Close Out
PA0073 · Modification PA0073 - close out for the construction of the rambo federal courthouse in harrisburg, PA
-$0
Definitize Change Order
PS0072 · Modification PS0072 for construction manager as constructor (CMC) services for the sylvia rambo federal courthouse in harrisburg, PA
-$26,999
Supplemental Agreement for work within scope
PS0070 · Modification PS0070 for construction manager as constructor (CMC) services for the sylvia rambo federal courthouse in harrisburg, PA
$0
Supplemental Agreement for work within scope
PS0069 · Modification PS0069 for construction manager as constructor (CMC) services for the sylvia rambo federal courthouse in harrisburg, PA
$1,342
Supplemental Agreement for work within scope
PS0068 · Modification PS0068 for construction manager as constructor (CMC) services for the sylvia rambo federal courthouse in harrisburg, PA
$0
Supplemental Agreement for work within scope
PS0067 · Modification PS0067 for construction manager as constructor (CMC) services for the sylvia rambo federal courthouse in harrisburg, PA
$0
Supplemental Agreement for work within scope
PS0066 · Modification PS0066 for construction manager as constructor (CMC) services for the sylvia rambo federal courthouse in harrisburg, PA
$0
Supplemental Agreement for work within scope
PS0065 · Modification PS0065 for construction manager as constructor (CMC) services for the sylvia rambo federal courthouse in harrisburg, PA
$64,046
Supplemental Agreement for work within scope
PS0064 · Modification PS0064 for construction manager as constructor (CMC) services for the sylvia rambo federal courthouse in harrisburg, PA
$144,298
Supplemental Agreement for work within scope
PS0063 · Modification PS0063 for construction manager as constructor (CMC) services for the sylvia rambo federal courthouse in harrisburg, PA
$63,259
Supplemental Agreement for work within scope
PS0062 · Modification PS0062 for construction manager as constructor (CMC) services for the sylvia rambo federal courthouse in harrisburg, PA
$180,695
Supplemental Agreement for work within scope
PS0061 · Modification PS0061 for construction manager as constructor (CMC) services for the sylvia rambo federal courthouse in harrisburg, PA
$0
Supplemental Agreement for work within scope
PS0060 · Modification PS0060 for construction manager as constructor (CMC) services for the sylvia rambo federal courthouse in harrisburg, PA
$266,043
Supplemental Agreement for work within scope
PS0059 · Modification PS0059 for construction manager as constructor (CMC) services for the sylvia rambo federal courthouse in harrisburg, PA
$915,536
Supplemental Agreement for work within scope
PS0058 · Modification PS0058 for construction manager as constructor (CMC) services for the sylvia rambo federal courthouse in harrisburg, PA
$483,597
Supplemental Agreement for work within scope
PS0057 · Modification PS0057 for construction manager as constructor (CMC) services for the sylvia rambo federal courthouse in harrisburg, PA
$399,403
Supplemental Agreement for work within scope
PS0056 · Modification PS0056 for the construction of the rambo federal courthouse in harrisburg, PA
$357,662
Funding Only Action
PA0055 · MOD PA0055 for the new federal courthouse in harrisburg, PA
$0
Supplemental Agreement for work within scope
PS0054 · 47PD0118C0003, MOD PS0054 - HFC construction CMC- harrisburg, PA various changes from RFP 388-400 including usms furniture feeds.
$344,887
Supplemental Agreement for work within scope
PS0053 · Harrisburg federal courthouse CMC project, harrisburg, PA- additional work to install cypher locks for the 2ND floor and various RFP's.
$239,903
Supplemental Agreement for work within scope
PS0052 · MOD PS52- various MOD settlements-for judge rambo exhibits and display harrisburg federal courthouse renovation to mascaro construction
$881,816
Supplemental Agreement for work within scope
PS0051 · Harrisburg federal courthouse CMC contract harrisburg, PA- MOD PS51 for mascaro construction.
$333,647
Supplemental Agreement for work within scope
PS0050 · Modification PS50 to harrisburg federal courthouse located in harrisburg, PA.
$911,893
Supplemental Agreement for work within scope
PS0049 · MOD PS49- mascaro REA RFP numbers 193, 195, 209, 215, 218, 219, 222, 223, 226, 230, 231, 237, 238, 239, 240, 242, 243, 244, 245, 246, 247, 249, 250, 251, 253,…
$322,218
Supplemental Agreement for work within scope
PS0048 · This MOD is for the following RFP143, 171, 199, 200, 202, 204, 207A, 207B, 213, 214, 217, 221, 225, 228, 233, 235, 236, REA021
$306,915
Change Order
PC0047 · This modification is issued to determine the final amount allowed for the price to be determined later modification number PC00041 issued on 8/27/2021.
$0
Supplemental Agreement for work within scope
PS0046 · This MOD is for the following: RFP143, 179, 198, 203, 180, 201, 205, PCO215, 206, 208, REA009, 210, usms PDL, 211, 212 RFP192, and ASI 063.
