Burial expansion project at fort smith national cemetery

Ended Definitive Contract Awarded Last action

Contract number
36C78620C0286
Awardee
Awarding agency
Obligated
$3,408,406

Award facts

Contract value 100% obligated
$3,408,405.60 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
Service-Disabled Veteran-Owned Small Business
Competition
Full and Open Competition after exclusion of sources · 5 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Fort Smith, AR 72901, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00008 · Design issues requires correct irrigation system and pavement issues. $29,924
Additional Work (new agreement, FAR part 6 applies) P00007 · Unforeseen site conditions requires removal and replacement of subbase with engineered fill. $28,404
Supplemental Agreement for work within scope P00006 · Unforeseen site conditions requires corrections to irrigation system, asphalt, turf, & grass pavers with a 10 day POP extension _burial expansion project at… $34,668
Supplemental Agreement for work within scope P00005 · No cost POP extension _burial expansion project at fort smith national cemetery $0
Supplemental Agreement for work within scope P00004 $0
Supplemental Agreement for work within scope P00003 · Add funds for unforeseen site condition and extend POP 12 days due to bad weather _burial expansion project at fort smith national cemetery $54,010
Supplemental Agreement for work within scope P00002 · POP extended 123 days due to bad weather _burial expansion project at fort smith national cemetery $0
Other Administrative Action P00001 · Change to obligation number for construction_burial expansion project at fort smith national cemetery $0
Original award $3,261,400

About this award

This definitive contract was awarded by the Department of Veterans Affairs National Cemetery Administration to Knighto LLC, doing business as Knight Solutions, for $3.4 million. The contract is for a burial expansion project at Fort Smith National Cemetery in Fort Smith, Arkansas, and involves constructing 2,040 pre-placed crypts, 1,515 in-ground cremains, 1,280 niches, and additional site work to add 4,835 new burial spaces at the cemetery. The period of performance is from June 2020 through May 2022. The solicitation was set aside 100% for Service-Disabled Veteran-Owned Small Businesses and sought bids to fulfill the scope of expanding gravesite capacity as described. No major subcontractors were indicated.

Quick answers

Who was awarded contract 36C78620C0286?

36C78620C0286 was awarded to Knighto LLC by National Cemetery Administration (Department of Veterans Affairs) on June 11, 2020.

How much is contract 36C78620C0286 worth?

The government has obligated $3,408,406 on 36C78620C0286.

Was contract 36C78620C0286 competed?

The extent of competition for 36C78620C0286 was full and open competition after exclusion of sources. The government received 5 offers. It was set aside: Service-Disabled Veteran-Owned Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award