Construction services to replace fire main piping at the celebrezze federal building in cleveland, OH.

Ended Definitive Contract Awarded Last action

Contract number
47PF0025C0004
Awardee
Awarding agency
Obligated
$633,293

Award facts

Opportunity
Contract value 99% obligated
  • $633,293.34 Current, with exercised options
  • $638,293.34 Potential, with all options
Completion date 100% complete
  • Current, with exercised options
  • Potential, with all options
Set-aside
Total Small Business
Competition
5 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Cleveland, OH 44199, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action PA0008 · Construction service to replace degraded fire water supply pipe project at the anthony J. Celebrezze federal building, 1240 east ninth ST, cleveland, OH… $0
Supplemental Agreement for work within scope PS0006 $14,750
Supplemental Agreement for work within scope PS0007 · Construction services to replace degraded fire water supply pipe construction project at the anthony J. Celebrezze federal building, 1240 east ninth ST,… $31,699
Supplemental Agreement for work within scope PS0004 · Additional scope added to the fire main replacement at the celebrezze federal building in cleveland, OH. $22,558
Other Administrative Action PA0003 · Modification to correct accoutning string for the fire main replacement at the anthony J. Celebrezze federal building, cleveland, OH. $0
Original award $565,000

About this award

The General Services Administration (GSA) Region 5 awarded a $638,293.34 firm fixed-price definitive contract to Town Center Construction, LLC for construction services to replace the fire main piping system at the Anthony J. Celebrezze Federal Building in Cleveland, Ohio. The contract, awarded December 19, 2024, with an ultimate completion date of September 2, 2025, is designated as a Total Small Business set-aside. The scope of work includes replacing degraded fire water supply piping and encompasses the replacement of underground fire mains, installation of underground utility vaults, fire department connections, and associated interior fire protection piping. This modification represents a scope reduction and cost savings from the original solicitation estimate of $1.0–$2.0 million.

Town Center Construction, LLC is a Northfield, Ohio-based small business with extensive experience in federal construction and facility upgrades. The company is performing this work under its $50 million GSA Region 5 Regional Construction Indefinite Delivery Indefinite Quantity contract, awarded in September 2024 and designated as a Total Small Business set-aside. Town Center Construction has demonstrated substantial capability executing complex projects for federal facilities across the Midwest, with particular expertise in fire system installations, mechanical upgrades, and facility hardening initiatives. The company holds relevant experience at the Celebrezze Federal Building, having previously completed bus duct replacement and transformer vault sprinkler system installation work at the same location.

Quick answers

Who was awarded contract 47PF0025C0004?

47PF0025C0004 was awarded to Town Center Construction, L.L.C. by Region 5 (Public Buildings Service) on December 19, 2024.

How much is contract 47PF0025C0004 worth?

The government has obligated $633,293 on 47PF0025C0004. Its potential value, with all options, is $638,293.

Was contract 47PF0025C0004 competed?

The government received 5 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award