FAR 52.249-14 Excusable Delays

Clause Federal Acquisition Regulation Apr 1984 version

Facts

Citation
FAR 52.249-14
Type
Clause
Current version
April 1984
Prescribed in
FAR 49.505(b)
Last amended
72 FR 27364 Effective Jun 14, 2007
Proposed changes
1
Text as of
FAC 2026-01
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this clause.

Text

As prescribed in 49.505(b), insert the following clause in solicitations and contracts for supplies, services, construction, and research and development on a fee basis whenever a cost-reimbursement contract is contemplated. Also insert the clause in time-and-material contracts, and labor-hour contracts. When used in construction contracts, substitute the words "completion time" for "delivery schedule" in the last sentence of the clause.

Excusable Delays (Apr 1984)

(a) Except for defaults of subcontractors at any tier, the Contractor shall not be in default because of any failure to perform this contract under its terms if the failure arises from causes beyond the control and without the fault or negligence of the Contractor. Examples of these causes are (1) acts of God or of the public enemy, (2) acts of the Government in either its sovereign or contractual capacity, (3) fires, (4) floods, (5) epidemics, (6) quarantine restrictions, (7) strikes, (8) freight embargoes, and (9) unusually severe weather. In each instance, the failure to perform must be beyond the control and without the fault or negligence of the Contractor. "Default" includes failure to make progress in the work so as to endanger performance.

(b) If the failure to perform is caused by the failure of a subcontractor at any tier to perform or make progress, and if the cause of the failure was beyond the control of both the Contractor and subcontractor, and without the fault or negligence of either, the Contractor shall not be deemed to be in default,- unless-

(1) The subcontracted supplies or services were obtainable from other sources;

(2) The Contracting Officer ordered the Contractor in writing to purchase these supplies or services from the other source; and

(3) The Contractor failed to comply reasonably with this order.

(c) Upon request of the Contractor, the Contracting Officer shall ascertain the facts and extent of the failure. If the Contracting Officer determines that any failure to perform results from one or more of the causes above, the delivery schedule shall be revised, subject to the rights of the Government under the termination clause of this contract.

(End of clause)

Federal Register history

Final rule Published Effective
Federal Acquisition Regulation; FAR Case 2004-025, Government Property 72 FR 27364 · FAC 2005-17

Proposed changes

Proposed rule Published Comments
Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 3 and 49 91 FR 37698 · FAR Case 2026-007, Docket No. FAR-2026-0007, Sequence No. 1 Closed Jul 23, 2026No final rule found

Quick answers

What is FAR 52.249-14?

FAR 52.249-14 is a clause of the Federal Acquisition Regulation, titled "Excusable Delays".

What is the current version of FAR 52.249-14?

The current version is dated April 1984.

Where is FAR 52.249-14 prescribed?

It is prescribed in FAR 49.505(b), Other termination clauses.

When was FAR 52.249-14 last changed?

The most recent final rule on record is "Federal Acquisition Regulation; FAR Case 2004-025, Government Property" (72 FR 27364), published May 15, 2007 and effective Jun 14, 2007.

Are changes to FAR 52.249-14 proposed?

One proposed change has no final rule yet.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract