FAR 8.404 Use of Federal Supply Schedules

Section Federal Acquisition Regulation

Facts

Citation
FAR 8.404
Type
Section
Last amended
90 FR 41872 Effective Oct 1, 2025
Proposed changes
1
Text as of
FAC 2026-01
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this section.

Text

(a) General. parts 13 (except 13.303-2(c)(3)), 14, 15, and 19 (except for the requirements at 19.102(b)(3) and 19.202-1(e)(1)(iii)) do not apply to BPAs or orders placed against Federal Supply Schedules contracts (but see 8.405-5). BPAs and orders placed against a MAS, using the procedures in this subpart, are considered to be issued using full and open competition (see 6.102(d)(3)). Therefore, when establishing a BPA (as authorized by 13.303-2(c)(3)), or placing orders under Federal Supply Schedule contracts using the procedures of 8.405, ordering activities shall not seek competition outside of the Federal Supply Schedules or synopsize the requirement; but see paragraph (g) of this section.

(b)

(1) The contracting officer, when placing an order or establishing a BPA, is responsible for applying the regulatory and statutory requirements applicable to the agency for which the order is placed or the BPA is established. The requiring agency shall provide the information on the applicable regulatory and statutory requirements to the contracting officer responsible for placing the order.

(2) For orders over $750,000, see subpart 17.5 for additional requirements for interagency acquisitions.

(c) Acquisition planning. Orders placed under a Federal Supply Schedule contract-

(1) Are not exempt from the development of acquisition plans (see subpart 7.1), and an information technology acquisition strategy (see part 39);

(2) Shall comply with all FAR requirements for a consolidated or bundled contract when the order meets the definition at 2.101 of "consolidation" or "bundling"; and

(3) Must, whether placed by the requiring agency, or on behalf of the requiring agency, be consistent with the requiring agency’s statutory and regulatory requirements applicable to the acquisition of the supply or service.

(d) Pricing. Supplies offered on the schedule are listed at fixed prices. Services offered on the schedule are priced either at hourly rates, or at a fixed price for performance of a specific task (e.g., installation, maintenance, and repair). GSA has already determined the prices of supplies and fixed-price services, and rates for services offered at hourly rates, under schedule contracts to be fair and reasonable. Therefore, ordering activities are not required to make a separate determination of fair and reasonable pricing, except for a price evaluation as required by 8.405-2(d). By placing an order against a schedule contract using the procedures in 8.405, the ordering activity has concluded that the order represents the best value (as defined in FAR 2.101) and results in the lowest overall cost alternative (considering price, special features, administrative costs, etc.) to meet the Government’s needs. Although GSA has already negotiated fair and reasonable pricing, ordering activities may seek additional discounts before placing an order (see 8.405-4).

(e) The procedures under subpart 33.1 are applicable to the issuance of an order or the establishment of a BPA against a schedule contract.

(f) If the ordering activity issues an RFQ, the ordering activity shall provide the RFQ to any schedule contractor that requests a copy of it.

(g)

(1) Ordering activities shall publicize contract actions funded in whole or in part by the American Recovery and Reinvestment Act of 2009 (Pub. L. 111-5):

(i) Notices of proposed MAS orders (including orders issued under BPAs) that are for "informational purposes only" exceeding $25,000 shall follow the procedures in 5.704 for posting orders.

(ii) Award notices for MAS orders (including orders issued under BPAs) shall follow the procedures in 5.705.

(2) When an order is awarded or a Blanket Purchase Agreement is established with an estimated value greater than the simplified acquisition threshold and supported by a limited-source justification at 8.405-6 (a), the ordering activity contracting officer must-

(i) Publicize the action (see 5.301); and

(ii) Post the justification in accordance with 8.405-6 (a)(2).

(h) Type-of-order preference for services.

(1) The ordering activity shall specify the order type (i.e., firm-fixed price, time-and-materials, or labor-hour) for the services offered on the schedule priced at hourly rates.

(2) Agencies shall use fixed-price orders for the acquisition of commercial services to the maximum extent practicable.

(3)

(i) A time-and-materials or labor-hour order may be used for the acquisition of commercial services only when it is not possible at the time of placing the order to estimate accurately the extent or duration of the work or to anticipate costs with any reasonable degree of confidence.

(ii) Prior to the issuance of a time-and-materials or labor-hour order, the contracting officer shall-

(A) Execute a determination and findings (D&F) for the order, in accordance with paragraph (h)(3)(iii) of this section that a fixed-price order is not suitable;

(B) Include a ceiling price in the order that the contractor exceeds at its own risk; and

(C) When the total performance period, including options, is more than three years, the D&F prepared in accordance with this paragraph shall be signed by the contracting officer and approved by the head of the contracting activity prior to the execution of the base period.

