Recovery modernization of IRS andover service center in andover, MA

Ended Definitive Contract Awarded Last action

Contract number
GS01P09BZC0014
Awardee
Awarding agency
Obligated
$97,828,262

Award facts

Opportunity
Contract value 100% obligated
  • $97,870,873.00 Current, with exercised options
  • $98,170,873.00 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 5 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Andover, MA 01810, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PSQ7 · This modification takes a credit for the carpet stock that can no longer be replaced by the contractor for the modernization, IRS service center, andover, MA. -$24,250
Supplemental Agreement for work within scope PSQ6 · This modification is for the settlement REA for columbia, griffin electric INC., h.carr & SON's INC and limbach company at the modernization, IRS service… $2,138,631
Supplemental Agreement for work within scope PSQ5 · The modification is for east roadway drainage and art in architecture plaques for the modernization IRS service center, andover, MA $13,241
Supplemental Agreement for work within scope PSQ4 · This modification includes work such as phase 1 bathroon countertops, power to water heater and remote for MMC curtains for the modernization at the IRS service… $66,522
Supplemental Agreement for work within scope PSQ3 · This modification resolves outstanding REA's for the modernization at the IRS service center, andover, MA $411,257
Supplemental Agreement for work within scope PSQ2 · This modification consists of RFP# 527 substation heater repair and conical light removal for the modernization at the IRS service center, andover, MA. $5,298
Supplemental Agreement for work within scope PCQ1 · This modification deletes HVAC afms work not installed AAT the modernization IRS service center, andover, MA -$60,000
Supplemental Agreement for work within scope PSP9 · This modificatio adds the south lobby breaker shutdown, lightening protection and floor fix for the modernization at the IRS service center, andover, MA $56,210
Supplemental Agreement for work within scope PSP8 · This modification is for CUH 3POWER fix and blast door circuitry fix at the modernization of the IRS service center, andover, MA. $0
Supplemental Agreement for work within scope PSP7 · This modification is for BMS programming changes for the modernization at the IRS service center, andover, MA $0
Supplemental Agreement for work within scope PSP6 · This modification provides the necessary program changes to the BMS system for the IRS modernization, IRS service center, andover, MA $0
Supplemental Agreement for work within scope PSP5 · This modification is for south lobby HVAC modifications at the IRS service center, andover, MA $493,000
Supplemental Agreement for work within scope PSP4 · This modification is to provide a new air flow monitoring station for air handeling unit #1 for the modernization, at the IRS service center, andover, MA $0
Supplemental Agreement for work within scope PSP3 · This modification is to repair a leaky seal and non-slip bega fixture lenses for the modernization, IRS service center, andover, MA $0
Supplemental Agreement for work within scope PSP2 · This modification consists of lincoln's REA for the modernization at the IRS service center, andover, MA $200,686
Supplemental Agreement for work within scope PSP1 · This modification consists of griffin REA for additional furniture wiring for phase 1 at the modernization at the IRS service center, andover, MA $54,664
Supplemental Agreement for work within scope PSN9 · This modification deobligates mony that is no longer needed in this contract -$17,992
Supplemental Agreement for work within scope PSN8 · This modification definitizes this NTE amount for the modernization, IRS service center, andover, MA $0
Supplemental Agreement for work within scope PSN7 · This modification is for the NER REA for the modernization at the IRS service center, andover, MA $7,559
Supplemental Agreement for work within scope PSN6 · This modification includes work related to an alternate hydraulic security barriers, tigta deadbolts locks, lifesaftey issues and duggan REA at the… $43,751
Supplemental Agreement for work within scope PSN5 · This modification provides a credit for work no longer needed for the skylight shades at the modernization of the IRS service center, andover, MA. -$5,061
Supplemental Agreement for work within scope PSN4 · This modification is for the work related to east roadway lights and relocation of spring air control panel for the modernization, IRS service center,… $0
Supplemental Agreement for work within scope PSN3 · This work consists of correcting IDF ductwork room 1123 at the modernization, IRS service center, andover, MA $0
Supplemental Agreement for work within scope PSN2 · This modification is to definitize this modification and include the childcare fire alarm class a upgrade for the modernization, IRS service center, andover, MA $0
Supplemental Agreement for work within scope PSN1 · This modification extends the contract completion date to june 5, 2014 for the modernization of the IRS service center, andover, MA $0
Supplemental Agreement for work within scope PSM9 · This modification is for the REA for frontline at the modernization, IRS service center, andover, MA. $0
Supplemental Agreement for work within scope PSM8 · This modification replaces the tigta locks with deadbolts for the modernization at the IRS service center, andover, MA. $0
