OK FW SQH T501(1) rehab riverbank & sandtown woods TR riverbank rehabilitation

Ended Definitive Contract Awarded Last action

Contract number
6982AF26C000013
Awardee
Awarding agency
Obligated
$428,678

Award facts

Opportunity
Contract value 100% obligated
$428,678.05 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 7 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Claremore, OK 74017, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out P00004 · OK FW SQH T501(1) rehab riverbank & sandtown woods trail the purpose of this contract modification (CM) is to deobligate remaining construction funds and… -$231,837
Additional Work (new agreement, FAR part 6 applies) P00003 · This contract modification adds work and new pay items. There will be an increase of $74,100 and change to the current contract completion date from march 30,… $74,100
Other Administrative Action P00002 · This administrative action will add 12 days to the period of performance (POP). POP end date will change from 4/5/2026 to 4/17/2026. This is in anticipation… $0
Supplemental Agreement for work within scope P00001 · Based on a 21-day delay in issuance of the notice to proceed (NTP) and 9-day negotiated time extension, the fixed completion date (FCD) will change from march… $0
Original award $586,415

About this award

The Federal Highway Administration awarded a firm-fixed-price definitive contract to Yorkshire Industries LLC on November 10, 2025, for riverbank stabilization and asphalt trail reconstruction, under a total small business set-aside with a ceiling of $428,678.05. The award record describes the action as a contract modification that deobligates remaining construction funds and closes out the construction contract. The prime is described as a HUBZone-certified and minority-owned small business. Ultimate completion is August 30, 2026, and no options are stated.

The project rehabilitates flood-damaged infrastructure at the Sequoyah National Wildlife Refuge in eastern Oklahoma, following 2019 flooding. Scope covers stabilization and repair of approximately 1,150 linear feet of riverbank and repair or reconstruction of approximately 500 linear feet of 6-foot-wide asphalt trail. Principal quantities are 2,700 cubic yards each of earthwork and riprap, 60 tons of asphalt concrete pavement, and 195 cubic yards of topsoil. Place of performance is recorded as Claremore, OK 74017.

The originating pre-solicitation, posted July 28, 2025, with responses due August 12, 2025, at 2 p.m. Denver time, sought qualified prime contractors holding HUBZone, woman-owned, 8(a), or service-disabled veteran-owned certifications. It required a statement of intent to bid, certifications, bonding capacity documentation, and comparable river embankment and asphalt trail portfolios. At that stage, no set-aside had been established, and the pre-solicitation estimated the value at $700,000 to $2,000,000.

Quick answers

Who was awarded contract 6982AF26C000013?

6982AF26C000013 was awarded to Yorkshire Industries LLC by Federal Highway Administration (Department of Transportation) on November 10, 2025.

How much is contract 6982AF26C000013 worth?

The government has obligated $428,678 on 6982AF26C000013.

Was contract 6982AF26C000013 competed?

The extent of competition for 6982AF26C000013 was full and open competition after exclusion of sources. The government received 7 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award