Definitive Contract IBM10C0007
Award Date 12/30/09
Potential Completion Date 2/29/12
Potential Value $26M
Federal Agency
Awardee
Ultimate Awardee
Not listed NAICS Category
PSC Category
Federal Contract Vehicle
- Not listed
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Mercedes, TX, USA
Solicitation Procedures
Sealed Bid
Number Of Offers Received
11
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- This is a $11,036,274.50 firm-fixed-price definitive contract awarded by the International Boundary and Water Commission U.S.-Mexico, a civilian federal agency, to Sbbi, Inc. (doing business as Sun Belt Builders), a woman-owned small business and minority-owned company, for the construction of the Hidalgo Levee Phase 1 and 2 project. The contract has a HUBZone set-aside designation and a period of performance ending on March 27, 2103. No additional information about subcontractors or the...
- <p>This is a $24,976,249.11 firm fixed price definitive contract awarded by the International Boundary and Water Commission U.S.-Mexico, a civilian federal agency, to Longhorn Excavators Inc. for RECOVERY - MAIN FLOODWAY LEVEE IMPROVEMENTS IN HIDALGO COUNTY, TX. The contract has an ultimate completion date of February 21, 2012 and was awarded on August 21, 2009. This contract does not have a set-aside designation.</p>
- This is a $8,199,875.37 firm fixed price contract awarded by the International Boundary and Water Commission U.S.-Mexico, a civilian federal agency, to Ultimate Concrete LLC, a minority-owned, small disadvantaged, veteran-owned limited liability company. The contract is for the RECOVERY - SUNLAND PARK LEVEE REHABILITATION project, and has a set-aside designation for total small businesses. The contract was awarded on September 10, 2010 with a targeted completion date of November 30, 2013. The...
- This is a $8,225,232.57 firm fixed-price definitive contract awarded by the International Boundary and Water Commission U.S.-Mexico, a civilian agency, to Ultimate Concrete LLC, a minority-owned, self-certified small disadvantaged business, for construction and rehabilitation improvements to the Fabens Levee Reach in El Paso County, TX and the Ft. Hancock Reach in Hudspeth County, TX. The contract is recovery-related and has an ultimate completion date of August 18, 2011. It does not have a...
- This is a $145,645.00 firm fixed-price delivery order awarded by the International Boundary and Water Commission U.S.-Mexico, a civilian agency, to S & B Infrastructure LTD. The contract is for aerial survey services to support the design of rehabilitation improvements for the Lateral A to Retamal Dam Levee Reach, as part of a recovery effort. The work is being performed in Houston, Texas. This delivery order is part of a larger indefinite delivery vehicle (IDV) contract held by S & B...
- This is a delivery order contract awarded by the International Boundary and Water Commission U.S.-Mexico, a civilian federal agency, to Tetra Tech, Inc. for construction management services related to the Recovery Act-funded project for the Lateral A to Retamal Dam River Levee and Retamal Dike in Mercedes, Texas. The contract is a firm fixed-price contract with a ceiling value of $569,429.88 and an ultimate completion date of January 21, 2011. The contract was awarded on January 19, 2010 and...
- <p>This is a firm fixed-price definitive contract awarded by the International Boundary and Water Commission U.S.-Mexico, a civilian federal agency, to Milestone Excavation Inc., a veteran-owned small business. The contract, valued at $19,058,377.13, is for the RECOVERY - CANUTILLO PHASE 1 LEVEE IMPROVEMENTS project and has a period of performance ending on June 30, 2011. There is no set-aside designation for this contract. The contract was awarded on December 31, 2009.</p>
- <p>This is a $2,911,916.96 firm fixed price contract awarded by the International Boundary and Water Commission U.S.-Mexico, a civilian federal agency, to Tamez-Pearson Construction Inc., a minority-owned, small disadvantaged, woman-owned business, for RECOVERY - MISSION LEVEE IMPROVEMENTS. The contract has a competitive 8(a) set-aside designation and an ultimate completion date of September 18, 2011. This contract does not appear to be associated with a larger contract vehicle.</p>
- <p>This is a $31,767,447.52 firm fixed price contract awarded by the International Boundary and Water Commission U.S.-Mexico, a civilian federal agency, to Lakeshore Engineering Services, Inc. (Lakeshore Group) for the RECOVERY - MESILLA PHASE 1 LEVEE IMPROVEMENTS project. The contract was awarded on December 30, 2009 with a completion date of October 27, 2012. This contract is not associated with a set-aside designation.</p>
- This is a firm fixed-price delivery order awarded by the International Boundary and Water Commission U.S.-Mexico, a civilian agency, to S & B Infrastructure LTD (doing business as S B I) for engineering design services related to the recovery and repairs of an international dam and weir. The award has a ceiling value of $612,066.00 and a completion date of June 9, 2009. The contract is not designated as a set-aside. S & B Infrastructure LTD is the prime contractor, and the award is...
This is a $26,488,498.54 firm fixed-price construction contract awarded by the International Boundary and Water Commission (IBWC) to Sbbi, Inc. (doing business as Sun Belt Builders) for the Recovery - Construction of Lateral A to Retamal Dam River Levee in Hidalgo County, Texas. The contract does not have a set-aside designation and is set to be completed by February 29, 2012.
Generated 4/2/25, 10:18 AM
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
RECOVERY - Construction of the Lateral A to Retamal Dam River Levee in Hidalgo County Texas | IBM09B0009 | International Boundary and Water Commission U.S.-Mexico | Award Notice 1/1 | 5/19/09, 8:13 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00020 | Close Out | ($1k) | 12/27/18 | |
| P00019 | Supplemental Agreement for work within scope | $8.1m | 3/20/18 | |
| M018 | Other Administrative Action | $0 | 9/15/15 | |
| M017 | Supplemental Agreement for work within scope | $1.3k | 9/12/14 | |
| M015 | Change Order | ($198k) | 6/10/14 |