Text

As prescribed in 41.501(d)(4), insert a clause substantially the same as the following:

Termination Liability (Feb 1995)

(a) If the Government discontinues utility service under this contract before completion of the facilities cost recovery period specified in paragraph (b) of this clause, in consideration of the Contractor furnishing and installing at its expense, the new facility described herein, the Government shall pay termination charges, calculated as set forth in this clause.

(b) Facility cost recovery period. The period of time, not exceeding the term of this contract, during which the net cost of the new facility shall be recovered by the Contractor is [fill-in] months.[Insert negotiated duration.]

(c) Net facility cost. The cost of the new facility, less the agreed upon salvage value of such facility, is $[fill-in]

(d) Monthly facility cost recovery rate. The monthly facility cost recovery rate which the Government shall pay the Contractor whether or not service is received is $[fill-in]

(e) Termination charges. Termination charges = $[fill-in]

(f) If the Contractor has recovered its capital costs at the time of termination there will be no termination liability charge.

(End of clause)

Proposed changes

Proposed rule Published Comments
Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 6, 7, 10, 18, 26, 37, and 41 91 FR 37636 · FAR Case 2026-002, Docket No. FAR-2026-0002, Sequence No. 1 Closed Jul 23, 2026No final rule found

Quick answers

What is FAR 52.241-10?

FAR 52.241-10 is a clause of the Federal Acquisition Regulation, titled "Termination Liability".

What is the current version of FAR 52.241-10?

The current version is dated February 1995.

Where is FAR 52.241-10 prescribed?

It is prescribed in FAR 41.501(d)(4), Solicitation provision and contract clauses.

Are changes to FAR 52.241-10 proposed?

One proposed change has no final rule yet.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract