Shreveport JCC project 2896 - center modernization

Ended Definitive Contract Awarded Last action

Contract number
DOLETA15C0086
Awardee
Awarding agency
Obligated
$16,707,557

Award facts

Contract value 100% obligated
$16,707,556.92 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Funding agency
Shreveport Job Corps Center Office of Job Corps, Department of Labor
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 5 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Shreveport, LA 71109, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out 57 · DOL-ETA-15-C-0086, shreveport JCC redevelopment $0
Funding Only Action 56 · DOL-ETA-15-C-0086, shreveport JCC redevelopment - T -$56,196
Change Order 55 · DOL-ETA-15-C-0086, shreveport JCC redevelopment - the purpose of MOD 0055 is to incorporate the may 19, 2025 settlement agreement into the contract. $0
Change Order 54 · DOL-ETA-15-C-0086, shreveport JCC redevelopment - MOD 0054 is to provide funding for the unilateral decision for the fire alarm panel board. $2,379
Supplemental Agreement for work within scope 53 · DOL-ETA-15-C-0086, shreveport JCC redevelopment - MOD 0053 is to extend the period of performance 79 days thru december 1, 2023. $0
Supplemental Agreement for work within scope 52 · DOL-ETA-15-C-0086, shreveport JCC redevelopment - MOD 0052 settles the change order for the replacement of the window in workroom 113 $2,430
Supplemental Agreement for work within scope 51 · DOL-ETA-15-C-0086, shreveport JCC redevelopment - MOD 0051 is to process the credit due for discontinued VCT tile. The approved substitution was less expensive. -$2,279
Supplemental Agreement for work within scope 50 · DOL-ETA-15-C-0086, shreveport JCC redevelopment - MOD 0050 is to provide an additional 120 calendar days to the period of performance. $0
Supplemental Agreement for work within scope 49 · DOL-ETA-15-C-0086, shreveport JCC redevelopment -MOD 0049 is to conduct asbestos removal of the tile flooring in building a, corridors 122, 203 & 204 and to… $32,661
Change Order 48 · DOL-ETA-15-C-0086, shreveport JCC redevelopment - MOD 0048 is to update the sidewall vents, modify the corridor opening and lower the ceiling to accommodate the… $11,268
Change Order 47 · DOL-ETA-15-C-0086, shreveport JCC redevelopment - MOD 0047 for additional plumbing fixtures and increased price/funding $23,292
Supplemental Agreement for work within scope 46 · DOL-ETA-15-C-0086, shreveport JCC redevelopment - MOD 0046 is to provide funds for the canceled funding and accept the change requests for soundproofing,… $254,137
Other Administrative Action 45 · DOL-ETA-15-C-0086, shreveport JCC redevelopment - MOD 0045 is to incorporate far 52.222-55, increasing the minimum wage for federal contractors (JAN 2022) and… -$233,502
Supplemental Agreement for work within scope 44 · New cafeteria/culinary building, new warehouse/carpentry building, renovate buildings a, X and N. At the shreveport job corp center, shreveport, louisiana.… $659,154
Supplemental Agreement for work within scope 43 · Modification 0043 - new cafeteria/culinary building, new warehouse/carpentry building ,renovate buildings a, X and N . At the shreveport job corp center,… $0
Supplemental Agreement for work within scope 42 $60,505
Supplemental Agreement for work within scope 41 $18,001
Supplemental Agreement for work within scope 40 $11,786
Supplemental Agreement for work within scope 39 $163,668
Supplemental Agreement for work within scope 38 $0
Supplemental Agreement for work within scope 37 · Shreveport, JCC project 2896 center modernization. Requisitions 1631-OJC-21-CDC-0011 is included in this modification. -$1,396
Supplemental Agreement for work within scope 36 · Shreveport, JCC project 2896 center modernization. Zero dollar requisitions 1631-OJC-21-CDC-0091 and 1631-OJC-21-CDC-0061 are also included in this… $11,708
Supplemental Agreement for work within scope 35 $3,078
Supplemental Agreement for work within scope 34 $257,165
Other Administrative Action 33 $0
Supplemental Agreement for work within scope 32 $7,971
Supplemental Agreement for work within scope 31 $0
Supplemental Agreement for work within scope 30 $1,958
Supplemental Agreement for work within scope 29 $19,361
Supplemental Agreement for work within scope 28 $16,216
Supplemental Agreement for work within scope 27 $14,147
Supplemental Agreement for work within scope 26 -$32
Supplemental Agreement for work within scope 25 $0
Funding Only Action 24 -$3,908,477
Supplemental Agreement for work within scope 23 · Modification 0023 incorporates additional contract administration services. Other than this change, all other terms and conditions of the contract remain… $28,285
