Recovery CMC contract (mainly construction services) for edith green-wendell wyatt federal building modernization, portland, or. Base award is design phase services. Construction phase services are an…

Ended Definitive Contract Awarded Last action

Contract number
GS10P09LTC0052
Awardee
Awarding agency
Obligated
$137,835,857

Award facts

Opportunity
Contract value 100% obligated
$137,835,857.00 Current and potential, with all options
Completion date 100% complete
  • Current, with exercised options
  • Potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 6 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Portland, OR 97204, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out PS38 · Original award, construction project to modernize edith green - wendell wyatt federal building, portland, or. This action closes contract and deobligates… -$60,277
Other Administrative Action PZ06 · Original contract for the construction/modernization of the edith green wendell wyatt federal building, this action extends the period of performance to… $0
Supplemental Agreement for work within scope PS37 · Construction project for modernization of EG-WW federal building, portland, or. This action prices several tenant requested changes. $120,751
Supplemental Agreement for work within scope PS36 · Construction contract to modernize edith green wendell wyatt federal building porland or, this action settles the cost for several tenant changes. $37,767
Other Administrative Action PZ5 · Construction project to modernized edith green - wendell wyatt federal building portland oregon, this action corrects a database input on modification PA35. -$80,000
Other Administrative Action PA35 · Modernize federal building (EG-WW) this action corrects admininstrative error by cancelling modification (PS30) which was never issued. $0
Supplemental Agreement for work within scope PS34 · Construction project to modernize EG-WW federal building this action settles the cost of several tenant requested changes. $110,739
Other Administrative Action PZ4 · Construction contract to modernize EG-WW federal building. This action corrects contract value in database only. $48,202
Funding Only Action PZ3 · Construction contract to modernize EG-WW federal building this MOD corrects funding amount obligated by modification PS31. $293,461
Other Administrative Action PA33 · Construction contract to modernize EG-WW federal building. This action clarified funding obligated on modification PS32. $0
Supplemental Agreement for work within scope PS32 · Modernize EG-WW federal building, this action settles the cost of several tenant changes. $48,202
Supplemental Agreement for work within scope PS31 · Construction contract to modernize EG-WW federal building, this action settles the price increase for adding a tenant buildout to the project scope. $340,493
Change Order PC29 · Modernize federal office building, EG-WW portland oregon, this action obligates design funding for design build subcontract effort for new tenant. $70,305
Change Order PC28 · Modernization of federal building, egww, portland, or. This action deobligaes excess contingency. -$80,000
Supplemental Agreement for work within scope PS27 · Construct edith green wendell wyatt federal building portland oregon. This action evidences the cost of several tenant changes; GFP provided, and buy-american… $21,375
Supplemental Agreement for work within scope PS26 · Modernization of EG-WW federal building, this action settles cost of miscellaneous tenant changes. $431,365
Supplemental Agreement for work within scope PS25 · Construct EG-WW federal building, this modification settles cost of several tenant driven changes. $1,459,858
Supplemental Agreement for work within scope PS24 · Modernize the EG-WW federal building this action settles the cost of changes. $50,000
Supplemental Agreement for work within scope PS22 · Modernization of edithgreen-wendellwyatt federal building, this modification deopligates excess funding. -$61,509
Supplemental Agreement for work within scope PS21 · Construction project to modernize the EG-WW federal building portland oregon, this modification evidences the pricing of various tenant changes. $495,898
Supplemental Agreement for work within scope PS20 · Construct EG-WW federal building, portland, or, this action definitizes cost of several tenant above allowance program cost. $366,792
Supplemental Agreement for work within scope PS19 · Construction contract to modernize EG-WW federal building, this action definitizes the price for tenant security and data cabeling. $715,184
Supplemental Agreement for work within scope PS17 · Modernization of edith green - wendell wyatt federal building, this MOD settles above program construction cost for the shared server room. $1,515,479
Supplemental Agreement for work within scope PS15 · Modernize edith green-wendell wyatt federal building, portland, or, this action definitizes tenant construction changes. $77,982
Supplemental Agreement for work within scope PS16 · Construct EG-WW federal building, this MOD adds above program construction for several tenants. $1,441,108
Supplemental Agreement for work within scope PS18 · Modernize edith green-wendell wyatt federal building, this MOD settles the cost of above program tenant work. $830,919
Supplemental Agreement for work within scope PS13 · Construction to modernize federal building, this action definitizes construction cost for several tenant programs. $239,025
Supplemental Agreement for work within scope PS14 · Modernize federal building, this action definitize cost for tenant above allowance construction. $733,604
Supplemental Agreement for work within scope PS12 · Modernize edith green-wendell wyatt federal building, this action definitizes above program tenant construction. $860,380
Supplemental Agreement for work within scope PS10 $813,007
Supplemental Agreement for work within scope PS11 · Modernize EG-WW federal building, portland, oregon. This action definitizes above allowance tenant program construction. $98,519
Supplemental Agreement for work within scope PS09 · Tenant improvements for opla and USDA $327,958
Supplemental Agreement for work within scope PS08 · The purpose of this modification is to incorporate latent defects and TI designs. $1,015,032
Supplemental Agreement for work within scope PS07 · Egww outbound support $14,771
Change Order PC06 · Perf. Period, NTP, D-B, bonds, tree fund, camera fund $78,150
Change Order PC05 · Modernization of edith green/wendell wyatt federal building in portland oregon. Funding added for additional scope. $782,000
Supplemental Agreement for work within scope PS04 · CM services $62,075
Exercise an Option PS03 · Modernize edith green wendell wyatt federal building portland oregon. Exercise modification for construction phase services. $1,465,589
Supplemental Agreement for work within scope PS02 · Recovery act project, modernize edith green-wendell wyatt federal building, portland oregon. This modification incorporates a project labor agreement. $0
Exercise an Option PS01 · Establish GMP $122,034,411
Original award $1,117,242
Show all 41

About this award

This is a federal contract awarded by the General Services Administration (GSA) Region 10 to the Howard S. Wright Companies Oregon Joint Venture. The contract, valued at $137,835,857.00, is for the design phase services of the Edith Green-Wendell Wyatt Federal Building Modernization project in Portland, Oregon. The contract is a definitive, firm-fixed-price contract and does not have a set-aside designation. The contract includes an unpriced option for the construction phase services of the project.

Description

Recovery CMC contract (mainly construction services) for edith green-wendell wyatt federal building modernization, portland, or. Base award is design phase services. Construction phase services are an unpriced option.

Quick answers

Who was awarded contract GS10P09LTC0052?

GS10P09LTC0052 was awarded to Howard S Wright Companies Oregon Joint Venture by Region 10 (Public Buildings Service) on December 11, 2009.

How much is contract GS10P09LTC0052 worth?

The government has obligated $137,835,857 on GS10P09LTC0052.

Was contract GS10P09LTC0052 competed?

The extent of competition for GS10P09LTC0052 was full and open competition. The government received 6 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award