Text

Before first article approval, the acquisition of materials or components, or commencement of production, is normally at the sole risk of the contractor. To minimize this risk, the contracting officer shall provide sufficient time in the delivery schedule for acquisition of materials and components, and for production after receipt of first article approval. When Government requirements preclude this action, the contracting officer may, before approval of the first article, authorize the contractor to acquire specific materials or components or commence production to the extent essential to meet the delivery schedule (see Alternate II of the clause at 52.209-3, First Article Approval-Contractor Testing, and Alternate II of the clause at 52.209-4, First Article Approval-Government Testing). Costs incurred based on this authorization are allocable to the contract for—

(a) Progress payments; and

(b) Termination settlements if the contract is terminated for the convenience of the Government.

Federal Register history

Final rule Published Effective
Federal Acquisition Regulation; Technical Amendments 84 FR 19839 · FAC 2019-02

Proposed changes

Proposed rule Published Comments
Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 9, 27, and 47 91 FR 59584 · FAR Case 2026-011, Docket No. FAR-2026-0011, Sequence No. 1 Closed Oct 19, 2026No final rule found

Sections cited

Quick answers

What is FAR 9.305?

FAR 9.305 is a section of the Federal Acquisition Regulation, titled "Risk".

When was FAR 9.305 last changed?

The most recent final rule on record is "Federal Acquisition Regulation; Technical Amendments" (84 FR 19839), published May 6, 2019 and effective May 6, 2019.

Are changes to FAR 9.305 proposed?

One proposed change has no final rule yet.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract