This is a continuation of SP0600-02-C-8250, awarded on september 26, 2002, due to the transfer of contract administration. The period of performance is september 26, 2002 to september 25, 2052 (600…

Active Definitive Contract Awarded Last action

Contract number
SP060021C8346
Awardee
Awarding agency
Obligated
$81,489,453

Award facts

Opportunity
  • SP060000R0009 Solicitation number
Contract value 47% obligated
$171,754,622.10 Current and potential, with all options
Completion date 48% complete
Current and potential, with all options
Contracting staff
Funding agency
Southwest Region Installation Management Command, Department of Defense
NAICS code
221122 Electric Power Distribution
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Negotiated Proposal / Quote
Pricing
Fixed Price Redetermination
Place of performance
Fort Bliss, TX 79916, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00066 · Authorize a no-cost extension to the project completion date for project fbtx-E-24-001 advanced metering infrastructure FB main cantonment, originally… $0
Funding Only Action P00065 · Establish two months of funding for utility service charge for CY 24 for the period of performance of may 1, 2026 through june 31, 2026. $2,399,296
Funding Only Action P00064 · Establish one month of funding for utility service charge for CY 24 for the period of performance of april 1, 2026 through april 31, 2026, on subclin 0024AA,… $1,199,648
Change Order P00063 · Update RIO grande electric cooperative, INC. Project fbtx-E-25-007 range 61 offset, previously awarded in P00057. The contract line-item number clin 0069 is… $0
Other Administrative Action P00061 · Revise contract section G.5, clause dfars 252.232-7006, wide area workflow payment instructions, to update the routing data table and service acceptor… $0
Funding Only Action P00062 · Provide 3 months of funding for the utility service charge for CY 24 on subclin 0024AA and 3 months of funding for the initial CIP west project for the period… $3,598,944
Change Order P00060 · This modification updates pricing for projects fbtx-E-25-006 and fbtx-E-24-006. $0
Funding Only Action P00059 · This modification provides three months of funding for the USC contract year 24, and the initial CIP west project for the period of performance of october 1,… $3,598,944
Other Administrative Action P00058 · Revises language in contract section G.2 submission and payment of invoices contract section G.5, clause dfars 252.232-7006, wide area workflow payment… $0
Funding Only Action P00057 · The modification establishes and funds clins 0067, 0068, and 0069 for projects fbtx-E-24-006, fbtx-E-25-006, and fbtx-E-25-007. $676,140
Other Administrative Action P00056 · The purpose of this modification is to update section I, contract clauses, in accordance with executive orders 14173 and 14168. $0
Funding Only Action P00055 · Establish two months of funding for the period of performance of august 1, 2025 through september 30, 2025. $2,399,296
Funding Only Action P00054 · Establish two months of funding for the period of performance of june 1, 2025 through july 31, 2025. $2,399,296
Funding Only Action P00053 · Establish two months of funding for the utility service charge for CY23 for the period of performance of april 1, 2025 through may 31, 2025, on subclin… $2,399,296
Funding Only Action P00052 · This modification funds the performance period of february 1, 2025 through march 31, 2025 $2,399,296
Funding Only Action P00051 · This modification establishes and provides two months of funding for the utility service charge and initial CIP west project for POP DEC 1, 2024 - JAN 31, 2025. $2,399,296
Funding Only Action P00050 $1,199,648
Funding Only Action P00049 · This modification establishes and provides one month of funding for the utility service charge and initial CIP west project for POP OCT 1 - 31, 2024. $1,199,648
Other Administrative Action P00048 · The purpose of this modification is to incorporate updates to dfars 252.204-7012 and 252.204-7020. $0
Other Administrative Action P00047 · The purpose of this modification is to incorporate attachment JA44B wage determination in its entirety with updates applicable to contract year 23 for POP… $0
Supplemental Agreement for work within scope P00046 $37,014
Supplemental Agreement for work within scope P00043 $57,146
Supplemental Agreement for work within scope P00045 $1,240,888
Supplemental Agreement for work within scope P00044 · Accept and fund the following RIO grande electric cooperative, INC. (RGEC) firm fixed price proposals of fbtx-E-24-001. $1,050,023
Supplemental Agreement for work within scope P00042 $144,441
Supplemental Agreement for work within scope P00041 · The purpose of this action is to accept and fund RIO grande electric cooperative, INC. Firm fixed price project fbtx-E-24-009 industrial pad mounted nova. $188,925
Terminate for Convenience P00040 · The purpose of this action is to terminate project ftbx-E-22-005 for the convenience of the government and establish agreed upon settlement costs. -$145,201
Funding Only Action P00039 · Funds six months of performance for the period of april 1 2024- september 30 2024. $7,197,888
Funding Only Action P00038 · Obligates two months of funding for the utility service charge for contract year 22 for POP FEB 1 2024 to march 31, 2024 and two months of funding for the… $2,399,296
Funding Only Action P00037 · Obligates three months of funding for the utility service charge for contract year 22 and three months of funding for the initial CIP west project. $3,598,944
Funding Only Action P00036 · The purpose of this modification is to establish and provide one month of funding for the utility service charge for contract year 22 for the period of… $1,199,648
Other Administrative Action P00035 · The purpose of this modification is to replace and incorporate attachment JA44B wage determinations. $0
Supplemental Agreement for work within scope P00034 · The purpose of this modification is to accept and fund RIO grande electric cooperative, INC. (RGEC) project fbtx-E-23-001. $397,994
Funding Only Action P00033 · The purpose of this modification is to establish and provide three months of funding for the period of performance of july 1 - september 30, 2023. $3,598,944
Supplemental Agreement for work within scope P00030 · The purpose of this modification is to authorize a no-cost extension to the project completion date for projects awarded on modifications P00018 and P00019. $0
Change Order P00031 · The purpose of this modification is to issue a change order pursuant to far 52.243-1 changes - fixed price (ALT 1), which requires rgec to submit an annual usca… $0
Other Administrative Action P00032 · The purpose of this modification is to incorporate far clause 52.204-27 in accordance with far 4.2203 and OMB memorandum M-23-13, dated FEB 27, 2023, "no tiktok… $0
Other Administrative Action P00029 · The purpose of this modification is to replace and incorporate attachment J22, mspr form electric(V2). $0
Other Administrative Action P00028 · The purpose of this modification is to make administrative corrections to section I.4 of the contract. $0
Funding Only Action P00027 · The purpose of this modification is to establish and provide three months of funding for the period of performance of april 1 - june 30, 2023. $3,598,944
Supplemental Agreement for work within scope P00026 · The purpose of this modification is to incorporate the army's new standardized mspr monthly report templates, replacing the old outage report format. $0
Funding Only Action P00025 · The purpose of this modification is to provide two (2) months of funding for the performance period of february 1, 2023 to march 31, 2023. $2,399,296
Funding Only Action P00024 $1,199,648
Funding Only Action P00023 $1,199,648
Funding Only Action P00022 $1,199,648
Funding Only Action P00021 · The purpose of this modification is to provide one month of funding for the performance period of october 1 to october 31, 2022. $1,199,648
Other Administrative Action P00020 · The purpose of this modification is to incorporate the updated applicable wage determinations. $0
Supplemental Agreement for work within scope P00019 $834,765
Supplemental Agreement for work within scope P00018 · The purpose of this modification is to fund and authorize completion of project fbtx-E-21-003 and project fbtx-E-22-005. $446,157
Funding Only Action P00017 · The purpose of this modification is to obligate funding for the performance period of 1 september 2022 - 30 september 2022. $1,199,648
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

