FAR part 6 applies) P00006 $67,968
Other Administrative Action P00005 $0
Supplemental Agreement for work within scope A00025 · Construction of a new building the JCC, including associated landscaping and underground utility install and connection to existing utilities. $6,835
Supplemental Agreement for work within scope A00024 · CD - construction joint cryptologic center, buckley SFB, CO R00032 heat trace additional circuits/HWS DDC changes $8,678
Supplemental Agreement for work within scope A00023 · CD - joint cryptologic center, buckley SFB, CO R00031 weather days JUN-JUL 2025 $0
Supplemental Agreement for work within scope A00022 · CD - joint cryptologic center, buckley SFB, CO R00030 net/TEL drops BAS, area of refuge, signage & access door $12,030
Supplemental Agreement for work within scope A00020 · CD - construction joint cryptologic center, buckley SFB, CO R00027 comm rack power changes $2,930
Supplemental Agreement for work within scope A00021 · CD - construction joint cryptologic center, buckley SFB, CO R00028 concrete cross pan drainage $16,645
Supplemental Agreement for work within scope A00019 · CD - construction joint cryptologic center, buckley SFB, CO R00029 weather delay day(s) APR24-MAY25 $0
Supplemental Agreement for work within scope A00018 · CD - construction joint cryptologic center, buckley SFB, CO R00025 500 KVA transformer nest testing $3,233
Supplemental Agreement for work within scope A00017 · CD - construction joint cryptologic center, buckley SFB, CO R00021 cable tray fill capacity R00023 additional keys for offices and classrooms R00024… $4,846
Supplemental Agreement for work within scope A00016 · CD - construction joint cryptologic center, buckley SFB, CO R00022 PFAS testing borrow site import fill $1,621
Supplemental Agreement for work within scope A00015 · CD - construction joint cryptologic center, buckley SFB, CO R00020 west canopy structural supports $23,775
Supplemental Agreement for work within scope A00014 · CD - construction joint cryptologic center, buckley SFB, CO R00019 additional disposal of racs material $91,698
Additional Work (new agreement, FAR part 6 applies) P00004 · CD - construction joint cryptologic center, buckley SFB, CO R00013 ISP MOD $316,850
Supplemental Agreement for work within scope A00013 · CD - construction joint cryptologic center, buckley SFB, CO R00017 HSS framing support $30,807
Supplemental Agreement for work within scope A00012 · CD - construction joint cryptologic center, buckley SFB, CO R00018 door cores and keys $6,361
Supplemental Agreement for work within scope A00011 · CD - construction joint cryptologic center, buckley SFB, CO R00015 AV monitors $62,154
Supplemental Agreement for work within scope A00010 · CD - construction joint cryptologic center, buckley SFB, CO R00016 flush valve circuits $12,425
Supplemental Agreement for work within scope A00009 · CD - construction joint cryptologic center, buckley SFB, CO R00014 RFI-0029 fire damper relocation $6,422
Supplemental Agreement for work within scope A00008 · CD - construction joint cryptologic center, buckley SFB, CO R00012 power to irrigation timer $14,899
Supplemental Agreement for work within scope A00007 · CD - construction joint cryptologic center, bickley SFB, CO R00010 - concrete out of spec for "time" - base operational delay causing rejection of three… $5,520
Supplemental Agreement for work within scope A00006 · CD - construction joint cryptologic center, buckley SFB, CO R00009 additional racs disposal $1,946
Supplemental Agreement for work within scope A00005 · CD - construction joint cryptologic center, buckley SFB, CO R00011 weather time extension may 23 - MAR 24 $0
Supplemental Agreement for work within scope A00004 · CD - construction joint cryptologic center, buckley SFB, CO R00008 deconflict SS and concrete encased telecomm $80,238
Exercise an Option P00003 · Construction joint cryptologic center exercise of option clins 0006 and 0007. $2,470,000
Supplemental Agreement for work within scope A00003 · CD - construction joint cryptologic center, buckley SFB, CO R00002 bedrock embed length and soil DA amount: $101,131.00 $101,131
Supplemental Agreement for work within scope A00002 · CD - construction joint cryptologic center, buckley SFB, CO R00005 import of clean fill $9,225
Supplemental Agreement for work within scope A00001 · CD - construction joint cryptologic center, buckley SFB, CO R00004 quantity variation - additional asbestos containing material/soil removal and disposal $88,864
Exercise an Option P00002 · Construction joint cryptologic center - exercise option clin 0005 $12,000
Exercise an Option P00001 · Modification to exercise an option for addition parking for the construction joint cryptologic center $310,000
Original award $27,290,000
Show all 33

About this award

The Defense Information Systems Agency (ENDIST Omaha) awarded a $63.9 million definitive firm fixed-price contract to Roundhouse PBN - Tepa EC Joint Venture for construction of a new Joint Cryptologic Center building at Buckley Space Force Base, Colorado, under a total small business set-aside on May 29, 2023, with ultimate completion by August 31, 2026.

Roundhouse PBN - Tepa EC Joint Venture is a tribally-owned and minority-owned small disadvantaged business. The scope includes construction of the JCC building with associated landscaping and underground utility installation and connection to existing utilities. Place of performance is Aurora, CO.

Quick answers

Who was awarded contract W9128F23C0019?

W9128F23C0019 was awarded to Roundhouse PBN - Tepa EC Joint Venture by ENDIST Omaha (US Army Corps of Engineers) on May 29, 2023.

How much is contract W9128F23C0019 worth?

The government has obligated $31,235,271 on W9128F23C0019. Its current value, with exercised options, is $62,219,569. Its potential value, with all options, is $63,915,569.

Was contract W9128F23C0019 competed?

The extent of competition for W9128F23C0019 was full and open competition after exclusion of sources. The government received 3 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award