Construction management services for the modernization of the peter rodino federal building, newark, NJ

Ended Definitive Contract Awarded Last action

Contract number
GS02P04DTC0048
Awardee
Awarding agency
Obligated
$10,559,563

Award facts

Contract value 100% obligated
$10,559,563.14 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 10 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Newark, NJ 07102, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Additional Work (new agreement, FAR part 6 applies) PS44 · Modification no. PS44 is hereby issued to extend the contract completion date from july 1, 2017 to september 30, 2017 at no additional cost to the government… $0
Vendor DUNS or Name Change - Non-Novation AS43 · Modification no. PA43 is hereby issued to incorporate the terms and conditions of the attached "change of name agreement" which changes your company name from… $0
Supplemental Agreement for work within scope PS42 · Modification no, PS42 is hereby issued to extend the construction management services from april 1, 2017 to june 30, 2017 for the negotiated amount of… $141,027
Supplemental Agreement for work within scope PS41 · Modification no, PS41 is hereby issued to provide commissioning services for the negotiated amount of $15,568.00 for the peter W. Rodino federal office building… $15,568
Supplemental Agreement for work within scope PS40 · Modification no. PS40 is hereby issued for additional services for the negotiated amount of $563,772.23 for the peter rodino federal office building at 970… $563,772
Other Administrative Action PA39 · Modification no. PA39 to extend to 6/2016 for comprizon only! $0
Supplemental Agreement for work within scope PS38 · Modification no. PS38 is hereby issued for the negotiated amount of $23,591.65 to extend CM services for the vestibule at 970 broad street, newark, NJ.… $23,592
Supplemental Agreement for work within scope PS39 · Modification no. PS39 is hereby issued for the negotiated amount of $94,366.59 to extend CM services for the vestibule at 970 broad street, newark, NJ.… $94,367
Supplemental Agreement for work within scope PS37 · Modification no. PS37 is hereby issued to provide the estimate for the vestibule and first floor HVAC upgrade as described in the scope of work dated december… $0
Supplemental Agreement for work within scope PS36 · Modification no. PS36 is hereby issued to change personnel as described in the scope of work dated november 21, 2014 at no additional cost to the government for… $0
Supplemental Agreement for work within scope PS35 · Modification no. PS35 is hereby issued for the negotiated amount of $34,584.50 to provide staff extension and parking as stated in the scope of work dated… $34,585
Supplemental Agreement for work within scope PS33 · Modification no. PS33 is hereby issued for the negotiated amount of $26,449.50 to provide extension of services as described in the scope of work dated august… $26,450
Supplemental Agreement for work within scope PS34 · Modification no. PS34 is hereby issued for the agreed amount of $88,424.00 to provide HVAC study as described in the attached scope of work dated september… $88,424
Supplemental Agreement for work within scope PS32 · Modification no. PS32 is hereby issued for a credit amount of of ($54,659.00) to provide additional commissioning services, delete modification no. PS26, and… -$54,659
Supplemental Agreement for work within scope PS31 · Modification no. PS31 is hereby issued to replace the hours of senior project manager "david porsolt" for the period of january through march 2014 with the… $0
Supplemental Agreement for work within scope PS30 · Modification no. PS30 is hereby issued in the negotiated amount of $ 1,271,055.00 for extended CM services as described in the scope of work (dated november… $1,271,055
Supplemental Agreement for work within scope PS29 · Modification no. 29 is hereby issued at no additional cost to the government for additional senior project manager services and credit salary difference between… $0
Supplemental Agreement for work within scope PS28 · Modification no. 28 is hereby issued to for the negotiated amount of $ 113,470.00 to provide extension services as described in the attached scope of work dated… $113,470
Supplemental Agreement for work within scope PS27 · Modification no. PS27 changes lend lease project manager from david porsolt to justin white at an hourly rate of $70.02 at no additional cost to the… $0
Change Order PS25 · Modification no. PS25 is hereby issued for the negotiated amount of $ 345,595.13 for construction management services to provide extension services as described… $345,595
Change Order PS24 · Modification no. PS24 is hereby issued in the negotiated amount of $ 216,704.00 to provide the escalated effort for the original contract for options 1, 2, 3B… $216,704
Change Order PS26 · Modification no. PS26 is hereby issued for the negotiated amoumt of $ 56,296.24 for additional testing services as described in the scope of work dated december… $56,296
