Project MS erfo NPS vick 2020-1(2) the project consists of slide repairs on grant avenue and union avenue. The work includes clearing and grubbing, roadway excavation and embankment construction,…
Active Definitive Contract Awarded Last action
- Contract number
- 693C7325C000007
- Awardee
-
Central Southern Construction Corp. UEI GKU1XRD7BCX7
- Awarding agency
-
Federal Highway Administration
Department of Transportation
- Obligated
- $8,933,610
Award facts
- Opportunity
-
- Vicksburg National Military Park Pre-Solicitation · 693C7325B000002 · Posted Oct 8, 2024
- Contract value 100% obligated
- $8,933,610.00 Current and potential, with all options
- Completion date 56% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 4 offers Sealed Bid
- Pricing
- Firm Fixed Price
- Place of performance
- Vicksburg, MS, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
- Employment Eligibility Verification (E-Verify) FAR subpart 22.18
- Service Contract Inventory FAR subpart 4.17
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Other Administrative Action | $0 | |
| Other Administrative Action | $0 | |
| Funding Only Action | $1,495,150 | |
| Original award | $7,438,460 |
About this award
The Federal Highway Administration awarded an $8.93 million firm fixed-price definitive contract to Central Southern Construction Corp., an SBA-certified HUBZone firm, for slide repairs on Grant Avenue and Union Avenue at Vicksburg National Military Park in Mississippi, on January 9, 2025.
The originating solicitation, posted October 8, 2024, describes clearing and grubbing, roadway excavation and embankment construction, geogrid installation, gabions, aggregate base, and mechanically compacted fill work to address slope stabilization. Place of performance is Vicksburg, MS. The contract ultimate completion date is March 31, 2028.
Subcontractors include Peterson Contractors, Inc., Chris-Hill Construction Company, LLC, and Brock Mountain Land Company, LLC. The contract resulted from a sealed-bid procurement with no set-aside designation; the solicitation anticipated total project costs between $5 million and $10 million split across multiple work schedules and contract options.
Description
Project MS erfo NPS vick 2020-1(2) the project consists of slide repairs on grant avenue and union avenue. The work includes clearing and grubbing, roadway excavation and embankment construction, geogrid, gabions, aggregate base, mechanically compac
Subawards
| Subcontractor | Amount | Awarded |
|---|---|---|
| Peterson Contractors, Inc. | $600,000 | |
| Chris-Hill Construction Company, LLC | $94,393 | |
| Brock Mountain Land Company, LLC | $444,575 |
Quick answers
Who was awarded contract 693C7325C000007?
693C7325C000007 was awarded to Central Southern Construction Corp. by Federal Highway Administration (Department of Transportation) on January 9, 2025.
How much is contract 693C7325C000007 worth?
The government has obligated $8,933,610 on 693C7325C000007.
Was contract 693C7325C000007 competed?
The extent of competition for 693C7325C000007 was full and open competition. The government received 4 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award