Construction manager as agent (CMA) services for the facade repair and slate roof replacement for the U.S. Post office and courthouse at 271 cadman plaza, east, brooklyn, NY

Ended Definitive Contract Awarded Last action

Contract number
GS02P07DTC0009
Awardee
Awarding agency
Obligated
$8,412,569

Award facts

Contract value 100% obligated
$8,412,568.77 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 17 offers Architect-Engineer FAR 6.102
Pricing
Firm Fixed Price
Place of performance
Brooklyn Heights, NY 11201, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS16 · Modification no. PS16 is hereby issued for credit for controlled inspections for the agreed to amount of ($312,118.65) for the facade repair & slate roof… -$312,119
Supplemental Agreement for work within scope PS15 · Modification no. PS15 is hereby issued to decrease ($89,074.69) for constrolled inspection services and increase $89,074.69 for additional commissioning… $0
Change Order PS14 · Modification no. PS14 is hereby issued for item NOS. 1 through 3 for the facade repair and slate roof replacement at the U.S. Post office & courthouse at 271… -$6,727
Supplemental Agreement for work within scope PS13 · Modification no. PS13 is hereby issued for lend lease office relocation for the negotiated amount of $ 17,478.24 for the CMA services for the facade repair &… $17,478
Other Administrative Action PA12 · Modification no. PA12 is hereby issued to incorporate TH terms and conditions of the "change of name agreement" which changes your company name from bovis… $0
Supplemental Agreement for work within scope PS11 · Recovery act: modification no. PS11 is hereby issued for additional commissioning services for june 2011 for the negotiated amount of $ 171,124.71 for the CMA… $171,125
Other Administrative Action PA07 · This modification is issued to correct the accounting string for modification numbers PS07 and PS08 to reflect the arra funding in the accounting… $0
Supplemental Agreement for work within scope PS10 · Recovery act: modification no. PS10 is hereby issued for the negotiated amount of $ 42,095.26 for travel expenses and personnel changes for the CMA services for… $42,095
Supplemental Agreement for work within scope PS09 · Recovery act: modification no. PS09 is hereby issued for the negotiated amount of $ 44,913.17 for the additional air monitoring and environmental testing for… $44,913
Change Order PS07 · Recovery act: modification no. PS07 was issued for CMA commissioning data base and GSA electronic project management (EPM) for the negotiated amount of… -$6,141
Change Order PS08 · Recovery act: modification no. PS08 is hereby issued for replacement of terra cotta ashlers at piers for the negotiated amount of $422,298.09 for the CMA… $422,298
Change Order PS06 · Recovery act: modification no. PS06 is hereby for additional services for controlled inspection option 1 -construction management phase for the negotiated… $653,365
Change Order PS05 · Recovery act: modification no. PS05 is hereby issued for additional services to option 1 - construction management phase for the negotiated amount of $… $2,811,668
Supplemental Agreement for work within scope PS04 · Recovery act: PS04 was issued to procure and maintain a secure (128-bit encrypted) web-based electronic project management (EPM) system for the negotiated… $66,406
Exercise an Option PS03 · Recovery act: PS03 was issued to exercised option 1 construction management phase for the negotiated amount of $ 3,788,089.09 for the CMA services for the FA… $3,788,089
Other Administrative Action PS01 · Recovery act: MOD. PS01 was issued to incorporate the american recovery and reinvestment act (ARRA) of 2009 clauses to contract no. GS-02P-07-DTC-0009 for the… $0
Supplemental Agreement for work within scope PS02 · Recovery act: MOD. PS02 is hereby issued to: (1) credit for final construction document phase for the negotiated amount of ($15,761.21); (2) escalation for 100%… $53,419
Original award $666,699
Show all 18

About this award

This is a federal contract awarded by the U.S. General Services Administration (GSA) to Lendlease (Us) Construction LMB Inc. for $8,412,568.77 to provide construction manager as agent (CMA) services for facade repair and slate roof replacement at the U.S. Post Office and Courthouse in Brooklyn, New York. The contract is a definitive contract with a firm fixed price. The work is to be completed by March 15, 2015. The contract does not have a set-aside designation.

Quick answers

Who was awarded contract GS02P07DTC0009?

GS02P07DTC0009 was awarded to Lendlease (Us) Construction LMB Inc. by Region 2 (Public Buildings Service) on November 7, 2007.

How much is contract GS02P07DTC0009 worth?

The government has obligated $8,412,569 on GS02P07DTC0009.

Was contract GS02P07DTC0009 competed?

The extent of competition for GS02P07DTC0009 was full and open competition. The government received 17 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award