Supplemental Agreement for work within scope PS23 · Modification no. PS23 is hereby issued for the negotiated amount of $ 56,000.00 to provide IT consultant services for the peter W. Rodino federal building at… $56,000
Supplemental Agreement for work within scope PS22 · Modification no. PS22 is hereby issued for the negotiated amount of $ 50,943.20 to provide additional commissioning of variable air volume units (VAVS) and… $50,943
Supplemental Agreement for work within scope PS21 · Modification no. PS21 is hereby issued for the negotiated amount of $ 89,000.80 for engineering services to apply for the new jersey pay for performance (P4P)… $89,001
Novation Agreement PA20 · Modificsation no. PA20 is hereby issued to incorporate the terms and conditions of the "change of name agreement" which changes the company name from bovis lend… $0
Supplemental Agreement for work within scope PS19 · Modification no. PS19 is hereby issued to provide weekend superintendent and technical services review of structural overclad alternative for the negotiated… $45,687
Change Order PC18 · TAS: 47 4543::TAS recovery act: unilateral modification no. PC18 is hereby issued to adjust modification NOS. PS09 by ($2,768.00) and PS14 by ($410,983.00)… -$408,215
Supplemental Agreement for work within scope PS16 · Recovery act: modification no. PS16 is hereby issued for testing and inspection services for the negotiated amount of $ 175,612.64 for the peter W. Rodino… $175,613
Supplemental Agreement for work within scope PS15 · Recovery act: modification no. PS15 is hereby issued for additional second shift services for the negotiated amount of $ 159,111.60 for the peter W. Rodino… $159,112
Definitize Change Order PS13 · Recovery act: modification no. PS13 is hereby issued to definitized PDL#1 under modification no. 12 for the negotiated amount of $ 10,164.70 for the asbestos… $2,181
Exercise an Option PS14 · Recovery act: modification no. PS14 is hereby issued to exercise the following options: 1) option 1: design/build design phase for the negotiated amount of $… $6,427,119
Change Order PC12 · Recovery act: PDL# 1 under modification no. PC12 is issued immediately proceed with the feasibility study regarding project labor agreement for the not exceed… $7,984
Supplemental Agreement for work within scope PS10 · Recovery act: modification no. PS10 was issued to incorporate and exercise option 3A for the commissioning services (bridging design phase) for the negotiated… $27,200
Supplemental Agreement for work within scope PS09 · Recovery act: PS09 was issued to revised the scope of services for bridging/design-build for the negotiated amount of $ 506,839.00 for the construction… $506,839
Supplemental Agreement for work within scope PS08 · PS08 is hereby issued to redefine the necessary services for the final concept desigh phase for the negotiated amount of $192,362.00 for the construction… -$165,007
Supplemental Agreement for work within scope PS07 · PS07 was issued for the negotiated amount of $ 373.44 to cover the other direct costs under MOD PS06 for curtain wall market research for the construction… $373
Supplemental Agreement for work within scope PS05 · Modificaiton no. PS05 is hereby issued for the negotiated amount of $ 8,190.00 for curtain wall market research for the construction management services for the… $8,190
Other Administrative Action PS06 · Recovery act: MOD. PS06 was issued to incorporate the american recovery and reinvestment act (ARRA) of 2009 clauses to contract no. GS-02P-04-DTC-0048 for the… $0
Supplemental Agreement for work within scope PS04 · MOD PS04 for reprogramming phase for the construction management services for the asbestos/abatement/modernization of the peter W. Rodino FOB at newark, new… $69,556
Other Administrative Action AC03 $0
Change Order PS02 $74,904
Other Administrative Action AC01 $0
Original award $495,839
Show all 44

About this award

This is a $10,559,563.14 fixed-price construction management services contract awarded by the General Services Administration (GSA) to Lendlease (Us) Construction Inc., a foreign-owned, for-profit construction services company. The contract is for construction management services to modernize the Peter Rodino Federal Building in Newark, New Jersey. The award does not have a set-aside designation. Lendlease has established itself as a key contractor for complex, culturally sensitive renovation and infrastructure projects for federal agencies, particularly the Smithsonian Institution, where it holds a single-award Indefinite Delivery Contract for construction management, facilities services, and project management support.

Quick answers

Who was awarded contract GS02P04DTC0048?

GS02P04DTC0048 was awarded to Lendlease (Us) Construction Inc. by Region 2 (Public Buildings Service) on October 5, 2005.

How much is contract GS02P04DTC0048 worth?

The government has obligated $10,559,563 on GS02P04DTC0048.

Was contract GS02P04DTC0048 competed?

The extent of competition for GS02P04DTC0048 was full and open competition. The government received 10 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award