Physical security and emergency management(PSEM) construction services, 200 independence avenue, SW, washington, DC 20201.

Active Definitive Contract Awarded Last action

Contract number
47PM0225C0008
Awardee
Awarding agency
Obligated
$5,269,578

Award facts

Opportunity
  • 47PM0225R0005 Solicitation number
Contract value 100% obligated
$5,269,578.18 Current and potential, with all options
Completion date 53% complete
  • Current, with exercised options
  • Potential, with all options
Funding agency
US-Mexico Border Health Commission Immediate Office of the Secretary, Department of Health and Human Services
Set-aside
8(a) Sole Source
Competition
Not Available for Competition · 1 offer Only One Source
Pricing
Firm Fixed Price
Place of performance
Washington, DC 20201, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS0009 · Bilateral modification for additional work to add wire tracing due to an unforeseen condition as well as suite 120 and the remaining second floor. $3,979,679
Supplemental Agreement for work within scope PS0008 · Modification to incorporate DEI clause under EO 14398. $0
Supplemental Agreement for work within scope PS0007 · Time extension $0
Supplemental Agreement for work within scope PS0006 · 47PM0225C0008 psem modernization construction project - hubert humphrey headquarters 200 independence AVE SW washington DC 20201 is modified to add the… $3,590
Supplemental Agreement for work within scope PS0005 $7,515
Supplemental Agreement for work within scope PS0004 · 47PM0225C0008 physical security and emergency management modernization construction project - hubert humphrey headquarters 200 independence AVE SW washington DC… $68,000
Supplemental Agreement for work within scope PS0003 · Implementation of CDS and drones clause $0
Supplemental Agreement for work within scope PS0002 · Psems modernization construction project hubert humphrey headquarters 200 independence AVE SW washington DC 20201 is modified to change line item date to… $0
Supplemental Agreement for work within scope PS0001 · Psems - hubert humphrey headquarters 200 independence AVE SW washington DC 20201 is modified to remove option 2 (remaining 2ND floor). The base and all… $0
Original award $1,210,794

About this award

The US-Mexico Border Health Commission awarded a $5.27 million definitive contract to Abode Inc. for physical security and emergency management construction services at 200 Independence Avenue, SW, Washington, DC on March 10, 2025, under an 8(a) sole-source set-aside.

Abode Inc. is an SBA-certified 8(a) Program Participant and minority-owned small disadvantaged business. The originating modification adds wire tracing due to an unforeseen condition, along with work in Suite 120 and the remaining second floor. The contract is firm fixed price with an ultimate completion date of April 11, 2028. Place of performance is Washington, DC 20201.

In FY2025, Abode Inc. invoiced $731 thousand against this contract while deploying 1.7 FTEs, self-performing all reported work with no subcontractors reported.

Quick answers

Who was awarded contract 47PM0225C0008?

47PM0225C0008 was awarded to Abode Inc. by National Capital Region (Public Buildings Service) on March 10, 2025.

How much is contract 47PM0225C0008 worth?

The government has obligated $5,269,578 on 47PM0225C0008.

Which agency awarded contract 47PM0225C0008?

National Capital Region (Public Buildings Service) awarded 47PM0225C0008, with funding from US-Mexico Border Health Commission (Immediate Office of the Secretary).

Was contract 47PM0225C0008 competed?

The extent of competition for 47PM0225C0008 was not available for competition. The government received 1 offer. It was set aside: 8(a) Sole Source.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award