The contractor shall provide all tools, equipment, materials, labor, supervision, personnel, and shall do all things necessary that will result in the construction of the upgrade switchgear and…
Active Definitive Contract Awarded Last action
- Contract number
- 36E77620C0057
- Awardee
-
Veteran Design & Construction Inc. UEI JCZTEML8Z2W9
- Awarding agency
-
VA Technology Acquisition Center
Headquarters, Department of Veterans Affairs
- Obligated
- $5,362,805
Award facts
- Opportunity
-
- Upgrade Switchgear and Distribution - Baltimore Pre-Solicitation · 36E77620B0001 · Posted Dec 11, 2019
- Upgrade Switchgear and Distribution - Baltimore Award Notice · Posted Jun 15, 2020
- Upgrade Switchgear and Distribution - Baltimore Solicitation · Posted Jan 15, 2020
- Contract value 100% obligated
- $5,362,804.59 Current and potential, with all options
- Completion date 98% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 238210 Electrical Contractors and Other Wiring Installation Contractors
- Set-aside
- Service-Disabled Veteran-Owned Small Business
- Competition
- Full and Open Competition after exclusion of sources · 7 offers Sealed Bid
- Pricing
- Firm Fixed Price
- Place of performance
- Baltimore, MD 21201, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
- Employment Eligibility Verification (E-Verify) FAR subpart 22.18
- Service Contract Inventory FAR subpart 4.17
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Supplemental Agreement for work within scope | $245,485 | |
| Supplemental Agreement for work within scope | $5,029 | |
| Change Order | $163,964 | |
| Supplemental Agreement for work within scope | -$1,674 | |
| Original award | $4,950,000 |
About this award
The Department of Veterans Affairs Technology Acquisition Center awarded a $5.36 million definitive contract to Veteran Design & Construction Inc. for construction of an upgraded switchgear and distribution system at Baltimore VA Medical Center on August 3, 2020, under a Service-Disabled Veteran-Owned Small Business set-aside.
The contract is firm fixed price. Work includes building a new electrical room, installing enclosed paralleling switchgear on the roof, and associated electrical, mechanical, and plumbing upgrades. Place of performance is Baltimore, MD. The ultimate completion date is December 31, 2026, representing approximately 540 calendar days from notice to proceed.
Service Contract Inventory data shows labor-intensive front-loading during initial construction phases, with $4 million invoiced in FY2021 across 4.3 FTEs and 8,971 hours at a blended rate of $444.70 per hour. Activity declined substantially in subsequent years as construction matured: FY2022 posted $836 thousand across 1.5 FTEs; FY2023 reported minimal hours; FY2024 invoiced $35 thousand across 3.0 FTEs and 6,286 hours at $5.49 per hour. The FY2024 teaming structure included one subcontractor performing 99 percent of contractor hours, indicating subcontracted delivery for closeout and final commissioning work.
Description
The contractor shall provide all tools, equipment, materials, labor, supervision, personnel, and shall do all things necessary that will result in the construction of the upgrade switchgear and distribution construction project.
Quick answers
Who was awarded contract 36E77620C0057?
36E77620C0057 was awarded to Veteran Design & Construction Inc. by VA Technology Acquisition Center (Headquarters) on August 3, 2020.
How much is contract 36E77620C0057 worth?
The government has obligated $5,362,805 on 36E77620C0057.
Was contract 36E77620C0057 competed?
The extent of competition for 36E77620C0057 was full and open competition after exclusion of sources. The government received 7 offers. It was set aside: Service-Disabled Veteran-Owned Small Business.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award