Construction project renovating the NIX federal building and courthouse in philadelphia, PA. GSA is retrofitting vacated space by the uspo for another federal agency.

Ended Definitive Contract Awarded Last action

Contract number
47PD0120C0011
Awardee
Awarding agency
Obligated
$19,506,078

Award facts

Opportunity
Contract value 100% obligated
$19,506,078.38 Current and potential, with all options
Completion date 100% complete
  • Current, with exercised options
  • Potential, with all options
Funding agency
Bureau of Consular Affairs Department of State
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 8 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Philadelphia, PA 19107, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action PA0048 · Modification extending until 12/31/2024 $0
Supplemental Agreement for work within scope PS0047 · Modification to add RFP 043R bypass dampers $7,185
Supplemental Agreement for work within scope PS0046 · Modification to incorporate RFP 043 $74,255
Supplemental Agreement for work within scope PS0045 · Modification to extend until april 30, 2024 $0
Supplemental Agreement for work within scope PS0044 · This modification is for the construction contractor on the NIX renovation project in philadelphia PA adding an additional fan as part of the commissioning… $19,836
Supplemental Agreement for work within scope PS0043 · This is a modification adding the work in change order proposals 117, 131, 143, 185 & 189 to the general contractor's contract for the NIX restoration project… $68,177
Supplemental Agreement for work within scope PS0042 · This is a modification to the construction contractor's contract adding the work in cops 184, 187 & 188 to the NIX project in philadelphia, PA. $175,922
Supplemental Agreement for work within scope PS0041 · This is a modification to the construction contractor's contract for the NIX FED bldg renovation project in philadelphia, PA to add chiller pump installation… $208,191
Supplemental Agreement for work within scope PS0040 · This is a modification for stair railing work being awarded to the construction contractor for the NIX renovation project in philadelphia, PA. $40,761
Supplemental Agreement for work within scope PS0039 · This is a modification to the general contractor's contract adding hydronic pump purchase for the NIX renovation project in philadelphia, PA. $9,633
Supplemental Agreement for work within scope PS0038 · This is a modification incorporating the work described in COP 180 into the construction contractor on the NIX renovation project in phila, PA. $39,967
Supplemental Agreement for work within scope PS0037 · This is a modification to the construction contractor's contract adding add'l work described in cops 177, 178 & 179 for the NIX renovation project in phila, PA. $42,852
Supplemental Agreement for work within scope PS0036 · This is a modification for the GC including change order proposals 158 159 AKA 171 162 168 173 and 176 for the NIX renovation project in philadelphia, PA. $113,610
Supplemental Agreement for work within scope PS0035 · This is a modification to the construction contractor's contract on the NIX renovation project in philadelphia, PA. IT incorporates the add'l work included in… $12,623
Supplemental Agreement for work within scope PS0034 · This is modification PS0034 which incorporates the work described in ASI 18 revised and COP 144 for the construction contractor on the NIX FED bldg renovation… $23,315
Supplemental Agreement for work within scope PS0033 · This is a modification to the construction contractors contract on the NIX federal building project in philadelphia adding the work described in change order… $36,439
Supplemental Agreement for work within scope PS0032 · This is a modification to the contractors construction contract adding the work in change order proposals 141 & 147 to the NIX renovation project in… $23,541
Supplemental Agreement for work within scope PS0031 · This is a modification to the construction contractor's contract on the NIX federal building project in philadelphia, PA to incorporate the work in change order… $170,682
Other Administrative Action PA0030 · This is an administrative modification to correct an accounting string issue that occurred when processing the previous modification to the contractor for the… $0
Supplemental Agreement for work within scope PS0029 · This is a modification to the construction contractor's contract adding the work in change order proposal 140R1 to the NIX renovation project in philadelphia,… $6,046
Supplemental Agreement for work within scope PS0028 $195,623
Supplemental Agreement for work within scope PS0027 $335,462
Supplemental Agreement for work within scope PS0026 $61,407
Supplemental Agreement for work within scope PS0025 · This is a modification to the construction contractor's contract for the NIX renovation project in philadelphia, PA incorporating the work in change order… $22,392
Supplemental Agreement for work within scope PS0024 · This modification is for additional work at the NIX federal building and courthouse in philadelphia that will now include certain additional speaker and… $174,895
Supplemental Agreement for work within scope PS0023 · This is a modification to the construction contractors contract on the NIX FED bldg in philadelphia incorporating change order proposals 74, 109, 111 & 114. $19,017
Supplemental Agreement for work within scope PS0022 · This is a modification to the contractor's construction contract for the NIX renovation project in philadelphia PA that includes change order proposals 92 &… $47,356
Supplemental Agreement for work within scope PS0021 · This is a modification to the construction contractor's contractor for the NIX renovation project in phila PA that includes change order proposals 66, 93R1,… $94,708
Supplemental Agreement for work within scope PS0020 · This is a modification to the construction contractor's contract to incorporate six additional change order proposals for the NIX renovation project in phila,… $71,315
Supplemental Agreement for work within scope PS0019 · This is a modification to the construction contractor's contract for various change order proposals at the NIX renovation project in philadelphia, PA. $94,136
Supplemental Agreement for work within scope PS0017 · This is a modification to the construction contractor's contract on the NIX federal bldg renovation project in philadelphia. IT includes change order… $14,220
Supplemental Agreement for work within scope PS0016 · This modification adds the work in change order proposals 22 53 63 72 76 to the construction contract for the NIX renovation project in philadelphia, PA. $42,140
Supplemental Agreement for work within scope PS0015 · This is a modification to the construction contractor TBC's contract to include the work in change order proposals 28 & 49 at the NIX renovation project in… $19,874
Supplemental Agreement for work within scope PS0014 · This is a modification to the construction contractor's contract to include catwalk work inside the NIX federal bldg in phila that was described in RFP 011… $493,059
Supplemental Agreement for work within scope PS0013 · This is a modification to the construction contractors contract for five separate add'l items of work on the project at the NIX federal building and… $83,956
Supplemental Agreement for work within scope PS0012 · NIX renovatiob project, philadelphia, PA - modification PS0012 incorporating the following cops (change order proposals): 24, 32, 43, 48, 50, 51 & 59. $358,430
Supplemental Agreement for work within scope PS0011 · Modification PS0011 incorporating the following cops (change order proposals): 03, 13, 17, 26, 33, 34, 45, 56, & 62 for the NIX renovation project. $148,731
Supplemental Agreement for work within scope PS0010 · This is a modification to the construction contractors contract on the NIX FED bldg & US courthouse renovation project in philadelphia, PA. The work includes… $545,876
Supplemental Agreement for work within scope PS0009 · This is a modification to bedwell's contract to include certain additional structural steel and work associated W/the installation of a new AHU at the NIX… $54,918
Supplemental Agreement for work within scope PS0008 · This is a modification to the construction contract including add'l compensation for change order proposals 5 15 30 35 36 and 47 at the NIX renovation project… $73,782
Supplemental Agreement for work within scope PS0007 · This is a modification to the construction contractor's contract for multiple additional items of work due to unforeseen conditions for the most part on the NIX… $74,493
Supplemental Agreement for work within scope PS0006 · This is a modification to the construction contractors contract adding the work identified in change order proposals 27 & 29 (RFP 006) for the NIX bldg… $61,334
Supplemental Agreement for work within scope PS0005 · This is a modification to the construction contractors contract for additional work identified in change order proposals 4, 19 & 23 at the NIX FED bldg… $61,354
Supplemental Agreement for work within scope PS0004 · This is a modification to the contractor's contract for additional unforeseen work that included the demo and removal of concrete encased steel beams at the NIX… $20,075
Supplemental Agreement for work within scope PS0003 · This is a modification to the construction contractor at the NIX federal building in philadelphia PA covering the demolition work described in change order… $55,196
Supplemental Agreement for work within scope PS0002 · This is a modification for the construction contractor to demolish and remove add'l concrete and steel that was an unforeseen condition at the NIX renovation… $86,295
Other Administrative Action PA0001 · This is the notice to proceed issued to the bedwell company for the NIX federal building and courthouse renovation project in philadelphia, pennsylvania. $0
Original award $15,123,000
Show all 48