Supplemental Agreement for work within scope PSM7 · Recovery this modification is for the flagpole repair and winch replacement for the modernization at the IRS service center, andover, MA $0
Supplemental Agreement for work within scope PSM6 · This modification is for the REA for exterior security camera for griffin electric costs at the modernization at the IRS service center, andover, MA. $0
Supplemental Agreement for work within scope PSM5 · This modification consists of an REA for the subcontractor quinn brothers for the modernization at the IRS service center, andover, MA $0
Supplemental Agreement for work within scope PSM4 · This modification partially defines PSL2 to include REA for DB contractors for the modernization at IRS service center, andover, MA. $0
Supplemental Agreement for work within scope PSM3 · This modification is to extend the contract completion date to august 30, 2013. $0
Supplemental Agreement for work within scope PSM2 · This modification defines the NTE for the associated REA for the modernization at the IRS service center, andover, MA. $0
Supplemental Agreement for work within scope PSM1 · This work consists of a path of return air AHU-11 for the modernization at the IRS service center, andover, MA $0
Supplemental Agreement for work within scope PSL9 · This modification definitizes NTE MOD PSK9 in final for the modification of IRS service center, andover, MA. $0
Supplemental Agreement for work within scope PSL8 · This modification defines a part of MOD PSL4 for the modernization of IRS service center, andover, MA $0
Supplemental Agreement for work within scope PSL7 · This modification decreases the NTE PSL4, and partially definitizes this line item for duct detector inthe childcare center, electrical distribution power,… $0
Supplemental Agreement for work within scope PSL6 · Bilateral modification to 1.) IRS temporary walls demolition, removing temp amenities and security offices walls, shipping office and corridor in accordance… $72,669
Supplemental Agreement for work within scope PSL5 · This modification descopes the electrical portion for some of the furniture in phase 2 and provides a credit to the contract for the modernization at the IRS… -$135,000
Supplemental Agreement for work within scope PSL4 · This modification defines a part of the REA for the modernization at the IRS service center, andover, MA $0
Supplemental Agreement for work within scope PSL3 · This work consists of summer garden area revisions and skylight shades fabric mock up at the modernization of the IRS service center, andover, MA $87,917
Supplemental Agreement for work within scope PSL1 · This work consists of removing tree along north roadway, exterior wall patching and sector h drain clog repair for the modernization at the IRS service… $43,251
Change Order PSL2 · This change order is to provide all work related to extended conditions for general contractor and sub contractor as a result of geothermal time extension and… $960,754
Change Order PSK9 · This work consists of revised steel, floor framing, support center channel, tigta power, wall type, receptacles at CMU, summer garden grate detail, power for… $97,073
Supplemental Agreement for work within scope PSK7 · This work consists of light fixtures above summer garden canteen and DAC indoor and outdoor unit for the modernization at the IRS service center, andover, MA. $6,691
Supplemental Agreement for work within scope PSK8 · This work is to replace the preschool playground slide and drill weeps at the toddler room door for the modernization at the IRS service center, andover, MA. $4,138
Supplemental Agreement for work within scope PSK6 · This work consists of installing shim plates at phase 2 penthouse doors and correcting the wiring of the access door, lintel at door 14K, surface mounted… $4,523
Supplemental Agreement for work within scope PSK2 · This modification definitizes PC81 with the following work, asbestos extras VAT in temp corridor and CU mastic foundation at area drains, ACM foundation at CU… -$10,021
Supplemental Agreement for work within scope PSK3 · This MOD definitizes PC84 and includes steel lintel above door and siesmic reinforcement details for the modernization at the IRS service center, andover, MA -$72,099
Supplemental Agreement for work within scope PSK4 · This work consists of phase 2 AHU internal lights, alternative for roof structures at computer room, east mechanical room ceiling, summer garden equipment… $318,610
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

This is a definitive, firm-fixed-price contract awarded by the General Services Administration (GSA) to Columbia Construction Co. for the recovery modernization of the Internal Revenue Service (IRS) Andover Service Center in Andover, Massachusetts. The contract has a ceiling value of $98,170,873.00 and a completion date of September 30, 2015. The contract was not set aside for any particular business category. As a civilian agency contract, this work is likely part of the IRS's broader efforts to modernize and maintain its facilities and infrastructure.

Quick answers

Who was awarded contract GS01P09BZC0014?

GS01P09BZC0014 was awarded to Columbia Construction Co by Region 1 (Public Buildings Service) on July 21, 2009.

How much is contract GS01P09BZC0014 worth?

The government has obligated $97,828,262 on GS01P09BZC0014. Its current value, with exercised options, is $97,870,873. Its potential value, with all options, is $98,170,873.

Was contract GS01P09BZC0014 competed?

The extent of competition for GS01P09BZC0014 was full and open competition. The government received 5 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award