Funds construction project: AK PFH 58(1), neck lake road reconstruction: npowi HWY. To marine access facility JCT. Work includes excavation, rock blasting, embankment, grading, drainage, retaining…
Active Definitive Contract Awarded Last action
- Contract number
- 69056725C000012
- Awardee
-
Glacier Construction Inc. UEI ZKY5WY34JEP7
- Awarding agency
-
Federal Highway Administration
Department of Transportation
- Obligated
- $22,527,341
Award facts
- Opportunity
-
- AK PFH 58(1), Neck Lake Road Reconstruction: NPOWI Hwy. to Marine Access Facility Jct. Pre-Solicitation · 69056725B000001 · Posted Sep 25, 2024
- Contract value 100% obligated
- $22,527,340.50 Current and potential, with all options
- Completion date 98% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 3 offers Sealed Bid
- Pricing
- Firm Fixed Price
- Place of performance
- Coffman Cove, AK, USA
- Legislative mandates
-
- Service Contract Act FAR subpart 22.10
- Davis-Bacon Act FAR subpart 22.4
- Employment Eligibility Verification (E-Verify) FAR subpart 22.18
- Service Contract Inventory FAR subpart 4.17
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Funding Only Action | $2,000,000 | |
| Other Administrative Action | $0 | |
| Original award | $20,527,341 |
About this award
The Federal Highway Administration awarded a $22.5 million definitive contract to Glacier Construction Inc. for the AK PFH 58(1) Neck Lake Road Reconstruction project on March 31, 2025, under firm fixed-price pricing with no set-aside used.
The work reconstructs 1.6 miles of Neck Lake Road from the Npoui Highway to the Marine Access Facility junction in Coffman Cove, Alaska. Scope includes excavation, rock blasting, embankment and grading, drainage infrastructure, retaining wall, and guardrail installation. This modification addresses an increase in bid items that exceeded 115 percent of the original quantity. Ultimate completion is due November 9, 2026. Place of performance is Coffman Cove, AK.
Glacier Construction Inc. engages Glacier State Contractors, Inc. for guardrail system and terminal section work; R & M Engineering-Ketchikan, Incorporated for technical services related to rock monitoring; and Dowl, LLC for professional engineering services on rock dowel and construction survey and staking activities.
Description
Funds construction project: AK PFH 58(1), neck lake road reconstruction: npowi HWY. To marine access facility JCT. Work includes excavation, rock blasting, embankment, grading, drainage, retaining wall, and guardrail.
Subawards
| Subcontractor | Amount | Awarded |
|---|---|---|
| Glacier State Contractors, Inc. | $638,280 | |
| Subcontractor not on record | $315,000 | |
| R & M Engineering-Ketchikan, Incorporated | $70,720 | |
| Dowl, LLC | $53,728 |
Quick answers
Who was awarded contract 69056725C000012?
69056725C000012 was awarded to Glacier Construction Inc. by Federal Highway Administration (Department of Transportation) on March 31, 2025.
How much is contract 69056725C000012 worth?
The government has obligated $22,527,341 on 69056725C000012.
Was contract 69056725C000012 competed?
The extent of competition for 69056725C000012 was full and open competition. The government received 3 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award