Arra new custom house modernization project, denver CO

Ended Definitive Contract Awarded Last action

Contract number
GS08P10JBC0007
Awardee
Awarding agency
Obligated
$40,496,684

Award facts

Opportunity
Contract value 100% obligated
  • $40,496,683.97 Current, with exercised options
  • $40,496,684.46 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
Competitive 8(a)
Competition
Full and Open Competition after exclusion of sources · 11 offers Two Step
Pricing
Firm Fixed Price
Place of performance
Denver, CO 80202, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action PC87 · DE-obligate remaining balance for close out -$14,008
Supplemental Agreement for work within scope PS86 · DE-obligate remaining RWA funds from contract. -$112,570
Supplemental Agreement for work within scope PS85 · Additional meps TI work $17,504
Supplemental Agreement for work within scope PS84 · TI work $56,696
Supplemental Agreement for work within scope PS81 · Arra: DE-obligate remaining arra funds from contract as a result of DE-scoping and cost efficiencies -$209,508
Supplemental Agreement for work within scope PS82 · No cost modification to reconcile changes to attic stock quanties $0
Supplemental Agreement for work within scope PS83 · Modification to add boiler screen gate for maintenance access $759
Supplemental Agreement for work within scope PS80 · Tenant improvements and time extension for meps 2ND floor $126,240
Supplemental Agreement for work within scope PS79 · No cost modification to reconcile changes in scope for work that awarded in PS72 and PS73 $0
Supplemental Agreement for work within scope PS78 · Tenant improvements for 2ND floor, meps $69,279
Supplemental Agreement for work within scope PS76 · Adding zone paging to tenant area $13,008
Change Order PS75 · Additional work needed for assurance of heating as of OCT 1, 2013 $4,902
Supplemental Agreement for work within scope PS74 · Unforseen site condition, trench found during construction. $1,085
Additional Work (new agreement, FAR part 6 applies) PS73 · Phase II of the installation of a high efficiency condensing boiler system $308,197
Supplemental Agreement for work within scope PS72 · Phase I of the installation of a high efficiency contdensing boiler system $970,000
Supplemental Agreement for work within scope PS69 · Arra funded: credits from arra portions of the project applied to differing site conditions for arra project at NCH $0
Additional Work (new agreement, FAR part 6 applies) PS70 · DE-scope of data cabling requirements for U.S.B.C. -$3,900
Additional Work (new agreement, FAR part 6 applies) PS71 · DE-scope of previously awarded tenant improvements for U.S.B.C. -$9,184
Supplemental Agreement for work within scope PS68 · Tenant improvements and carpet installation $11,300
Supplemental Agreement for work within scope PS67 · Non arra funded: agency tenant improvement project $1,520,062
Other Administrative Action PA66 · Arra budget action funds transfer $0
Other Administrative Action PA65 · There was an error in PA64 and this MOD corrects. No change in contract price or terms and conditions $0
Other Administrative Action PA64 · Clin 0074 incorrect ADN change from PJ0I00036 to PN0I00385 $0
Supplemental Agreement for work within scope PS63 · Non-arra funded: blast wall upgrade proposal to provide exterior blast doors enhancing security for the whole blast upgrade project. $62,532
Supplemental Agreement for work within scope PS61 · Arra funded: repair 1ST and 2ND subfloors and extend POP and subsequent GCS $397,056
Other Administrative Action PA62 · Arra funded: administrative correction to funding string $0
Definitize Change Order PS60 · Arra funded: modification to descope photo voltaics in its entirety and definitize remaining amount of CLIN22 for unforseen site conditions discovered during… $0
Supplemental Agreement for work within scope PS59 · Non arra funded TI improvements $10,775
Supplemental Agreement for work within scope PS58 · Non arra panic bar installation for custom doors $547
Supplemental Agreement for work within scope PS57 · Non arra funded: 3RD & 4TH level improvements to historical corridors. This change also resulted in a time extension. $102,502
Supplemental Agreement for work within scope PS56 · Non arra funded SBA tenant improvements $38,433
