CMC design phase services with bilateral construction option for peace arch POE redevelopment, blaine, WA

Ended Definitive Contract Awarded Last action

Contract number
GS10P06LTC3022
Awardee
Awarding agency
Obligated
$88,681,145

Award facts

Opportunity
Contract value 97% obligated
$91,681,336.95 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 1 offer Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Blaine, WA, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Funding Only Action PZ36 · Administrative funding change only -$33
Close Out PS35 · Construct peace arch border station, this modification evidences final contract closeout and savings realized. -$688,734
Other Administrative Action PA34 · Construct new border station at blaine washington, this MOD extends period of performance to facilate administrative contract close out functions only. Contract… $0
Other Administrative Action PZ4 · Construct new border station blain washington, this action extends period of performance to facilitate admininstrative closeout actions only. $0
Other Administrative Action PA33 · Original contract for construction of new land point of entry, peace arch, modification deobligates excess funding. -$1,500,000
Other Administrative Action PZ33 · Construct new border station blaine washington, modification correct database entry error. $0
Other Administrative Action PA32 · Construct new border station blain washington, modification to deobligate excess funding pending official contract closeout. -$3,000,000
Other Administrative Action PA31 · Construct new port of entry blain washington administrative MOD to extend performance period to conduct contract closeout activities only $0
Other Administrative Action PA30 · Construct border station, blaine washington, this MOD corrects accounting data on modification PS25 $0
Other Administrative Action PA29 · Construct new border station blaine washington, this MOD corrects an error in accounting data. $0
Novation Agreement PS27 · Change name and address of construction contractor for the new peace arch border station project. $0
Supplemental Agreement for work within scope PS26 · Modify construction contract to build new peace arch border station to include tenant traffic changes. $29,791
Definitize Change Order PS25 · Construct new peace arch border station, modification to definitize cost of various changes. $626,170
Other Administrative Action PA24 · Construct new boader station at blaine washington. This change corrects financial data on previous MOD. $0
Definitize Change Order PS23 · Add tenant work to construction of new port facility. $1,407,136
Other Administrative Action PA21 · Construct new border station, this MOD corrects GSA accounting system data. $0
Other Administrative Action PA20 · Corrects obligation data. $0
Other Administrative Action PA19 · Corrects funding code error $0
Other Administrative Action PA18 · Correct error in prior accounting data $0
Other Administrative Action PZ02 · Recovery. This administrative modification is issued to add the recovery account codes to the contract line item associated with modification PS15. This… $0
Other Administrative Action PA17 · Construct peace arch border station, administrative MOD to correct PS16 $0
Funding Only Action PS16 · New lpoe blain washington -$1,598,234
Exercise an Option PS15 · Obligates arra funding (in response to escalation request) fully funding the guaranteed maximum price (GMP) for construction of the new peace arch POE.… $26,284,708
Change Order PS14 $388,329
Other Administrative Action PA13 $0
Supplemental Agreement for work within scope PS12 $26,098,091
Supplemental Agreement for work within scope PS10 $1,671,452
Supplemental Agreement for work within scope PS11 $1,840,499
Supplemental Agreement for work within scope PS06 $10,539,688
Supplemental Agreement for work within scope PS07 $44,210
Supplemental Agreement for work within scope PS08 $68,741
Supplemental Agreement for work within scope PS09 $504,379
Additional Work (new agreement, FAR part 6 applies) PS05 $98,166
Other Administrative Action PZ01 $799,802
Supplemental Agreement for work within scope PS04 $21,827,227
Additional Work (new agreement, FAR part 6 applies) PS02 $100,000
Supplemental Agreement for work within scope PS03 $2,030,779
Supplemental Agreement for work within scope PS01 $799,802
Original award $309,176
Show all 39

About this award

This is a definitive contract awarded by the General Services Administration (GSA) Region 10 to J.E. Dunn Construction Company, a family and employee-owned commercial construction firm, for $91,681,336.95. The contract is for the design phase services and bilateral construction option for the Peace Arch Port of Entry (POE) Redevelopment project in Blaine, Washington. The contract has a firm fixed price pricing type and does not have a set-aside designation. J.E. Dunn Construction Company has extensive experience as a prime contractor on major federal construction projects for agencies such as the Department of Defense and Department of the Air Force. This contract award is not associated with a larger contract vehicle.

Quick answers

Who was awarded contract GS10P06LTC3022?

GS10P06LTC3022 was awarded to J.e. Dunn Construction Company by Region 10 (Public Buildings Service) on March 14, 2007.

How much is contract GS10P06LTC3022 worth?

The government has obligated $88,681,145 on GS10P06LTC3022. Its current value, with exercised options, is $91,681,337.

Was contract GS10P06LTC3022 competed?

The extent of competition for GS10P06LTC3022 was full and open competition. The government received 1 offer.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award