$675,333
Supplemental Agreement for work within scope
PS0045 · This modification is for the following RFP142, 166.1, 168, 183, 189, 190, 191, 196, 206, REA018, PCO183, REA017R1, REA015B, PCO203, and PCO206 , and for…
$977,626
Supplemental Agreement for work within scope
PS0044 · This modification is for: rfps 14, 164, 166.2, 178, 128, 135R1, 140, 148, 159, 163, 165, 169, 170, 173, 175, 177, 182, 184, and 186. Harrisburg, PA
$792,938
Supplemental Agreement for work within scope
PS0042 · This modification is for RFP134.1, 144, 145, 151, 154, 158, 160, 167, 174 and fencing additional scope in harrisburg, PA.
$229,307
Change Order
PC0041 · This modification is for PCO 163. Price to be determined later.
$222,413
Other Administrative Action
PA0040 · Construction of a new U.S. Courthouse in harrisburg, PA. Modification to fix accounting string errors.
$0
Supplemental Agreement for work within scope
PS0039
$610,094
Supplemental Agreement for work within scope
PS0038
$340,346
Supplemental Agreement for work within scope
PS0037
$243,698
Supplemental Agreement for work within scope
PS0036 · Construction of a new U.S. Courthouse in harrisburg, PA. Modification to incorporate several customer requested changes.
$145,090
Supplemental Agreement for work within scope
PS0035 · Construction of a new U.S. Courthouse in harrisburg, PA. Modification to credit part of the courts' demountable partition.
-$34,239
Supplemental Agreement for work within scope
PS0034 · Construction of a new U.S. Courthouse in harrisburg, PA. Modification to award rfps 98.2 115 and 118.
$205,173
Supplemental Agreement for work within scope
PS0033 · Construction of a new U.S. Courthouse in harrisburg, PA. Modification to incorporate rfps 78, 88, 82, 95, 98.1, 101, 102.1, 110, 111, 112, 123, 125, 121, and…
$235,429
Supplemental Agreement for work within scope
PS0032 · Construction of a new federal courthouse in harrisburg, PA. Modification to incorporate RFP 119.
$70,752
Supplemental Agreement for work within scope
PS0031 · Construction of a new U.S. Courthouse in harrisburg, PA. Modification to include multiple rfps.
$180,132
Change Order
PO0030 · Construction of a new federal courthouse in harrisburg, PA. Modification to provide a no-cost time extension for covid-19 related delays.
$0
Supplemental Agreement for work within scope
PS0029 · Construction of a new U.S. Courthouse in harrisburg, PA. Modification to extend the completion date at no additional cost.
$0
Supplemental Agreement for work within scope
PS0028 · Construction of a new U.S. Courthouse in harrisburg, PA. Modification to incorporate pcos 28, 40, 72, 74, 80, 39, and 76.
$29,554
Supplemental Agreement for work within scope
PS0027 · New US courthouse in harrisburg, PA. Modification to incorporate rfps 028, 061, 064, 073, 081, and 089.
$469,288
Supplemental Agreement for work within scope
PS0026 · Construction of a new federal courthouse in harrisburg, PA modification to incoroorate rfps 26, 50, 77, 79, 80, and 62.
$602,868
Supplemental Agreement for work within scope
PS0025 · Construction of a new U.S. Courthouse in harrisburg, PA. Modification to incorporate rfps 68, 85 and 86.
$1,810,741
Supplemental Agreement for work within scope
PS0023 · Implementation of section 889 requirements/certification.
$0
Supplemental Agreement for work within scope
PS0022 · 47PD0118C0003 construction of a new U.S. Courthouse in harrisburg, PA. Modification to incorporate rfps 025, 041, 047, 048, 067, 069, 072, 074, 075.
$2,012,317
Supplemental Agreement for work within scope
PS0021 · Construction of a new U.S. Courthouse in harrisburg, PA modification to incorporate rfps 037, 038, 040, 046, 052, 054, 071, 049, 070.
This is a definitive, fixed-price incentive contract awarded by the General Services Administration (GSA) to Mascaro Construction Co LP for construction management services as the constructor (CMC) for the U.S. Courthouse in Harrisburg, Pennsylvania. The total ceiling value of the contract is $169,880,054.51, with a period of performance through November 30, 2024. The contract was awarded on March 9, 2018 and was not set aside for any specific business size or type. No additional details about subcontractors or the agency's high-level programs were provided.
Quick answers
Who was awarded contract 47PD0118C0003?
47PD0118C0003 was awarded to Mascaro Construction Co LP by Region 3 (Public Buildings Service) on March 9, 2018.
How much is contract 47PD0118C0003 worth?
The government has obligated $169,880,055 on 47PD0118C0003.
Was contract 47PD0118C0003 competed?
The extent of competition for 47PD0118C0003 was full and open competition. The government received 9 offers.