Definitive Contract 140P1421C0001
Award Date 1/21/21
Potential Completion Date 4/15/22
Potential Value $56K
Federal Agency
Awardee
Ultimate Awardee
Not listed NAICS Category
Federal Contract Vehicle
- Not listed
Set-Aside Type
Total Small Business
Extent Competed
Competed under SAP
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Fort Smith, MT 59035, USA
Solicitation Procedures
Simplified Acquisition
Number Of Offers Received
3
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- The U.S. Bureau of Reclamation awarded a $300,250 delivery order to Hydra Engineering & Construction, LLC, a woman-owned small business based in Crawfordsville, Florida, for the extension of the Big Sandy Boat Ramp located in Boulder, Wyoming. This firm-fixed-price contract, awarded on September 20, 2024, is set aside for small businesses and carries an ultimate completion date of November 1, 2025. The work is being performed under the Great American Outdoors Act Multiple Award Task Order...
- This federal contract was awarded by the Department of the Interior's National Park Service Intermountain Region to C.R. Powless & CO. LLC, a self-certified small disadvantaged business, for the replacement of three docks at Bighorn Canyon National Recreation Area. The contract has a firm-fixed price of $192,000.00 and was awarded on April 16, 2018, with a completion date of January 31, 2020. It was set aside for small businesses. C.R. Powless & CO. LLC is a for-profit limited...
- SNC Tallimat, LLC, an SBA-certified 8(a) small business, was awarded a $13.4M firm fixed-price contract by the National Park Service to construct a boat launch ramp extension at Echo Bay within Lake Mead National Recreation Area in Boulder City, Nevada. The project scope includes building a gravel roadway and an in-water boat ramp extending to 1,000 feet above mean sea level using precast concrete panels in 7-foot vertical sections, capable of accommodating water depths up to 40 feet. The work...
- The National Park Service awarded a $13.2M definitive firm fixed-price contract to SNC Tallimat, LLC on January 31, 2025, to extend the public launch ramp at Hemenway Harbor within Lake Mead National Recreation Area in Boulder City, Nevada. The contract, designated as an Indian Small Business Economic Enterprise set-aside, is scheduled for completion by May 16, 2027. The work encompasses construction of gravel roadways, new launch ramps, parking areas, utilities, and associated marina...
- The U.S. Department of the Interior's National Park Service Intermountain Region awarded a $118,391.45 firm-fixed-price delivery order contract to Bairco Construction Inc., a woman-owned small business and HUBZone-certified construction firm, for the Emergency Water System Rehab Project at the OK-A-BEH Marina in the Big Horn Canyon National Recreation Area. The work involves removing and replacing components of the existing water system serving various facilities at the marina. The contract...
- The U.S. Army Corps of Engineers awarded a $280,153.92 firm fixed price delivery order to Lake Contracting, Inc. of Benton, Illinois for resurfacing the auxiliary spillway dam's west service boat ramp in Benton. No set-aside designation was applied to this contract. Work is to be completed by November 30, 2020 to restore the boat ramp, supporting the Corps' mission to maintain navigability of waterways and flood protection infrastructure. As the prime contractor, Lake Contracting will be...
- The National Park Service Intermountain Region awarded a $408,935 delivery order to Bairco Construction Inc., a women-owned small business and HUBZone-certified firm based in Lovell, Wyoming, for excavation and re-lining work at the Lovell Visitor Center Pond within Bighorn Canyon National Recreation Area. The contract, awarded on September 18, 2025, is set aside for total small business and carries a firm fixed price structure with an ultimate completion date of May 12, 2026. A modification has...
- The Department of the Interior National Park Service Intermountain Region awarded a $793,322 delivery order to Bairco Construction Inc. to rehabilitate the afterbay at Fort Smith, Montana under the major program code BICA 304011 RR AFTERBAY CG. The firm fixed price order runs from July 26, 2021 through April 30, 2022 to perform repairs after the afterbay at the National Park Service site. No set aside designation or subcontractors were indicated. The funding falls under the National Park...
- This is a definitive contract awarded by the National Park Service's Intermountain Region to Site Work Solutions, a certified HUBZone small business, for the installation of concessions docks at the OK A BEH Marina in Bighorn Canyon National Recreation Area. The firm fixed-price contract has a ceiling value of $706,944.63 and is set to be completed by June 15, 2017. Site Work Solutions is a construction and facilities maintenance company that specializes in water resource management and...
- This is a firm-fixed price definitive contract awarded by the USDA Forest Service, Region 4 - Intermountain Region to BFC Diversified LLC, a woman-owned small business doing business as Blake Ford Construction, for the replacement of two existing boat ramps located on the Caribou-Targhee National Forest in Fremont County, Idaho. The contract has a ceiling value of $315,933.50 and is set to be completed by December 20, 2024. This contract was awarded under a total small business set-aside...
AFTERBAY RIVER BOAT RAMP EXTENSION, BIGHORN CANYON NATIONAL RECREATION AREA
Posted 1/8/21
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
REPAIR AFTERBAY RIVER BOAT LAUNCH RAMP | 140P1421R0001 | Department of the Interior National Park Service Intermountain Region | Award Notice 3/3 | 1/8/21, 12:27 PM | |
AFTERBAY RIVER BOAT LAUNCH RAMP EXTENSION | 140P1421R0001 | Department of the Interior National Park Service Intermountain Region | Pre-Solicitation 1/3 | 11/5/20, 4:04 PM | |
REPAIR AFTERBAY RIVER BOAT LAUNCH RAMP | 140P1421R0001 | Department of the Interior National Park Service Intermountain Region | Solicitation 2/3 | 11/20/20, 7:54 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00004 | Change Order | $6.3k | 4/5/22 | |
| P00003 | Supplemental Agreement for work within scope | $0 | 3/1/22 | |
| P00002 | Supplemental Agreement for work within scope | $0 | 12/16/21 | |
| P00001 | Supplemental Agreement for work within scope | $0 | 10/21/21 | |
| Not listed | Not listed | $49.5k | 1/8/21 |