This project will replace existing stehekin wastewater treatment plant (wwtp) with a modern facility. Project scope includes demolition and removal of existing package skid and tanks, rehabilitation…

Ended Definitive Contract Awarded Last action

Contract number
140P2023C0120
Awardee
Awarding agency
Obligated
$12,141,990

Award facts

Opportunity
Contract value 100% obligated
$12,141,989.85 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 2 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Stehekin, WA 98852, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00006 · This modification is to definitize the unilateral modification $554,640
Additional Work (new agreement, FAR part 6 applies) P00005 $0
Additional Work (new agreement, FAR part 6 applies) P00004 $0
Supplemental Agreement for work within scope P00003 · This modification is to compensate the contractor for RFP 0001, 0002, and 0004. $12,841
Supplemental Agreement for work within scope P00002 · This project will extend the period of performance from 31 october 2025 to 21 april 2026. $0
Supplemental Agreement for work within scope P00001 · This project will provide crane service for the placement of 4 large containment tanks. $93,459
Original award $11,481,050

About this award

The National Park Service awarded a $12.14 million definitive contract to HB Hansen Construction, Inc. for replacement of the Stehekin Wastewater Treatment Plant on September 21, 2023, under a total small business set-aside. The awardee is a self-certified small disadvantaged business.

The project scope includes demolition and removal of the existing package skid and tanks, rehabilitation and upgrade of the building, and installation of new treatment infrastructure. The existing wastewater treatment plant and associated drainfield, originally constructed between 1974–1976, are beyond their useful life; replacement protects water quality in Lake Chelan. Place of performance is Stehekin, WA 98852. The contract carries a firm fixed price and an ultimate completion date of June 1, 2026.

The originating solicitation was issued on a total small business set-aside under NAICS 237110 (Construction of Waste Treatment Facilities) with a $39.5 million size standard. The pre-solicitation posting on July 14, 2023 estimated contract value between $5 million to $10 million and specified a 720 calendar day period of performance.

Through fiscal year 2025, HB Hansen Construction invoiced $3 million (FY2024, 1.9 FTEs, 3,931 contractor hours at $757.11/hr) and $6.9 million (FY2025, 8.3 FTEs). The prime self-performed all reported hours with no subcontractor reporting.

Description

This project will replace existing stehekin wastewater treatment plant (wwtp) with a modern facility. Project scope includes demolition and removal of existing package skid and tanks, rehabilitation and upgrade of the building, and installation of n

Quick answers

Who was awarded contract 140P2023C0120?

140P2023C0120 was awarded to HB Hansen Construction, Inc. by National Office (National Park Service) on September 21, 2023.

How much is contract 140P2023C0120 worth?

The government has obligated $12,141,990 on 140P2023C0120.

Was contract 140P2023C0120 competed?

The extent of competition for 140P2023C0120 was full and open competition after exclusion of sources. The government received 2 offers. It was set aside: Total Small Business.

On GovTribe