Repair campus steam tunnel & structural supports at the clement j. Zablocki VAMC, milwaukee, WI

Ended Definitive Contract Awarded Last action

Contract number
36C25218C0092
Awardee
Awarding agency
Obligated
$2,217,139

Award facts

Contract value 100% obligated
$2,217,139.30 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
Service-Disabled Veteran-Owned Small Business
Competition
Full and Open Competition after exclusion of sources · 3 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Milwaukee, WI 53295, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00007 · P00007: incorporate RFP109. P00006: incorporate RFP110. P00005: time extension due to pending RFP's for within scope work. P00004: incorporate RFP105, RFP106,… $7,286
Supplemental Agreement for work within scope P00006 · P00006: incorporate RFP110 into contract. P00005: no-cost time extension due to pending RFP's. P00004: incorporate RFP105, RFP106, RFP017 & REA into contract.… $1,502
Supplemental Agreement for work within scope P00005 · P00005: time extension due to pending RFP's for within scope work. P00004: incorporate RFP105, RFP106, RFP017 & REA into contract. P00003: incorporate… $0
Supplemental Agreement for work within scope P00004 · P00004: incorporate RFP105, RFP106, RFP017 & REA into contract. P00003: incorporate RFP103R2 into contract. P00002: incorporate RFP101 & RFP102 into contract.… -$2,078
Supplemental Agreement for work within scope P00003 · P00003: incorporate RFP103R2 into contract. P00002: incorporate RFP101 & RFP102 into contract. P00001: incorporate correct wage determination into contract.… $80,000
Supplemental Agreement for work within scope P00002 · P00002: incorporate RFP101 & RFP102 into contract. P00001: incorporate correct wage determination into contract. Repair campus steam tunnel & structural… $50,430
Supplemental Agreement for work within scope P00001 · P00001: incorporate correct wage determination into contract. Repair campus steam tunnel & structural supports at the clement j. Zablocki VAMC, milwaukee, WI $0
Original award $2,080,000

About this award

This is a definitive contract awarded by the Department of Veterans Affairs (VA) Veterans Health Administration to Progressive Construction Services LLC (PCS), a Service-Disabled Veteran-Owned Small Business (SDVOSB). The contract, valued at $2,217,139.30, is for the repair of the campus steam tunnel and structural supports at the Clement J. Zablocki VA Medical Center in Milwaukee, Wisconsin. PCS has been awarded over $35 million in federal contracts and task orders from 2019 to 2023 to deliver critical infrastructure upgrades, renovations, maintenance, and construction services for VA medical centers in Wisconsin. The firm holds multiple MATOC (Multiple Award Task Order Contract) and IDC (Indefinite Delivery Contract) vehicles with the VA, which allow the agency to rapidly issue task orders to PCS for construction and upgrades at VA hospitals on an as-needed basis.

Quick answers

Who was awarded contract 36C25218C0092?

36C25218C0092 was awarded to Progressive Construction Services LLC by Veterans Integrated Service Network 12 (Veterans Health Administration) on June 4, 2018.

How much is contract 36C25218C0092 worth?

The government has obligated $2,217,139 on 36C25218C0092.

Was contract 36C25218C0092 competed?

The extent of competition for 36C25218C0092 was full and open competition after exclusion of sources. The government received 3 offers. It was set aside: Service-Disabled Veteran-Owned Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award