About this award

This is a $19,506,078.38 Firm Fixed Price contract awarded by the Bureau of Consular Affairs, a civilian federal agency, to The Bedwell Company, a small business contractor, for the construction project of renovating the approximately 47,000 square feet of historic former Post Office space on the first floor and mezzanine level of the Robert N.C. Nix Federal Building and Courthouse in Philadelphia, Pennsylvania. The contract has a period of performance from the notice to proceed through December 31, 2024. This project was originally competitively solicited as a total small business set-aside.

Subawards

Subcontractor Amount Awarded
Herman Goldner Co, Inc. MODIFICATION TO INCORPORATE RFP 043 HVAC water pumps $144,800
Mara Restoration, Inc. Modification to incorporate RFP 043 masonry work $249,270
A & S Sprinkler Company, Inc. MODIFICATION TO INCORPORATE RFP 043 Wet Pipe Sprinkler System $170,000

Quick answers

Who was awarded contract 47PD0120C0011?

47PD0120C0011 was awarded to The Bedwell Company by Region 3 (Public Buildings Service) on September 29, 2020.

How much is contract 47PD0120C0011 worth?

The government has obligated $19,506,078 on 47PD0120C0011.

Which agency awarded contract 47PD0120C0011?

Region 3 (Public Buildings Service) awarded 47PD0120C0011, with funding from Bureau of Consular Affairs (Department of State).

Was contract 47PD0120C0011 competed?

The extent of competition for 47PD0120C0011 was full and open competition after exclusion of sources. The government received 8 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award