East branch cutoff wall remediation construction project
Ended Definitive Contract Awarded Last action
- Contract number
- W911WN14C0002
- Awardee
-
Bencor Global, Inc. UEI PJRMMD5ANGG3 Part of Keller Group PLC
- Awarding agency
-
ENDIST Pittsburgh
US Army Corps of Engineers, Department of Defense
- Obligated
- $190,740,359
Award facts
- Opportunity
-
- W911WN13R0002 Solicitation number
- W911WN-13-r-0002 east branch cutoff wall construction project - special notice 7 OCT 2013 Award Notice · Posted Oct 7, 2013
- East Branch Cutoff Wall Construction Project Award Notice · Posted Mar 8, 2013
- Contract value 100% obligated
- $191,343,070.05 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Funding agency
- US Army Corps of Engineers Department of the Army, Department of Defense
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Z2KA Repair Or Alteration Of Dams
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 5 offers Negotiated Proposal / Quote
- Pricing
- Firm Fixed Price
- Place of performance
- Wilcox, PA 15870, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $10,500,000 | |
| Change Order | -$615,441 | |
| Other Administrative Action | $0 | |
| Change Order | $0 | |
| Change Order | -$1,010,853 | |
| Change Order | $24,500,000 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Other Administrative Action | $12,491,194 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Funding Only Action | $21,000,000 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Funding Only Action | $4,800,000 | |
| Funding Only Action | $16,000,000 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Funding Only Action | $153,300 | |
| Funding Only Action | $8,000,000 | |
| Other Administrative Action | $5,000,000 | |
| Additional Work (new agreement, FAR part 6 applies) | $0 | |
| Funding Only Action | $5,000,000 | |
| Funding Only Action | $6,500,000 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Funding Only Action | $4,950,000 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Funding Only Action | $2,000,000 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Funding Only Action | $15,000,000 | |
| Change Order | $0 | |
| Funding Only Action | $10,000,000 | |
| Change Order | $0 | |
| Vendor DUNS or Name Change - Non-Novation | $0 | |
| Change Order | $0 |
Show 40 more
Latest 50 listed here. See the rest on GovTribe.
Quick answers
Who was awarded contract W911WN14C0002?
W911WN14C0002 was awarded to Bencor Global, Inc. by ENDIST Pittsburgh (US Army Corps of Engineers) on August 26, 2014.
How much is contract W911WN14C0002 worth?
The government has obligated $190,740,359 on W911WN14C0002. Its current value, with exercised options, is $191,343,070.
Which agency awarded contract W911WN14C0002?
ENDIST Pittsburgh (US Army Corps of Engineers) awarded W911WN14C0002, with funding from US Army Corps of Engineers (Department of the Army).
Was contract W911WN14C0002 competed?
The extent of competition for W911WN14C0002 was full and open competition. The government received 5 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award