Furnish all plant, labor, equipment and materials and perform all work for installing and constructing improvements on the corporation's gatelifter barge.

Ended Definitive Contract Awarded Last action

Contract number
DTSL5511CC0941
Awardee
Awarding agency
Obligated
$1,552,061

Award facts

Opportunity
Contract value 100% obligated
$1,552,061.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
238990 All Other Specialty Trade Contractors
PSC
J019 Maint/Repair/Rebuild Of Equipment- Ships, Small Craft, Pontoons, And Floating Docks
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 1 offer Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Massena, NY 13662, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out 14 · Close out. $0
Supplemental Agreement for work within scope 13 · Modified to extend the project completion date. $0
Other Administrative Action 11 · Extend project completion date to september 18, 2013 $0
Supplemental Agreement for work within scope 10 · Modified to extend the project completion date. $0
Supplemental Agreement for work within scope 9 · Decrease modification no. 5 to the contract for changes to the reducer for the bilge pump. -$1,636
Supplemental Agreement for work within scope 8 · Extend project completion date to 1/15/13 to accommodate anticipated delivery dates of materials and complete installation of equipment. $0
Supplemental Agreement for work within scope 7 · Additional work to upsize the hydraquip actuators. $19,294
Supplemental Agreement for work within scope 6 · Additional work to remove the existing potable water pump/tank assembly and replace IT with a flotec model FP401215H assembly. $1,322
Supplemental Agreement for work within scope 5 · Furnish and install 10" elbow, flange, and pipe for the ballast pump discharge. $2,372
Supplemental Agreement for work within scope 4 · Additional work to remove and abate asbestos found in the gate lifter bathroom floor. $8,812
Supplemental Agreement for work within scope 3 · Acceptance of change orders to perform asbestos abatement and air monitoring; furnish 2 parker cylinders; and credit for owner requested changes to the winch… -$26,484
Supplemental Agreement for work within scope 2 · Additional work to add a 12 inch clean out hatch to the sewage tank and to install a ragulator and upgrade system air compressor drainage system. $2,747
Supplemental Agreement for work within scope 1 · Additional work to widen an existing walkway and install a new walkway in the corporation gatelifter. $5,096
Original award $1,540,538
Show all 14

Quick answers

Who was awarded contract DTSL5511CC0941?

DTSL5511CC0941 was awarded to Continental Construction LLC by Saint Lawrence Seaway Development Corporation (Department of Transportation) on September 30, 2011.

How much is contract DTSL5511CC0941 worth?

The government has obligated $1,552,061 on DTSL5511CC0941.

Was contract DTSL5511CC0941 competed?

The extent of competition for DTSL5511CC0941 was full and open competition after exclusion of sources. The government received 1 offer. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award