RIO grande supervisors office construction project

Ended Definitive Contract Awarded Last action

Contract number
1282AK20C0007
Awardee
Awarding agency
Obligated
$6,346,143

Award facts

Opportunity
Contract value 100% obligated
$6,345,142.88 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Funding agency
Region 2 - Rocky Mountain Region Forest Service, Department of Agriculture
Set-aside
Competitive 8(a)
Competition
Full and Open Competition after exclusion of sources · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Del Norte, CO 81132, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action P00026 · The purpose of this modification is to change the contracting officer from kellie shaw to tanya spanfellner. All further communications must go to and be signed… $0
Supplemental Agreement for work within scope P00025 -$1,000
Supplemental Agreement for work within scope P00023 -$2,000
Supplemental Agreement for work within scope P00022 · The purpose of this modification is to extend the completion date of the contract from october 26, 2022 to november 16, 2022. Extending the completion date of… $0
Supplemental Agreement for work within scope P00021 · The purpose of this modification is to obligate $19,141.20 to fund the following: **RFP 021 - total $19,141.20 RFP 021 incorporates changes to the drainage… $19,141
Supplemental Agreement for work within scope P00020 · The purpose of this modification is to obligate $5,945.94 to fund the following: **RFP 018 - total $2,201.94 RFP 018 includes supply and install a storeroom… $5,946
Supplemental Agreement for work within scope P00019 · The purpose of this modification is to obligate $17,207.19 to fund the following: **RFP 014 - total $13,016.25 RFP 014 includes raising the bar height… $17,207
Supplemental Agreement for work within scope P00018 · The purpose of this modification is to obligate $51,799.15 to fund the following: *change order #014 - additional electrical circuits $23,220.09 per price quote… $51,799
Supplemental Agreement for work within scope P00017 · The purpose of this modification is to add $2,925.00 to the contract to move the return air for furnace 4 to a new location. The change of location of the… $2,925
Supplemental Agreement for work within scope P00016 · The purpose of this modification is to obligate $24,757.20 to fund the following: *RFP-011 - additional landscaping $24,757.20 per price quote dated 3/18/2022… $24,757
Supplemental Agreement for work within scope P00015 · The purpose of this modification is to obligate $1,755.00 to fund the following: *RFP-013 - additional fence post holes $1,755.00 per price quote dated… $1,755
Supplemental Agreement for work within scope P00014 · The purpose of this modification is to obligate $26,344.27 to fund the following: *RFP-010 - additional light pole $23,075.45 per price quote dated 2/18/2022… $26,344
Supplemental Agreement for work within scope P00013 · The purpose of this modification is to obligate $25,828.94 to fund change order 9 for submittal delays caused by the government per the revised change order… $26,531
Supplemental Agreement for work within scope P00012 · The purpose of this modification is to obligate $67,053.81 to fund RFP-005 for the trash enclosure per the price quote 9/10/2021 and $4,095.00 to fund change… $71,149
Supplemental Agreement for work within scope P00011 · The purpose of this modification is to obligate $18,790.20 to fund RFP-001 for brick tuckpointing per the price quote 9/9/2021, $177,383.70 to fund RFP-006… $200,028
Supplemental Agreement for work within scope P00010 · The purpose of this modification is to obligate $17,867.07 to fund RFP-002 for furniture power/data floor relocation per the price quote dated 9/7/2021,… $85,718
Supplemental Agreement for work within scope P00009 · The purpose of this modification is to obligate $64836.78 for change request 10 per the revised price proposal dated 9/1/2021. The change is to add parterre LVT… $64,837
Supplemental Agreement for work within scope P00008 · The purpose of this modification is to obligate $6,084.00 for change order 4 per price proposal dated 6/14/2021. The change includes the supply and install 2… $6,084
Supplemental Agreement for work within scope P00007 · The purpose of this modification is to obligate $12,379.18 for change order 5 to sawcut and remove and replace new concrete in all three existing restroom… $13,559
Exercise an Option P00006 · The purpose of this modification is to add $65,563.20 in funding to the contract for optional item 23 export rock spoils. The schedule of items in the awarded… $65,563
Supplemental Agreement for work within scope P00005 · The purpose of this modification is to add $88,490.00 in funding to the contract for rock hammer excavation, additional shingle removal, asbestos vent pipe… $88,490
Change Order P00004 · RIO grande supervisors office construction project modification four (04) changes IPP approver 2 to ANN ("peggy") dobie. All other terms and conditions remain… $0
Other Administrative Action P00003 · RIO grande supervisors office construction project modification three (03) is an administrative modification to change the contracting officer on this project… $0
Other Administrative Action P00002 · RIO grande supervisors office construction project modification two (02) is an administrative modification to change the IPP approver in the IAS system to jason… $0
Other Administrative Action P00001 · RIO grande supervisors office construction project modification one (01) is an administrative modification to change the IPP approver in the IAS system to jason… $0
Original award $5,577,310
Show all 26

About this award

Jita Contracting, Inc. was awarded a $6.3 million firm fixed price contract by the USDA Forest Service Rocky Mountain Region to provide construction services for the Rio Grande Supervisor's Office Construction Project in Del Norte, Colorado. Under the contract, Jita Contracting will renovate the former Del Norte High School building, which involves demolishing approximately 60% of the existing 14,400 square foot structure and renovating the remaining space to comply with building codes, federal space requirements, and sustainability guidelines. The solicitation was designated as an 8(a) small business set-aside restricted to Colorado-based contractors. Performance will take place in Del Norte and is expected to be completed by May 2023. No major subcontractors were identified.

Quick answers

Who was awarded contract 1282AK20C0007?

1282AK20C0007 was awarded to Jita Contracting, Inc. by Forest Service (Department of Agriculture) on September 24, 2020.

How much is contract 1282AK20C0007 worth?

The government has obligated $6,346,143 on 1282AK20C0007. Its current value, with exercised options, is $6,345,143.

Which agency awarded contract 1282AK20C0007?

Forest Service (Department of Agriculture) awarded 1282AK20C0007, with funding from Region 2 - Rocky Mountain Region (Forest Service).

Was contract 1282AK20C0007 competed?

The extent of competition for 1282AK20C0007 was full and open competition after exclusion of sources. The government received 3 offers. It was set aside: Competitive 8(a).

On GovTribe

See this award's full record