- The U.S. Army's Joint Munitions Command awarded a $1.07 million delivery order to Stantec-FNI JV on September 30, 2024, for the Pine Bluff Arsenal South Side Water System Replacement project in Pine Bluff, Arkansas. This firm fixed-price task order, with an ultimate completion date of September 29, 2026, was issued without socioeconomic set-aside designation, allowing the joint venture to compete on a fully open basis. The project encompasses the replacement of aging waterline infrastructure...
- The U.S. Army Contracting Command – Rock Island, acting on behalf of the Joint Munitions Command, awarded a $4.39M firm fixed-price definitive contract to Amari Painting & Lining LLC for painting and repairs to water tanks at Pine Bluff Arsenal in Arkansas. The contract, designated as a Total Small Business set-aside, was awarded on May 17, 2024, with a completion deadline of November 17, 2025. The work encompasses sandblasting and painting six 200,000-gallon elevated water storage tanks,...
- This firm fixed-price purchase order was awarded by the Department of the Army Materiel Command Joint Munitions Command to Supplied Industrial Solutions Inc. for the delivery of over 7,000 linear feet of solid non-perforated sewer pipes. The contract valued at $297,260.04 will see the prime contractor provide 742 linear feet of 10-inch diameter pipe, 2,968 linear feet of 12-inch diameter pipe, and 2,968 linear feet of 18-inch diameter pipe to the place of performance in White Hall, Arkansas by...
- This federal contract was awarded by the Department of the Army Corps of Engineers Engineering Support Center Huntsville to the prime contractor HDR Engineering, Inc. to provide BUILDER assessments at the Pine Bluff Arsenal in Pine Bluff, Arkansas. The contract has a potential value of $1,225,931.18 and is a Firm Fixed Price Delivery Order. No set-aside designation was used. The contract involves HDR Engineering, a professional services firm, conducting assessments to support the Army's...
- Tri-State Industrial Contractors, Inc. was awarded a firm fixed price contract valued at two million two hundred twenty-two thousand ninety-one dollars by the Department of the Army Materiel Command Joint Munitions Command to perform upgrades and repairs to a white phosphorus production line at Pine Bluff Arsenal in Texarkana, Arkansas. The work includes replacing the hot water supply system, installing sixty thousand gallons of wastewater storage in three tanks, and upgrading two ABB Model...
- The Department of Defense, Army Corps of Engineers awarded a $3.3 million firm fixed-price contract to IHP Industrial Inc. for the installation of isolation valves in support of raw water piping replacement at the DeGray Power Plant in Arkadelphia, Arkansas. Per the original solicitation, the contractor will replace sections of raw water piping, install new isolation valves, remove and replace existing pipes, and ensure environmental compliance. This contract was set aside for small businesses...
- This is a definitive contract awarded by the U.S. Army Corps of Engineers, Little Rock District (ENDIST Little Rock) to the Gateway Public Water Authority of the State of Arkansas. The contract, valued at $620,997.94, is for the design, installation, and connection of a waterline to the Gateway Rural Water Authority water system, serving the Damsite North, Damsite Pines, and Damsite Parker Bottoms areas. The contract has a firm fixed price and was awarded on November 30, 2009, with a...
- The City of Watervliet was awarded a definitive, firm fixed-price contract by the U.S. Army's TACOM Life Cycle Management Command for potable water utility service at Watervliet Arsenal in Watervliet, New York. The contract, awarded on November 1, 2014, carries a ceiling value of $2,018,399.37 and extends through June 30, 2025. This administrative modification was issued to correct validation errors for migration to the Army Contract Writing System (ACWS) and updated the unit of measure for...
- <p>The Department of the Army Materiel Command Joint Munitions Command awarded a $128,275.00 firm fixed price purchase order to Woodbury-Beach Company, a for-profit small business, to replace boilers in Building 34-631 at the Pine Bluff Arsenal in North Little Rock, AR. This contract was set aside for total small business participation and originated from a February 2021 solicitation. The solicitation provided the purchase description for the required boiler replacement services.</p>
- <p>This is a firm fixed-price delivery order contract awarded by the U.S. Army Corps of Engineers (USACE) for the TAS STEAM LINE REPLACEMENT project at the Pine Bluff Arsenal in Arkansas. The total ceiling value of the contract is $16,832.61, and the ultimate completion date is October 30, 2009. The prime contractor is a joint venture between Carter & Burgess and Huitt-Zollars. This contract does not have a set-aside designation. The place of performance is Fort Worth, Texas.</p>
The U.S. Army Corps of Engineers - Little Rock District awarded a $49.6M firm fixed-price definitive contract to replace the waterline system serving Pine Bluff Arsenal in White Hall, Arkansas. This design-build project addresses critical water infrastructure upgrades at the active military installation, which currently relies on a water distribution system installed between 1942 and 1959 and supplies approximately 350,000 gallons of water daily. The scope encompasses replacement of approximately 154,000 linear feet of pipe ranging from 16 inches to smaller diameters, along with 328 fire hydrants and 186 valves, all while maintaining operational continuity at the facility. The contract was awarded November 13, 2025, with an ultimate completion date of November 22, 2027, and carries a total small business set-aside designation. The project originated from a pre-solicitation notice posted March 20, 2025, which solicited design-build contractors with demonstrated experience in water distribution infrastructure on military installations. The original solicitation estimated the contract value between $18M and $20M, significantly lower than the awarded ceiling value of $49.6M, suggesting substantial scope increases or cost adjustments during the design-build process. Funding derives from the Department of Defense through the Army Corps of Engineers, supporting essential infrastructure modernization at a critical defense facility. The contract follows a design-build delivery method with a 730-calendar-day project schedule and represents a significant capital investment in military installation infrastructure renewal.
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
PBA Waterline Replacement | W9127S25RA003 | Department of the Army Corps of Engineers Engineering District Little Rock | Pre-Solicitation 2/3 | 4/17/25, 3:51 PM | |
PBA Waterline Replacement | W9127S25RA003 | Department of the Army Corps of Engineers Engineering District Little Rock | Solicitation 3/3 | 5/5/25, 4:44 PM | |
Pine Bluff Arsenal Waterline Replacement | W9127S25RA003 | Department of the Army Corps of Engineers Engineering District Little Rock | Pre-Solicitation 1/3 | 3/20/25, 4:47 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| Not listed | Not listed | $22.9m | 11/13/25 |