Base item and options 0001 - 0005

Ended Definitive Contract Awarded Last action

Contract number
N4008511C7231
Awardee
Awarding agency
Obligated
$25,242,555

Award facts

Opportunity
Contract value 100% obligated
$25,242,554.87 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
236220 Commercial and Institutional Building Construction
PSC
Y199 Construct/Misc Bldgs
Set-aside
No set-aside
Competition
Full and Open Competition · 7 offers Two Step
Pricing
Firm Fixed Price
Place of performance
Newport, RI 02841, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action P00032 · Issue bilateral settlement agreement for griffin electric work $0
Other Administrative Action P00031 · Admin MOD to correct effective date for MOD P00030 form 11/167 to 11/27 due to typo $0
Supplemental Agreement for work within scope P00030 · Incorporate settlement and release agreement for EMI conduit asbca claim $35,000
Additional Work (new agreement, FAR part 6 applies) P00029 · Incorporate settlement agreement for claim 14-M04 PC 80 removal of contaminated soils $150,000
Supplemental Agreement for work within scope P00028 · Boiler piping rework and motion table roof alterations $90,102
Change Order P00027 · Incorporate settlement agreement on claim 13-M02 $6,500
Supplemental Agreement for work within scope P00026 · Remove unforeseen asbestos at pier 2 building demo site $155,114
Supplemental Agreement for work within scope P00025 · Electrical changes in rooms 217 and 401 due to design errors. $150,904
Change Order P00024 · Make necessary adjustments to the fire alarm system on pier 2 so IT is fully operational. $61,637
Supplemental Agreement for work within scope P00023 · Incorporate minor punch list item such as relocating a disconnect, installing an additional light in the elevator machine room, and replacing locks. $15,353
Supplemental Agreement for work within scope P00022 · The purpose of this modification is to include those changes assocaited with the tower roof stair hatch. $244,247
Supplemental Agreement for work within scope P00021 · The purpose of this modification is to incorporate the following changes: concrete pedestal change, new exit sign, break size change, added lightning… $18,549
Change Order P00020 · Provide and install longer hydraulic cylinders. $91,116
Change Order P00019 · This unilateral modification is issued to incorporate PCS 145 (change diameter of pipe holes and incorporate mesh screen to allow for adequate pond drainage)… $15,770
Change Order P00018 · This unilateral modification incorporates 12 various changes. $94,838
Supplemental Agreement for work within scope P00017 · This modification incorporates those changes associated with PCS 135 and 137. $16,993
Supplemental Agreement for work within scope P00016 · This modification incorporates those changes associated with the 29 PCS for this change. $520,408
Change Order P00015 · This unilateral modification is issued to incorporate those changes associated with the periscope rails. $7,517
Funding Only Action P00014 · This modification is to incorporate the funding ommitted from a previous modification. $100,130
Supplemental Agreement for work within scope P00013 · The modification includes 20 proposed changes for various pieces of work. $184,173
Supplemental Agreement for work within scope P00012 · This modification is to incorporate the various changes associated with 22 individuals PCS. $0
Change Order P00011 · This modification is to incorporate the changes associated with PCS 52, telecom survey; 79, roof top air handler valves; 90, replace filtrine water supply and… $483,168
Change Order P00010 · This modification is to incorporate the changes related to ten (10) various change orders. $177,081
Supplemental Agreement for work within scope P00009 · This modification is to incorporate the changes related to the installation of a unistrut support system in the shield room. $13,852
Change Order P00008 · This modification is to incorporate the changes related to the relocation of twenty-one fan coil units from the wall to the ceiling. $357,316
Change Order P00007 · Install two fixed cranes $632,864
Supplemental Agreement for work within scope P00006 $427,074
Change Order P00005 · Base item $151,448
Supplemental Agreement for work within scope P00004 · Base item metal paint panel and roof coating PC 23 and PC 24 $226,221
Supplemental Agreement for work within scope P00003 · Incorporate PCS 5, 19 and 20 $18,666
Supplemental Agreement for work within scope P00002 · Ification to include PC 02 horizontal bracing in periscope tower; PC 03 installation of member after roof dead loads are in place; PC 04 additional girt in… $29,036
Supplemental Agreement for work within scope P00001 · Asbestos pipe unfo MOD. $86,794
Original award $20,680,684
Show all 33

Quick answers

Who was awarded contract N4008511C7231?

N4008511C7231 was awarded to Suffolk Construction Company, Inc. by Naval Facilities Engineering Command (Department of the Navy) on August 9, 2011.

How much is contract N4008511C7231 worth?

The government has obligated $25,242,555 on N4008511C7231.

Was contract N4008511C7231 competed?

The extent of competition for N4008511C7231 was full and open competition. The government received 7 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award