Definitive Contract 47PC0223C0002
- Not listed
- This is a delivery order awarded to DCM Architecture & Engineering, LLC, a minority-owned small business, under the General Services Administration's (GSA) $500 million Region 2 Indefinite Delivery, Indefinite Quantity (IDIQ) contract for general construction and design-build services. The $1,082,225.60 fixed-price contract is for pavement repair work at the Charles L. Brieant Courthouse in White Plains, New York, with a completion date of December 6, 2024. DCM has performed previous work...
- The Definitive Contract awarded by the Administrative Office of the U.S. Courts to DCM Architecture & Engineering, LLC for the SDNY-Brieant Courthouse--1st Floor, 2nd Floor, and 6th Floor Option Renovation Build-outs project in White Plains, New York will involve renovating and building out specified floors of the 300 Quarropas Street federal courthouse located there on a firm fixed price basis. As a total small business set-aside contract, the work is intended to enhance facilities for...
- The federal contract award, valued at $807,413.23, was issued to DCM Architecture & Engineering, LLC (DCM), a minority-owned, for-profit limited liability company, to perform construction work at the 1st floor of the Executive Office for Immigration Review (EOIR) facility located at 290 Broadway in New York, NY. This contract is a Delivery Order under the General Services Administration's (GSA) Region 2 General Construction and Design-Build Construction Services indefinite delivery vehicle...
- This federal contract award is for the installation of bollards on Lexington Avenue in White Plains, New York, awarded by the Department of Justice U.S. Marshals Service to DCM Architecture & Engineering, LLC (doing business as DCM). The contract is a firm fixed-price delivery order with a potential value of $762,292.76 and a completion date of December 2, 2023. DCM is a minority-owned, for-profit limited liability company that specializes in high-performance design, sustainable construction...
- This is a delivery order awarded to DCM Architecture & Engineering, LLC, a minority-owned small business, under the General Services Administration's (GSA) $500 million Region 2 Indefinite Delivery Vehicle (IDV) for general construction and design-build services. The $640,731.07 contract is for design services at a federal facility in Holtsville, New York, with an ultimate completion date of October 25, 2024. DCM has previously performed work for several civilian federal agencies,...
- This firm-fixed-price delivery order was awarded by the General Services Administration (GSA) Region 2 to the woman-owned architectural firm Dattner Architects DPC on November 2, 2020. The $414,440.50 contract provides architectural and engineering (A/E) services for the roof at the Theodore M. Chewning Hall (TMCH) and a time extension for A/E services at the Charles L. Brieant Jr. Federal Courthouse in White Plains, New York. The work has an ultimate completion date of November 28, 2025....
- This is a $2,528,177.40 firm fixed-price delivery order awarded to DCM Architecture & Engineering, LLC (DCM), a minority-owned small business, by the General Services Administration (GSA) Region 2. The contract is for facade repairs under the PBS R2 General Construction and Design-Build Construction Services indefinite delivery vehicle (IDV). DCM will perform the work in New York, NY, with a completion date of January 31, 2025. This contract leverages DCM's expertise in high-performance...
- The Administrative Office of the U.S. Courts awarded a $810,222.72 firm fixed-price delivery order to Dattner Architects DPC on April 28, 2021, for third floor build-out services at a federal facility located in New York, NY 10008. The contract, which carries an ultimate completion date of January 31, 2026, was awarded without a set-aside designation, reflecting the contractor's competitive standing in the federal market. Dattner Architects DPC, a New York City-based woman-owned architectural...
- This firm fixed price delivery order was awarded by the Administrative Office of the United States Courts to DCM Architecture & Engineering, LLC for data infrastructure upgrade work at the United States Bankruptcy Court for the Southern District of New York located at 1 Bowling Green in New York City. The contract was issued under the General Services Administration's Region 2 General Construction and Design-Build Construction Services multiple award indefinite-delivery indefinite-quantity...
- The Administrative Office of the U.S. Courts awarded a delivery order valued at $584,214.68 to Dattner Architects DPC, a New York City-based, woman-owned architectural firm, for architectural and engineering (A/E) services supporting the Probation Reduction Space Project at the Alfonso D'Amato U.S. Federal Courthouse in Central Islip, New York. The contract was originally awarded on February 2, 2021, on a firm fixed-price basis with no set-aside designation. A no-cost time extension has extended...
This federal contract award, valued at $2,058,049.56, was made by the Administrative Office of the U.S. Courts to DCM Architecture & Engineering, LLC, a minority-owned small business, for renovations and alterations to the 5th floor District Courtroom Suite 521 at the Charles L. Brieant Jr. Federal Building and Courthouse in White Plains, New York. The contract is a definitive, firm fixed-price contract. The original solicitation was a sources sought notice that sought design-build services for the courtroom renovations, which were required to match recently completed renovations on the 6th floor. The project included selective demolition, construction, and infrastructure modifications such as electrical and IT/AV work. The contract has a period of performance requiring substantial completion within 448 calendar days of award. This contract award is associated with three significant Indefinite Delivery Vehicle (IDV) contracts held by DCM Architecture & Engineering, including a $30 million Dover Air Force Base Multiple Award Construction Contract, a $500 million GSA Public Buildings Service Region 2 General Construction and Design-Build Construction Services contract, and a $75 million GSA Region 3 contract focused on COVID-19 safety upgrades. These IDVs have enabled DCM to receive numerous task orders from various federal agencies to support infrastructure projects across multiple departments and regional offices.
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
5th Floor East Courtroom Repairs & Alterations - Charles L. Brieant Jr. Court House in White Plains, NY | EQ2PCM-22-0019 | General Services Administration Public Buildings Service Region 2 | Pre-Solicitation 2/4 | 2/3/22, 4:39 PM | |
5th Floor East Courtroom Repairs & Alterations - Charles L. Brieant Jr. Court House in White Plains, NY | EQ2PCM210013 | General Services Administration Public Buildings Service Region 2 | Pre-Solicitation 1/4 | 9/24/21, 3:54 PM | |
5th Floor East Courtroom Repairs & Alterations - Charles L. Brieant Jr. Court House in White Plains, NY | 47PC0222R0015 | General Services Administration Public Buildings Service | Award Notice 4/4 | 12/23/22, 10:31 AM | |
5th Floor East Courtroom Repairs & Alterations - Charles L. Brieant Jr. Court House in White Plains, NY | 47PC0222R0015 | General Services Administration Public Buildings Service Region 2 | Solicitation 3/4 | 3/3/22, 5:15 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| PS0011 | Supplemental Agreement for work within scope | $0 | 5/21/25 | |
| PS0012 | Supplemental Agreement for work within scope | $8.8k | 5/21/25 | |
| PS0010 | Supplemental Agreement for work within scope | $0 | 4/4/25 | |
| PS0009 | Supplemental Agreement for work within scope | $4.0k | 1/28/25 | |
| PS0008 | Supplemental Agreement for work within scope | $0 | 11/19/24 |