Supplemental Agreement for work within scope PS55 · Non arra funded: refurbish door and window frames for the 3RD floor agency SBA $7,243
Supplemental Agreement for work within scope PS54 · Non arra funded: tenant initiated improvement to office space $4,505
Supplemental Agreement for work within scope PS53 · Non arra funded: historic door hardware repair $9,997
Supplemental Agreement for work within scope PS52 · Non arra funded: installation of a fence for a temporary playground area during the construction of the permanent playground $9,990
Definitize Change Order PS51 · Arra funded: definitize photovoltaics line item. PV descoped to all for unforseen site conditions during project in the amount of $200,371.00. $0
Supplemental Agreement for work within scope PS50 · Non arra funded: flat plate balancing study $22,215
Supplemental Agreement for work within scope PS49 · Non arra funded: improvement to the corridor for historic significance $77,997
Supplemental Agreement for work within scope PS48 · Non-arra funded: modification for tenant improvements for 4TH floor, SBA office $24,953
Supplemental Agreement for work within scope PS47 · Additional SOW to repaint the soffitt with historical colors. $3,261
Supplemental Agreement for work within scope PS46 · Increase in SOW from tenant. Adding carpet and base to space renovation. $30,052
Supplemental Agreement for work within scope PS45 · Tenant improvements to their lease space to be done while they are in their swing space during construction. $3,716
Other Administrative Action PA44 · Received a duplicate requisition number and inadvertently duplicated modification PS37. This will delete modification PS42 and correct the action. -$6,624
Supplemental Agreement for work within scope PS43 · Non arra funded modification to add historic renovation to two rooms on the 4TH floor to the project. $34,986
Supplemental Agreement for work within scope PS41 · Fire sprinklers on 5TH floor were in need of repair, this modification addresses changes needed to bring the sprinkler system up to code. $4,361
Supplemental Agreement for work within scope PS42 · The purpose of this modification is to do repairs so that we shall meet the fire rating for the 4TH and 5TH floor stairwell. $6,624
Supplemental Agreement for work within scope PS40 · Waiver to the arra buy american requirements to allow contractor to purchase flush valves from the republic of china. Flush valves are not manufactured… $0
Supplemental Agreement for work within scope PS39 · Non arra funded action to replace electrical receptacles and cover plates on the 4TH floor $9,611
Supplemental Agreement for work within scope PS38 · Arra contract to extend period of performance for 54 days. Contract was DE-scoped and the resulting credit was applied to asbestos removal (unforseen site… $0
Supplemental Agreement for work within scope PS36 · Non arra funded: restore the picture rail to meet historical criteria $3,496
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

This is a firm fixed-price, definitive contract awarded by the U.S. General Services Administration (GSA) Region 8 to Matsuo Engineering Centerre Construction A Joint Venture, a minority-owned limited liability company, for the ARRA NEW CUSTOM HOUSE MODERNIZATION PROJECT in Denver, Colorado. The $40,496,684.46 contract was set aside for competitive 8(a) firms and has an ultimate completion date of April 21, 2018. As this is a modernization project, the contract likely involves construction, renovation, or other building improvement services, though the specific products or services were not provided in the information given.

Quick answers

Who was awarded contract GS08P10JBC0007?

GS08P10JBC0007 was awarded to Matsuo Engineering Centerre Construction A Joint Venture by Region 8 (Public Buildings Service) on March 19, 2010.

How much is contract GS08P10JBC0007 worth?

The government has obligated $40,496,684 on GS08P10JBC0007. Its potential value, with all options, is $40,496,684.

Was contract GS08P10JBC0007 competed?

The extent of competition for GS08P10JBC0007 was full and open competition after exclusion of sources. The government received 11 offers. It was set aside: Competitive 8(a).

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award