This project will address critical failing electrical infrastructure at yosemite national park in california. IT will replace or repair 5.1 miles (26,928 lineal feet ) of 70KV (KILOVOLT)…
Ended Definitive Contract Awarded Last action
- Contract number
- 140P2021C0048
- Awardee
-
Pacific Gas And Electric Company UEI J9EKLNMZXFM6
- Awarding agency
-
National Office
National Park Service, Department of the Interior
- Obligated
- $8,927,052
Award facts
- Opportunity
-
- YOSE 271651, Critical Repair and Replacement of 70KV Transmission Line From Par Pre-Solicitation · 140P2020R0097 · Posted Oct 2, 2020
- Yose 271651 - 70KV trans line rehab Limited / Sole Source Justification · Posted Apr 14, 2021
- Contract value 100% obligated
- $8,927,052.00 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- NAICS code
- 237130 Power and Communication Line and Related Structures Construction
- PSC
- S119 Utilities- Other
- Set-aside
- No set-aside
- Competition
- Not Available for Competition · 1 offer Only One Source
- Pricing
- Firm Fixed Price
- Place of performance
- Yosemite National Park, California, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
- Employment Eligibility Verification (E-Verify) FAR subpart 22.18
- Service Contract Inventory FAR subpart 4.17
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Supplemental Agreement for work within scope | $0 | |
| Original award | $8,927,052 |
About this award
The National Park Service awarded an $8.9 million firm fixed price contract to Pacific Gas and Electric Company (PG&E) to replace or repair approximately 5.1 miles of 70-kilovolt transmission line within Yosemite National Park in California. The line provides power to Yosemite Valley and surrounding areas serving up to 20,000 daily visitors and residents. Work will include repairs and replacements to address deficiencies identified in condition assessments of the towers, insulators, and conductors, with an estimated period of performance of one year beginning in January 2021. As the utility with technical expertise, certifications, equipment and experience working in the park, PG&E was deemed the only qualified party capable of performing the estimated $10 million in repairs to current standards. The funding agency is the Department of the Interior National Park Service National Office.
Description
This project will address critical failing electrical infrastructure at yosemite national park in california. IT will replace or repair 5.1 miles (26,928 lineal feet ) of 70KV (KILOVOLT) transmission line supported by 54 metal structures constructed
Quick answers
Who was awarded contract 140P2021C0048?
140P2021C0048 was awarded to Pacific Gas And Electric Company by National Office (National Park Service) on April 1, 2021.
How much is contract 140P2021C0048 worth?
The government has obligated $8,927,052 on 140P2021C0048.
Was contract 140P2021C0048 competed?
The extent of competition for 140P2021C0048 was not available for competition. The government received 1 offer.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award