FAR 52.237-6 Incremental Payment by Contractor to Government

Clause Federal Acquisition Regulation Apr 1984 version

Facts

Citation
FAR 52.237-6
Type
Clause
Current version
April 1984
Prescribed in
FAR 37.304(c)
Proposed changes
1
Text as of
FAC 2026-01
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this clause.

Text

As prescribed in 37.304(c), insert the following clause in solicitations and contracts for dismantling, demolition, or removal of improvements (a) if the Contractor is to receive title to dismantled or demolished property and a net amount of compensation is due the Government; and (b) if the Contracting Officer determines that it would be advantageous to the Government for the Contractor to pay in increments, and for the Government to transfer title to the Contractor for increments of property, only upon receipt of those payment:

Incremental Payment by Contractor to Government (Apr 1984)

(a) The Contractor shall perform the work called for under this contract and within [fill-in] days of receipt of notice of award, unless otherwise provided in the Schedule, and before proceeding with the work, shall pay [fill-in]. Thereafter, the Contractor shall make payment to the Government in the amount and frequency specified in the Schedule. Checks shall be made payable to the office designated in the contract and shall be forwarded to the Contracting Officer.

(b) Upon the Government’s receipt of each increment of payment, the Contractor shall receive title to such property as the Contracting Officer determines to be fair and reasonable for that increment of payment. Upon receipt of the Contractor’s final payment, all title that has not passed to the Contractor shall vest in the Contractor, unless specifically designated in the Schedule as being retained by the Government. The Government shall not be responsible for the condition of, or any loss or damage to, the property.

(c) The Contractor shall promptly remove from the site all property acquired by the Contractor. The Government will not permit storage of property on the site beyond the completion date. If the Contractor does not wish to remove from the site any of the property acquired, the Contracting Officer may, upon written request, grant the Contractor permission to leave the property on the premises. As a condition of the granting of this permission, the Contractor agrees to waive any right, title, claim, or interest in and to the property.

(End of clause)

Proposed changes

Proposed rule Published Comments
Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 6, 7, 10, 18, 26, 37, and 41 91 FR 37636 · FAR Case 2026-002, Docket No. FAR-2026-0002, Sequence No. 1 Closed Jul 23, 2026No final rule found

Quick answers

What is FAR 52.237-6?

FAR 52.237-6 is a clause of the Federal Acquisition Regulation, titled "Incremental Payment by Contractor to Government".

What is the current version of FAR 52.237-6?

The current version is dated April 1984.

Where is FAR 52.237-6 prescribed?

It is prescribed in FAR 37.304(c), Contract clauses.

Are changes to FAR 52.237-6 proposed?

One proposed change has no final rule yet.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract