FY19 mcon p-169 water transmission line, waiawa, jbphh, oahu

Ended Definitive Contract Awarded Last action

Contract number
N6274219C1319
Awardee
Awarding agency
Obligated
$74,546,726

Award facts

Opportunity
Contract value 100% obligated
$74,546,726.42 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Pearl City, HI 96782, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00008 -$65,209
Supplemental Agreement for work within scope P00007 · P-169 waterline $0
Supplemental Agreement for work within scope P00006 $8,435,045
Supplemental Agreement for work within scope P00005 · N62742-19-c-1319 mcon p-169 water transmission line, waiawa, oahu, hawaii modification for PC 6 for varying AC thickness along waihona street (STA 5+00 to… $1,064,955
Supplemental Agreement for work within scope P00004 · N62742-19-c-1319 FY19 mcon p-169 water transmission line, waiawa, oahu, hawaii modifications for unforeseen conditions for PC 62 varying AC thickness along… $390,124
Supplemental Agreement for work within scope P00003 · Contract no. N62742-19-c-1319 FY19 mcon p-169 water trasmission line, waiawa, HI modification for PC 23 and PC 43 for unforeseen hard rock conditions. $1,540,194
Supplemental Agreement for work within scope P00002 -$133,840
Supplemental Agreement for work within scope P00001 · Contract no. N62742-19-c-1319 mcon FY19 p-169 water transmission line, waiawa, oahu, hawaii modifications for various proposed changes (PCS) 4, 31, 36, 45,… $567,980
Supplemental Agreement for work within scope A00020 $1,674,867
Change Order A00019 · N62742-19-c-1319 mcon p-169 water transmission line, waiawa, oahu, hawaii modification to suspend all on-site work until further notice due to government delays… $0
Change Order A00018 · N62742-19-c-1319 mcon FY19 p-169 water transmission line, waiawa, oahu, hawaii modification for PC 35 ARV in vertical manhole per RFI 84. $7,272
Change Order A00017 · N62742-19-c-1319 mcon p-169 water transmission line, waiawa, oahu, hawaii modification for PC 24 relocate overhead lines near pile p-80 in UH urban gardens,… $30,355
Change Order A00016 · N62742-19-c-1319 mcon p-169 water transmission line, waiawa, jbphh, HI modification for the installation of the vehicle repair bridge at the waiawa pump… $829,406
Change Order A00015 $160,519
Supplemental Agreement for work within scope A00014 $9,476,270
Change Order A00013 · N62742-19-c-1319 FY19 mcon p-169 water transmission line, waiawa, jbphh, oahu, HI modification for htcom ductbank waterline realignment overpour existing… $81,822
Change Order A00012 · N62742-19-c-1319 FY19 mcon p-169 water transmission line, waiawa, waiawa, jbphh, oahu, hawaii modification (PC 038) for procurement and delivery items for… $75,128
Change Order A00011 · N62742-19-c-1319 mcon FY19 water transmission line, waiawa, jbphh, HI modification to incorporate revised specs and drawings for the bridge near waiawa pump… $1,225,867
Change Order A00010 · N62742-19-c-1319 mcon FY19 p-169 water transmission line, waiawa, oahu, hawaii unforseen modifications for PC 25 comm at pump station, PC 26 removal of 12INCH… $19,412
Change Order A00009 · N62742-19-c-1319 FY19 mcon water transmission line, waiawa, oahu, hawaii modification due to unforeseen board of water supply (BWS)6 inch lateral lines not… $173,678
Change Order A00008 · N62742-19-c-1319 mcon p-169 water transmission line, waiawa, oahu, hawaii modification for PC 14 (existing 4 inch BWS lateral STA 11+83 lower than plan… $100,760
Change Order A00007 · N62742-19-c-1319 mcon FY19 water transmission line, waiawa, hawaii modification to install a concrete jacket over the 6" lateral and demolish any excess… $22,400
Change Order A00006 · N62742-19-c-1319 mcon p-169 water transmission line, waiawa, hawaii modification to incorporate hawaii gas relocation proposal amount above cost estimate stated… $573
Change Order A00005 · N62742-19-c-1319 FY19 mcon water transmission line, waiawa, jbphh, oahu, hawaii modification for unfo sinkhole located in UH gardens area. $45,491
Change Order A00004 · N62742-19-c-1319 mcon p-169 water transmission line, waiawa, jbphh, HI modification for hart coordination and resequencing and accelerating work. $278,523
Change Order A00003 · N62742-19-c-1319 FY19 mcon p-169, water transmission line, waiawa, jbphh, HI modification (PC 5, 7, 9, 12) for unforeseen and design changes for the waterline… $280,597
Change Order A00002 · N62742-19-c-1319 FY19 mcon p-169, water transmission line, waiawa, jbphh, oahu, hawaii modification provides for actual cost estimate for heco and htcom work… $8,077
Change Order A00001 · N62742-19-c-1319 FY19 mcon p-169, water transmission line, waiawa, oahu, hawaii. Modification (credit) to incorporate easements & tree plan (reduction in… -$41,540
Original award $48,298,000
Show all 29

About this award

On March 29, 2019, Naval Facilities Engineering Command (NAVFAC) awarded a $74.5 million firm fixed-price definitive contract to Hawaiian Dredging Construction Company, Inc. for the design and construction of a water transmission line at Waiawa, Joint Base Pearl Harbor-Hickam (JBPHH) on Oahu, Hawaii. The contract, which carries an ultimate completion date of March 15, 2025, was awarded without a set-aside designation following a competitive solicitation process that closed on December 17, 2018. This infrastructure project supports critical water supply capabilities for one of the Navy's most strategically important installations in the Pacific region.

Hawaiian Dredging Construction Company, Inc., a Honolulu-based contractor and subsidiary of Japan-based Kajima Corporation, brings substantial experience in complex military and infrastructure construction projects throughout Hawaii and the Pacific. The company operates as a prime contractor under significant NAVFAC vehicles, including an $8 billion multiple-award indefinite delivery/indefinite quantity (IDIQ) contract for design-build and design-bid-build construction services across Hawaii and Wake Island. This water transmission line project represents a key utility infrastructure investment supporting JBPHH's operational requirements and demonstrates the contractor's established capability to execute large-scale, technically demanding construction efforts for the Department of Defense.

Quick answers

Who was awarded contract N6274219C1319?

N6274219C1319 was awarded to Hawaiian Dredging Construction Company, Inc. by Naval Facilities Engineering Command (Department of the Navy) on March 29, 2019.

How much is contract N6274219C1319 worth?

The government has obligated $74,546,726 on N6274219C1319.

Was contract N6274219C1319 competed?

The extent of competition for N6274219C1319 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award