Novation Agreement 22 · Modification 0022 incorporates the novation agreement to incorporate ELA group INC. As the new general contractor to provide services at shreveport JCC,… $0
Supplemental Agreement for work within scope 21 · Modification 0021 corrects the overall contract price, as appropriate. Other than this change, all other terms and conditions of the contract remain… $0
Supplemental Agreement for work within scope 20 · RFC #35 - remodel space in building D for educational space renovations add: $493,319.00 other than this change, all other terms and conditions of the… $493,319
Supplemental Agreement for work within scope 19 · RFC #33 - credit of the deletion of storm drains add: ($7,478.00) other than this change, all other terms and conditions of the contract remain unchanged. The… -$7,478
Supplemental Agreement for work within scope 18 · RFC #34- addition for stairway footings add: 3,368 other than this change, all other terms and conditions of the contract remain unchanged. The substantial… $3,368
Supplemental Agreement for work within scope 17 · RFC #31-furred-out in room 216 add: 1,141 RFC #32 -modify water main serving building a add: $3,712 other than this change, all other terms and conditions of… $4,853
Supplemental Agreement for work within scope 16 · RFC no. 28 - deleting knee walls at canopy B deduct: $6,264 subsequently, the government realizes a credit of $6,264. Other than this change, all other terms… -$6,264
Supplemental Agreement for work within scope 15 · RFC no. 29 - phase B & C elevator PIT sump pumps- shreveport JCC project. Add: $24,960 add: 8 calendar days RFC no. 30 - storm drain piping and boxes add:… $44,081
Supplemental Agreement for work within scope 14 · RFC no. 25 add door vision panels at building a - shreveport JCC project. Deduct: $532 RFC no. 26 - rerouting of water lines add: $32,155 the substantial… $44,501
Supplemental Agreement for work within scope 13 · RFC no. 24 incorporates additional services to the shreveport JCC project. Add: 52 calendar days the substantial completion date for phase B is changed from… $0
Supplemental Agreement for work within scope 12 · RFC no. 0023 incorporates additional services to the shreveport JCC project. Add: 21 calendar days add: $7,008 other than the changes made herein all other… $19,094
Change Order 11 · RFC no.0022 incorporates additional services to the shreveport JCC project. Add: 0 calendar days add: $7,008 other than the changes made herein all other… $5,000
Supplemental Agreement for work within scope 10 · RFC no.0020 and 0021 incorporates additional services to the shreveport JCC project. Add: 0 calendar days add: $7,008 other than the changes made herein all… $2,430
Supplemental Agreement for work within scope 9 · RFC no.0013,0014,0015, 0016, and 0017 incorporates additional services to the shreveport JCC project. Add: 0 calendar days add: $7,008 other than the changes… -$8,478
Supplemental Agreement for work within scope 8 · RFC no.0011 and 0012 incorporates additional services to the shreveport JCC project. Add: $5,954 add: 0 calendar days other than the changes made herein all… $5,954
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

This is a $16,707,556.92 firm fixed price definitive contract awarded by the U.S. Department of Labor, Employment and Training Administration (DOL-ETA) to ELA Group Inc., a veteran-owned small business, for the modernization of the Shreveport Job Corps Center in Shreveport, Louisiana. The contract has a total small business set-aside designation and an ultimate completion date of December 1, 2023. ELA Group Inc. has previously held prime contracts with various federal agencies for construction, renovation, and installation services. This award is for the CENTER MODERNIZATION program, but no additional details on the specific products or services to be delivered are provided.

Quick answers

Who was awarded contract DOLETA15C0086?

DOLETA15C0086 was awarded to ELA Group Inc. by Office of the Assistant Secretary for Administration and Management (Department of Labor) on September 23, 2015.

How much is contract DOLETA15C0086 worth?

The government has obligated $16,707,557 on DOLETA15C0086.

Which agency awarded contract DOLETA15C0086?

Office of the Assistant Secretary for Administration and Management (Department of Labor) awarded DOLETA15C0086, with funding from Shreveport Job Corps Center (Office of Job Corps).

Was contract DOLETA15C0086 competed?

The extent of competition for DOLETA15C0086 was full and open competition after exclusion of sources. The government received 5 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award