American river common features, sacramento river east levee, contract 1 award

Ended Definitive Contract Awarded Last action

Contract number
W9123820C0004
Awardee
Awarding agency
Obligated
$70,121,956

Award facts

Opportunity
Contract value 100% obligated
  • $70,121,955.75 Current, with exercised options
  • $70,299,455.75 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Sacramento, CA 95814, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00025 -$9,320
Supplemental Agreement for work within scope P00009 · Cutoff: SB wall and sccb wall to (-55' $2,239,493
Supplemental Agreement for work within scope A00024 · Cutoff: SB wall and sccb wall to (-55'). CD047 inspection fees. $13,841
Supplemental Agreement for work within scope A00023 · Cutoff: SB wall and sccb wall to (-55'). CD0023 option 1005 late award costs. $499,500
Supplemental Agreement for work within scope A00022 $267,697
Supplemental Agreement for work within scope A00021 $218,478
Supplemental Agreement for work within scope A00020 $80,646
Supplemental Agreement for work within scope A00019 · Cutoff: SB wall and sccb wall to (-55' $150,768
Supplemental Agreement for work within scope A00018 · Cutoff: SB wall and sccb wall to (-55'). Clin 6 rock redesign $120,350
Supplemental Agreement for work within scope A00017 · Cutoff: SB wall and sccb wall to (-55') R026 CD035 CD040 misc. Changes $190,082
Supplemental Agreement for work within scope A00016 $73,915
Supplemental Agreement for work within scope A00015 · Cutoff: SB wall and sccb wall to (-55' $123,997
Supplemental Agreement for work within scope A00014 · Cutoff: SB wall and sccb wall to (-55') R022 misc. Changes $95,671
Supplemental Agreement for work within scope A00013 $150,871
Supplemental Agreement for work within scope A00012 $5,000
Supplemental Agreement for work within scope A00011 $132,579
Supplemental Agreement for work within scope A00010 $51,359
Supplemental Agreement for work within scope A00009 · Cutoff: SB wall and sccb wall to (-55' $205,301
Supplemental Agreement for work within scope A00008 · Cutoff: SB wall and sccb wall to (-55'). CD020 & CD026 misc. Changes. $155,161
Supplemental Agreement for work within scope A00007 · Cutoff: SB wall and sccb wall to (-55' $11,750
Supplemental Agreement for work within scope A00006 · Cutoff: SB wall and sccb wall to (-55'). Change to garcia bend park entrance. -$138,342
Supplemental Agreement for work within scope A00005 · Cutoff: SB wall and sccb wall to (-55'). Trash in ballast rock. $138,758
Supplemental Agreement for work within scope P00008 · Cutoff: SB wall and sccb wall to (-55' $680,657
Supplemental Agreement for work within scope A00004 · Unknown city fiber line $99,772
Supplemental Agreement for work within scope A00003 · Cutoff: SB wall and sccb wall to (-55'). Tree & stump removal various locations. $232,000
Change Order A00002 · Cutoff: SB wall and sccb wall to (-55') remove SCB boulders in option 6 area. $133,862
Supplemental Agreement for work within scope A00001 · Install 3 inch galvanized pipe $61,494
Exercise an Option P00007 · Exercise optional clin 1005 $1,379,306
Other Administrative Action P00006 · Funding source change $0
Supplemental Agreement for work within scope P00005 · Increased controlled degrade part 2 $62,880
Exercise an Option P00004 · Exercise option clin 1006 - cutoff: DMM wall to (-95' to -15') $8,993,349
Change Order P00003 · Controlled degrade from 1000 LF to 2100 LF $200,000
Exercise an Option P00002 · Exercise option clins 1001, 1003, 1004, 1006, and 1007. $5,567,833
Other Administrative Action P00001 · Modification to issue notice to proceed $0
Original award $47,933,247
Show all 35

About this award

The U.S. Army Corps of Engineers, Engineering District Sacramento awarded a $70.3 million firm fixed price contract to Maloney-Odin JV on February 14, 2020. The contract is for improvements to approximately three miles of the Sacramento River East Levee in Sacramento, California under the American River Common Features, Sacramento River East Levee, Contract 1 project. Work will involve degrading and reconstructing over two miles of levee, constructing cutoff walls and berms totaling around 180,000 cubic yards, reusing and importing soils, removing and replacing bike paths and utilities, and restoring disturbed areas. All work must be completed by January 16, 2021 to restore the flood protection line by the end of the single 2020 construction season. No set-aside designation was specified. Funding is provided by the U.S. Army Corps of Engineers to improve flood risk management infrastructure along the Sacramento River.

Quick answers

Who was awarded contract W9123820C0004?

W9123820C0004 was awarded to Maloney-Odin JV by ENDIST Sacramento (US Army Corps of Engineers) on February 14, 2020.

How much is contract W9123820C0004 worth?

The government has obligated $70,121,956 on W9123820C0004. Its potential value, with all options, is $70,299,456.

Was contract W9123820C0004 competed?

The extent of competition for W9123820C0004 was full and open competition. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award