Design-build construction of casablanca new consulate compound project in casablanca, morocco.

Ended Definitive Contract Awarded Last action

Contract number
19AQMM19C0150
Awardee
Awarding agency
Obligated
$194,434,743

Award facts

Contract value 100% obligated
$194,434,743.31 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Funding agency
Bureau of Overseas Building Operations Department of State
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Morocco

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00032 $1,843,092
Other Administrative Action P00031 · Casablanca NCC $0
Other Administrative Action P00030 · Admin action to designate acor for the casablanca NCC project $0
Supplemental Agreement for work within scope P00029 · Casablanca NCC $935,000
Change Order P00028 · Modification to add a new clin for the new moroccan tax law payments $115,333
Change Order P00027 · Modification for RFP-022 for exterior zellige wall tiles $406,896
Change Order P00026 · Modification for RFP-019A for zellige tiles $298,681
Change Order P00025 · Modification to add clin 0005 to furnish, install and test all gfgi (post) audiovisual equipment. This is a post funded clin. $459,055
Change Order P00024 · Modification to extend the contract completion date 180 non-compensable days to october 13, 2024 $0
Change Order P00023 · Modification to settle RFP-013 $917,951
Change Order P00022 · Modification to settle REA 007 $107,304
Change Order P00021 · Modification to settle REA 005, RFP-018 and RFP-020 $201,039
Change Order P00020 · Modification to provide NTE funding amount for directive MOD P00018 for RFP-015 $128,015
Change Order P00019 · Directive change order modification for additional scope for RFP-015. $0
Change Order P00018 · Directive change order modification for RFP-015. $0
Change Order P00017 · Modification for RFP-013 and RFP-017 $455,392
Change Order P00016 · Modification for RFP 016 for EV charger. $38,229
Change Order P00015 · Modification for RFP 007, 010 and 014. $862,113
Other Administrative Action P00014 · Modification to update vendor code and cage code $0
Change Order P00013 · Modification for REA 002 $571,900
Change Order P00012 · Change order modification to incorporate RFP 005 and RFP 011. $425,323
Change Order P00011 · Change order modification to incorporate RFP 002 and 008. $342,184
Funding Only Action P00010 · Change order modification to incorporate RFP 009 revision 1. $245,235
Change Order P00009 · Change order modification to incorporate revised language into specification section 013550. $0
Change Order P00008 · Modification for RFP 6 to incorporate air and water infiltration testing. $144,784
Change Order P00007 · Modification for RFP 3 for fire modeling design study and revisions. $109,627
Change Order P00006 · Modification for RFP 4 related to febr trays. $32,551
Change Order P00005 · Modification to extend the completion date to april 16, 2024. $0
Other Administrative Action P00004 · Modification to incorporate j.1.1.1 - guide to internet collaboration $0
Other Administrative Action P00003 $0
Change Order P00002 · Settlement of RFP 1 $1,639,479
Change Order P00001 · Addition of clin for covid-19 for casablanca, morocco NCC project. $3,118,200
Original award $181,037,360
Show all 33

About this award

BL Harbert International LLC was awarded a $194.4 million firm fixed-price design-build contract by the U.S. Department of State's Bureau of Overseas Building Operations on September 26, 2019, for the design and construction of a new consulate compound in Casablanca, Morocco. This high-value construction project was not set aside for small business participation and represents a significant diplomatic infrastructure investment. The contract, with an ultimate completion date of June 25, 2025, demonstrates the State Department's commitment to modernizing its overseas facility portfolio with secure, purpose-built diplomatic compounds. As a leading design-build and construction management firm headquartered in Birmingham, Alabama, BL Harbert International brings substantial expertise in complex federal construction projects, including previous embassy and diplomatic facility work across multiple continents.

The project's execution involved a robust subcontracting network of specialized vendors providing critical building systems and materials. Key subcontractors included PWS International, Inc. for doors, windows, glass, and architectural components; Southern Pipe & Supply Company for plumbing and hydronic systems; Daikin Applied Americas for HVAC equipment; Capitol Materials for specialized stucco and finish work; and Fluid Solutions LLC for water treatment and fuel management systems. Additional subcontractors supplied electrical systems, fire protection equipment, security screening devices, lighting fixtures, and specialized construction materials. The extended performance timeline and comprehensive scope of work reflect the complexity inherent in constructing a secure diplomatic facility that must meet rigorous State Department security, operational, and design standards while serving as a prominent U.S. presence in a significant North African market.

Subawards

Subcontractor Amount Awarded
PWS International, Inc. DESIGN-BUILD CONSTRUCTION OF CASABLANCA NEW CONSULATE COMPOUND PROJECT IN CASABLANCA, MOROCCO. Div. 08 - Missing Door Hardware $36,954
The Sherwin-Williams Company DESIGN-BUILD CONSTRUCTION OF CASABLANCA NEW CONSULATE COMPOUND PROJECT IN CASABLANCA, MOROCCO. Traffic Coating $54,106
Capitol Materials, Incorporated MODIFICATION TO ADD CLIN 0005 TO FURNISH, INSTALL AND TEST ALL GFGI (POST) AUDIOVISUAL EQUIPMENT. THIS IS A POST FUNDED CLIN. Stucco Make Up Order Based on Site… $88,728
Subcontractor not on record MODIFICATION TO ADD CLIN 0005 TO FURNISH, INSTALL AND TEST ALL GFGI (POST) AUDIOVISUAL EQUIPMENT. THIS IS A POST FUNDED CLIN. Terrazzo Replacement $30,538
Subcontractor not on record MODIFICATION TO SETTLE REA 007 Terroxy Terrazzo Material - Makeup Order $219,061
Subcontractor not on record MODIFICATION TO SETTLE REA 007 Hydrotech Roof Materials - MAKEUP ORDER $36,025
Lighting Solutions Inc. MODIFICATION TO SETTLE REA 007 SG1 light fixture $71,930
Capitol Materials, Incorporated MODIFICATION TO SETTLE REA 007 9 - Stucco Air & Moisture Barrier - F $92,916
Subcontractor not on record Modification to settle REA 005, RFP-018 and RFP-020 indirect heat exchanger and hydronic MUO $61,871
Daikin Applied Americas Inc. MODIFICATION TO SETTLE REA 007 Central Station AHUs - Occupancy Filters - MN1 and MM $295,307
Specialty Products Of Alabama, LLC MODIFICATION TO SETTLE REA 005, RFP-018 AND RFP-020 NOB Motorized Roller Shade Shipment 9 $58,957
American Pipe & Supply Co, Inc. Modification to settle REA 005, RFP-018 and RFP-020 water heater tie in materials (US) $39,386
Show all 12

Quick answers

Who was awarded contract 19AQMM19C0150?

19AQMM19C0150 was awarded to BL Harbert International LLC by Office of Acquisition Management (Department of State) on September 26, 2019.

How much is contract 19AQMM19C0150 worth?

The government has obligated $194,434,743 on 19AQMM19C0150.

Which agency awarded contract 19AQMM19C0150?

Office of Acquisition Management (Department of State) awarded 19AQMM19C0150, with funding from Bureau of Overseas Building Operations (Department of State).

Was contract 19AQMM19C0150 competed?

The extent of competition for 19AQMM19C0150 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award