Change Order
48 · 1. RFC 87 value engineering in evaluation of field conditions and available products suitable for the non-linear chimney openings, NCI identified an alternate…
$129,678
Change Order
47
-$311,847
Change Order
46 · South bronx job corps center building one south bronx (DOL-ETA-14-c-0010) 1. RFC 086- differential pressure sensor for perimeter heating differential pressure…
$30,070
Other Administrative Action
45 · South bronx job corps center building one south bronx (DOL-ETA-14-c-0010) to extend the contract period of performance through january 31, 2019 at no additional…
$0
Change Order
44 · South bronx job corps center building one south bronx (DOL-ETA-14-c-0010) RFC 092 is a credit to DOL resulting from definitize modification 29 which was…
-$26,651
Change Order
43 · South bronx job corps center building one south bronx (DOL-ETA-14-c-0010) extend the contract period of performance 103 calendar days (through october 31,…
$0
Change Order
42 · South bronx job corps center building one south bronx (DOL-ETA-14-c-0010) the purpose of the modification is to extend the contract period of performance from…
$0
Funding Only Action
41
$0
Change Order
40 · South bronx job corps center building one south bronx (DOL-ETA-14-c-0010) 1. RFC 089 for additional work for GC's RC 049 (replace existing damaged condenser air…
$2,644
Other Administrative Action
39
$0
Change Order
38 · South bronx job corps center building one south bronx (DOL-ETA-14-c-0010) 1. To install balancing valves and pressure sensor to the water side of the heating…
$30,000
Other Administrative Action
37 · South bronx job corps center building one south bronx (DOL-ETA-14-c-0010) 1. Extend the contract period of performance forty-seven (47) calendar days. No…
$0
Change Order
36
$23,487
Change Order
35
$52,155
Change Order
34
$7,291
Change Order
33 · South bronx job corps center building one south bronx (DOL-ETA-14-c-0010) 1. RFC no. 082 (GC's RFC no. 077) upgrade perimeter heating at room 205 plenum…
$16,583
Change Order
32 · South bronx job corps center building one south bronx (DOL-ETA-14-c-0010) construction contract modification request for a 30 day no-cost-time extension the…
$0
Change Order
31 · South bronx job corps center building one south bronx (DOL-ETA-14-c-0010) nagan 10,393.00 construction contract modification request for multiple rfcs the final…
$10,393
Change Order
30 · South bronx job corps center building one 1. (RFC 68) ACM testing at connecting corridor roof 2. (RFC 72) replace concrete slab at room 325 3. (RFC 73) CDX…
$81,765
Change Order
29 · South bronx job corps center building one this modification adds/removes to the contract as described below: 1.remove the additional tower, n.&e. Elevations;…
$23,649
Change Order
28 · South bronx job corps center building one RFC 64 replace steel gas line and replace shut-off valve RFC 66 reconstruction and restoration of south-east masonry…
$739,708
Change Order
27 · South bronx job corps center building one renovation RFC 060R- credit for masonry raking and repointing the period of performance is june 30, 2017. The…
-$279,602
Change Order
26 · South bronx job corps center building one renovation RFC 062- provide additional tower, north & east 3RD floor facades. Provide additional historic…
$830,624
Change Order
25 · South bronx job corps center building one renovation RFC 61- provide additional facade restorations the period of performance is june 30, 2017. The…
$226,858
Change Order
24 · South bronx job corps center building one renovation RFC 54 kitchen exhaust fan repair RFC 55 sever room AC units condensate return piping RFC 57 extended…
$34,653
Change Order
23 · South bronx job corps center building one renovation RFC 38 credit for repair of exterior metal stair ($20,231.00) RFC 45 credit for definitize MOD 17…
-$37,432
Change Order
22 · South bronx job corps center building one renovation RFC 50- off-site storage fee for HVAC equipment RFC 52 removal of bird dropping the period of performance…
$36,946
Change Order
21 · South bronx job corps center building one renovation RFC 42- not-to-exceed amount($244,081.00)reconstruction and restoration southeast masonry gable RFC 60-…
$1,137,548
Change Order
20 · South bronx job corps center building one renovation RFC-46- testing at pump room water tanks RFC-47-additional rent for sidewalk bridge, scaffold and hoist…
$290,907
Supplemental Agreement for work within scope
19 · South bronx job corps center building one renovation RFC-53 - provide additional masonry restoration as described in the a & e's revised a-201.02 drawings…
$553,316
Change Order
18 · South bronx job corps center building one renovation RFC-44 list of corrections to be made: 1. References made to RFC 36, 37, 39 and 41 do not apply. 2. The…
$182,868
Supplemental Agreement for work within scope
17
$477,425
Change Order
16
$58,338
Change Order
14
$113,934
Change Order
15
$1,020,104
Change Order
13
-$32,464
Change Order
12
$10,181
Change Order
11
$501,026
Change Order
10
$160,056
Change Order
9 · South bronx job corps center building one renovation list of changes: 1. RFC 23 lintel installation in phase 2B. Install steel lintels across selected second…
$199,938
Change Order
8
-$244,817
Change Order
7 · South bronx job corps center building one renovation list of changes: RFC-13 chimney inspections RFC-08R additional funding for revised phasing plan RFC 9R…
$882,412
Change Order
6
$248,591
Change Order
5
$168,897
Change Order
4 · South bronx job corps center building one renovation list of changes: 1) RFC-10 assessment water damage at dental storage room 2) RFC-11 testing for asbestos in…
$9,132
Supplemental Agreement for work within scope
3 · South bronx job corps center building one renovation RFC-005 : abate approximately 10 lineal feet of asbestos pipe insulation in mechanical rooms 007 and 009
$13,363
Supplemental Agreement for work within scope
2 · South bronx job corps center building one renovation RFC-003 : new plywood floor in building 1 attic space. $16,298.25 RFC-00 relocate sprinkler line and header…
$26,298
Supplemental Agreement for work within scope
1
$588,734
Original award
$9,970,000
Show all 49
Quick answers
Who was awarded contract DOLETA14C0010?
DOLETA14C0010 was awarded to Nagan Construction Inc. by Employment and Training Administration (Department of Labor) on June 16, 2014.
How much is contract DOLETA14C0010 worth?
The government has obligated $17,956,760 on DOLETA14C0010.
Which agency awarded contract DOLETA14C0010?
Employment and Training Administration (Department of Labor) awarded DOLETA14C0010, with funding from Job Corps National Office (Office of Job Corps).
Was contract DOLETA14C0010 competed?
The extent of competition for DOLETA14C0010 was full and open competition after exclusion of sources. The government received 7 offers. It was set aside: Total Small Business.