Selway road repairs

Ended Definitive Contract Awarded Last action

Contract number
AG0343C160033
Awardee
Awarding agency
Obligated
$1,295,604

Award facts

Opportunity
Contract value 100% obligated
$1,295,603.71 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
HUBZone
Competition
Full and Open Competition after exclusion of sources · 4 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Grangeville, ID 83530, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out 8 · DE-obligate excess funds and close contract -$1,500
Supplemental Agreement for work within scope 7 · Extend completion deadline to may 31 $0
Supplemental Agreement for work within scope 6 · Slide repair - differing site condition $0
Supplemental Agreement for work within scope 5 · Defer dust abatement and final punch list items to spring of 2017 -$1,920
Supplemental Agreement for work within scope 4 · Modify road closure period, subgrade approval process and aggregate specification. $57,500
Change Order 3 · Modify gedney bridge repair design to require contractor to supply and install treated running plank. $21,132
Change Order 2 · Modify to remedy unsuitable material found in excavation at nineteenmile culvert. Haul in 300 CY of 3/4 inch aggregate from ohara PIT, waste unsuitable material… $17,613
Other Administrative Action 1 · Change COR to susan graves $0
Original award $1,202,778

About this award

The U.S. Forest Service, Region 1 - Northern Region, awarded a $1,295,603.71 firm-fixed-price definitive contract to Ascorp Inc., doing business as Debco Construction, for the Selway Road Repairs project. This HUBZone set-aside contract was awarded on May 25, 2016, with a completion date of May 31, 2017. Debco Construction is a small business certified as a HUBZone firm, structured as a for-profit Subchapter S Corporation, and specializes in infrastructure and construction services for federal agencies, including the U.S. Forest Service and Department of Transportation. The contract involves road repairs, grading, rock embankment, aggregate surfacing, retaining walls, and drainage improvements in Grangeville, Idaho. Additionally, Debco Construction holds a $50 million Indefinite Delivery Contract (IDC) with the U.S. Forest Service, Region 1 - Northern Region, for road and bridge construction and related services, with a total program ceiling of $150 million over a five-year ordering period.

Quick answers

Who was awarded contract AG0343C160033?

AG0343C160033 was awarded to Ascorp Inc. by Region 1 - Northern Region (Forest Service) on May 25, 2016.

How much is contract AG0343C160033 worth?

The government has obligated $1,295,604 on AG0343C160033.

Was contract AG0343C160033 competed?

The extent of competition for AG0343C160033 was full and open competition after exclusion of sources. The government received 4 offers. It was set aside: HUBZone.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award