The Southwest Region, designated a Defense funding agency, awarded a fixed-price redetermination definitive contract to RIO Grande Electric Cooperative, Inc. (doing business as Rionet) for an advanced metering infrastructure project at Fort Bliss, Texas, with a $171.8 million ceiling, a September 26, 2002 award date, and a project completion date extended to December 31, 2026. No set-aside was used.

The record continues SP0600-02-C-8250 following the transfer of contract administration, with a period of performance from September 26, 2002 to September 25, 2052 (600 months). A modification authorizes a no-cost extension of Project FBTX-E-24-001, Advanced Metering Infrastructure FB Main Cantonment, originally executed on P00044 under CLIN 0064. Place of performance is Fort Bliss, TX 79916.

Description

This is a continuation of SP0600-02-C-8250, awarded on september 26, 2002, due to the transfer of contract administration. The period of performance is september 26, 2002 to september 25, 2052 (600 months).

Quick answers

Who was awarded contract SP060021C8346?

SP060021C8346 was awarded to RIO Grande Electric Cooperative, Inc. by Energy (Defense Logistics Agency) on September 26, 2002.

How much is contract SP060021C8346 worth?

The government has obligated $81,489,453 on SP060021C8346. Its current value, with exercised options, is $171,754,622.

Which agency awarded contract SP060021C8346?

Energy (Defense Logistics Agency) awarded SP060021C8346, with funding from Southwest Region (Installation Management Command).

Was contract SP060021C8346 competed?

The extent of competition for SP060021C8346 was full and open competition. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award