P-266 structural shops consolidation

Ended Definitive Contract Awarded Last action

Contract number
N4008515C8746
Awardee
Awarding agency
Obligated
$42,213,360

Award facts

Opportunity
Contract value 98% obligated
  • $42,213,360.19 Current, with exercised options
  • $42,963,360.19 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Kittery, ME 03904, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00037 · Adds sanitary sewer line repair within existing tunnel to the project to allow for completion of system testing. $17,854
Supplemental Agreement for work within scope P00036 · Customer equipment change to steam tank & NDT bench $15,010
Supplemental Agreement for work within scope P00035 · Reinstallation/reorientation of pipe bending machine. $64,950
Supplemental Agreement for work within scope P00034 · NDT test bench move, ventilation change for brazing room & flush tank $28,809
Supplemental Agreement for work within scope P00033 · B75 move out delays and other equipment install changes $151,775
Supplemental Agreement for work within scope P00032 · Laser recert & other equipment mods $59,949
Supplemental Agreement for work within scope P00031 · Laser exhaust equipment installation maodification $16,453
Supplemental Agreement for work within scope P00030 · Laser utility changes - equipment relocation work $51,176
Supplemental Agreement for work within scope P00029 · Slab moisture mitigation, added fire safety devices, access panels for fire suppression inspection, flex floor correction $302,139
Supplemental Agreement for work within scope P00028 · Micro-pile delay - B75 soil mitigation; controls coordination changes $684,158
Supplemental Agreement for work within scope P00027 · Resolution of 33 PCS at net no cost $0
Supplemental Agreement for work within scope P00026 · Delete paving & add roof sheathing & support replacement $0
Supplemental Agreement for work within scope P00025 · Winter conditions 2017/2018 $139,844
Supplemental Agreement for work within scope P00024 · Winter conditions costs 2016/2017 $174,411
Supplemental Agreement for work within scope P00023 · Government delay due to relocated equipment from B155 $228,944
Supplemental Agreement for work within scope P00022 · Delay due to customer not having equipment platform available. $165,025
Supplemental Agreement for work within scope P00021 · Phase II ledge removal in B75 $41,755
Supplemental Agreement for work within scope P00020 · Delays due to forge area access problem - government caused $331,484
Supplemental Agreement for work within scope P00019 · Additional hazardous soil handing in B75 $155,813
Supplemental Agreement for work within scope P00018 · Delay costs associated with equipment in B75 lean-to not made available to contractor for relocation $221,633
Supplemental Agreement for work within scope P00017 · Add ledge removal & disposal from within B75(phase I) $183,212
Supplemental Agreement for work within scope P00016 · Equipment foundation work due to unforeseen conditions encountered $87,161
Supplemental Agreement for work within scope P00015 · Added slab cost disposal B75 $214,433
Change Order P00014 · Resolution of PCS 31/32/46/48/50 - net no cost MOD $0
Change Order P00013 · Equipment & installation $1,394,000
Change Order P00012 · Resolve numerous proposed changes $169,322
Change Order P00011 · FF & E for B75 $294,367
Change Order P00010 · FF & E for B76 $325,780
Change Order P00009 · Micro piles & added foundation work $321,591
Exercise an Option P00008 · Exercise option 1 $1,425,000
Exercise an Option P00006 · Execute option 5 (updated) a/V package purchase $418,265
Additional Work (new agreement, FAR part 6 applies) P00007 · Provide traffic control as customer requires and funds $280,792
Change Order P00005 · Added foundation work due to unforeseen conditions $561,178
Additional Work (new agreement, FAR part 6 applies) P00004 · Additional hazardous material abatement necessary to complete the project $4,223,178
Exercise an Option P00003 · Exercise option 3 - remove & dispose of bridge crane $20,000
Other Administrative Action P00002 · ACO transfer modification $0
Supplemental Agreement for work within scope P00001 · Correction to liquidated damages calculations $0
Original award $29,443,899
Show all 38

About this award

This is a $42,963,360.19 firm-fixed-price contract awarded by the Naval Facilities Engineering Command (NAVFAC) to Methuen Construction Co Inc. (MC) for the P-266 Structural Shops Consolidation project in Kittery, Maine. The contract involves general construction services, including design, construction, and modifications to facilities at the Portsmouth Naval Shipyard.

MC is a for-profit construction firm that has previously received multiple large contracts from the U.S. Navy for construction projects at the Portsmouth Naval Shipyard, demonstrating its expertise in executing large-scale industrial and naval facility construction projects. This contract does not have a set-aside designation.

Quick answers

Who was awarded contract N4008515C8746?

N4008515C8746 was awarded to Methuen Construction Co Inc. by Naval Facilities Engineering Command (Department of the Navy) on August 17, 2015.

How much is contract N4008515C8746 worth?

The government has obligated $42,213,360 on N4008515C8746. Its potential value, with all options, is $42,963,360.

Was contract N4008515C8746 competed?

The extent of competition for N4008515C8746 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award