(iii) The D&F required by paragraph (h)(3)(ii)(A) of this section shall contain sufficient facts and rationale to justify that a fixed-price order is not suitable. At a minimum, the D&F shall-

(A) Include a description of the market research conducted (see 8.404(c) and 10.002(e));

(B) Establish that it is not possible at the time of placing the order to accurately estimate the extent or duration of the work or anticipate costs with any reasonable degree of confidence;

(C) Establish that the current requirement has been structured to maximize the use of fixed-price orders (e.g., by limiting the value or length of the time-and-materials/labor-hour order; or, establishing fixed prices for portions of the requirement) on future acquisitions for the same or similar requirements; and

(D) Describe actions to maximize the use of fixed-price orders on future acquisitions for the same requirements.

(iv) Prior to an increase in the ceiling price of a time-and-materials or labor-hour order, the ordering activity shall-

(A) Conduct an analysis of pricing and other relevant factors to determine if the action is in the best interest of the Government and document the order file;

(B) Follow the procedures at 8.405-6 for a change that modifies the general scope of the order; and

(C) Comply with the requirements at 8.402(f) when modifying an order to add open market items.

(i) Ensure that service contractor reporting requirements are met in accordance with subpart 4.17, Service Contracts Inventory.

(j) Line items. When placing orders or establishing BPAs, ordering activities shall reference the special item number and the corresponding line or subline item awarded (established per 4.1005) in the schedule. If an ordering activity contracting officer adds an item not on the Federal Supply Schedule in accordance with 8.402(f), establish a new line item in accordance with subpart 4.10.

Federal Register history

Final rule Published Effective
Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds 90 FR 41872 · FAC 2025-06, FAR Case 2024-001
Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds 85 FR 62485 · FAC 2021-01, FAR Case 2019-013, Docket No. FAR-2019-0013
Federal Acquisition Regulation; Set-Asides Under Multiple-Award Contracts 85 FR 11746 · FAC 2020-05
Federal Acquisition Regulation: Governmentwide and Other Interagency Contracts 84 FR 19837 · FAC 2019-02
Federal Acquisition Regulation; Uniform Use of Line Items 82 FR 4709 · FAC 2005-95
Federal Acquisition Regulation; Consolidation and Bundling 81 FR 67763 · FAC 2005-91
Federal Acquisition Regulation; Inflation Adjustment of Acquisition-Related Thresholds 80 FR 38293 · FAC 2005-83
Federal Acquisition Regulation; Service Contracts Reporting Requirements 78 FR 80369 · FAC 2005-72
Federal Acquisition Regulation; Changes to Time-and-Materials and Labor-Hour Contracts and Orders 78 FR 13766 · FAC 2005-66
Federal Acquisition Regulation; Time-and-Materials and Labor-Hour Contracts for Commercial Items 77 FR 194 · FAC 2005-55
Federal Acquisition Regulation; Requirements for Acquisitions Pursuant to Multiple-Award Contracts 76 FR 14548 · FAC 2005-50
Federal Acquisition Regulation; Preventing Abuse of Interagency Contracts 75 FR 77733 · FAC 2005-47
Federal Acquisition Regulation; FAR Case 2009-010, American Recovery and Reinvestment Act of 2009 (the Recovery Act)-Publicizing Contract Actions 74 FR 14636 · FAC 2005-32
Federal Acquisition Regulation; Federal Supply Schedules Services and Blanket Purchase Agreements (BPAs) 69 FR 34231 · FAC 2001-24
Federal Acquisition Regulation; Contract Bundling 68 FR 60000 · FAC 2001-17
Federal Acquisition Regulation; Task-Order and Delivery-Order Contracts 67 FR 56117 · FAC 2001-09
Federal Acquisition Regulation; Federal Supply Schedules Small Business Opportunities 65 FR 36023 · FAC 97-18
Show all 17

Proposed changes

Proposed rule Published Comments
Federal Acquisition Regulation: Preventing Organizational Conflicts of Interest in Federal Acquisition 90 FR 4376 · FAR Case 2023-006, Docket No. FAR-2023-0006, Sequence No. 1 Closed Mar 17, 2025No final rule found

Sections cited

Quick answers

What is FAR 8.404?

FAR 8.404 is a section of the Federal Acquisition Regulation, titled "Use of Federal Supply Schedules".

When was FAR 8.404 last changed?

The most recent final rule on record is "Federal Acquisition Regulation: Inflation Adjustment of Acquisition-Related Thresholds" (90 FR 41872), published Aug 27, 2025 and effective Oct 1, 2025.

Are changes to FAR 8.404 proposed?

One proposed change has no final rule yet.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements