CA flap CR109(1) SIR francis drake boulevard and CA ftnp pore 10(4)200(1)201 limantour lighthouse chimney rock road reconstruction contract

Ended Definitive Contract Awarded Last action

Contract number
6982AF20C000016
Awardee
Awarding agency
Obligated
$45,713,570

Award facts

Opportunity
Contract value 100% obligated
$45,713,569.83 Current and potential, with all options
Completion date 100% complete
  • Current, with exercised options
  • Potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Point Reyes Station, CA 94956, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out P00017 · The purpose of this modification is to deobligate funds and close out the contract. -$16,244
Supplemental Agreement for work within scope P00016 · This modification is to complete additional work that was identified at the final walkthrough of the project. This is a zero-cost modification as IT reduces… $0
Supplemental Agreement for work within scope P00015 · This modification of the contract is for reimbursing the contractor for costs that were not covered by existing items while completing the wetland restoration… $30,816
Supplemental Agreement for work within scope P00014 · This modification adds $279,661.65 to clin 00001 - K200 funds, extends the contract 273 days and makes changes to the wetland restoration area in option Z… $279,662
Supplemental Agreement for work within scope P00013 · This modification adds $54,904.24 to clin 00001 - K200 funds and the government agrees to pay GCC the total SUM of eight hundred ninety-one thousand dollars… $54,904
Supplemental Agreement for work within scope P00012 · This modification updates the revegetation plan and adds clearing and grubbing (rare plants) pay item. This modification creates and adds $165,460.58 to clin… $165,461
Supplemental Agreement for work within scope P00011 · This modification updates the revegetation plan and adds several pay items. This modification adds $297,926.38 to clin 0001 - K200 funds. The contract is… $297,926
Supplemental Agreement for work within scope P00010 · This modification increases clin 00001 540.CN.K200 funds $182,662.00, add additional quantities of unclassified borrow and waste $182,662
Supplemental Agreement for work within scope P00009 · This modification increases clin 00001 540.CN.K200 funds $325,000.00, adds a pay item to remove material from drake's beach that was unable to be utilized on… $325,000
Supplemental Agreement for work within scope P00008 · This modification increases clin 00009 - K700 funds $349,965. The modification increases flexible pavement patching qtys on pore and additional work efforts… $349,965
Supplemental Agreement for work within scope P00006 · This modification increases the quantity of bid item 63506-0500, temporary traffic control, flagger due to actual, and projected future, hours on project. Add… $610,591
Supplemental Agreement for work within scope P00005 · This is a zero cost modification that reduces the pay item for fence (temporary plastic) and adds 250 delineators. $0
Supplemental Agreement for work within scope P00004 · This modification of the contract is to install a standard underdrain system from station 504+00 to station 526+00 to collect and redirect the significant… $349,500
Supplemental Agreement for work within scope P00003 · Modification P00003: reclass funds to correct BOC error. Modification for underground electrical and waterline utility relocation at the lighthouse road… -$9
Exercise an Option P00002 · Modification P00002: exercise options Y and Z $6,114,296
Exercise an Option P00001 · Modification P00001: exercise option X $9,062,988
Modification $26,726,028
Supplemental Agreement for work within scope P00007 · This modification increases clin 00001 - K200 funds $680,029.25 and clin 00009 - K700 funds $499,994.50. The modification increases subexcavation and waste… $1,180,024
Show all 18

About this award

This federal contract award, valued at $45,713,569.83, was granted by the Federal Highway Administration (FHWA) to the prime contractor, Ghilotti Construction Co Inc. (doing business as GCC), for the CA FLAP CR109(1) SIR FRANCIS DRAKE BOULEVARD AND CA FTNP PORE 10(4)200(1)201 LIMANTOUR LIGHTHOUSE CHIMNEY ROCK ROAD RECONSTRUCTION CONTRACT. The contract involves roadway resurfacing, restoration, rehabilitation, and reconstruction of approximately 12.9 miles of roadway, as well as pavement preservation of approximately 20.9 additional miles, within Point Reyes National Seashore in Marin County, California. The work includes asphalt paving, excavation, culvert replacement, drainage improvements, and various other infrastructure upgrades. This is a definitive, firm-fixed-price contract with no set-aside designation. The original solicitation was posted in October 2019, and the contract was awarded in February 2020 with a target completion date of November 2023.

Quick answers

Who was awarded contract 6982AF20C000016?

6982AF20C000016 was awarded to Ghilotti Construction Co Inc. by Federal Highway Administration (Department of Transportation) on February 13, 2020.

How much is contract 6982AF20C000016 worth?

The government has obligated $45,713,570 on 6982AF20C000016.

Was contract 6982AF20C000016 competed?

The extent of competition for 6982AF20C000016 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award