FAR 52.236-26 Preconstruction Conference
Clause Federal Acquisition Regulation Feb 1995 version
Facts
- Citation
- FAR 52.236-26
- Type
- Clause
- Current version
- February 1995
- Prescribed in
- FAR 36.522
- Proposed changes
- 1
- Text as of
- FAC 2026-01
- Official text
- acquisition.gov
Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this clause.
Text
As prescribed in 36.522 , insert the following clause:
Preconstruction Conference (Feb 1995)
If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed.
(End of clause)
Proposed changes
| Proposed rule | Published | Comments |
|---|---|---|
| Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 14, 28, 36, and 52 | Closed Oct 19, 2026No final rule found |
Quick answers
What is FAR 52.236-26?
FAR 52.236-26 is a clause of the Federal Acquisition Regulation, titled "Preconstruction Conference".
What is the current version of FAR 52.236-26?
The current version is dated February 1995.
Where is FAR 52.236-26 prescribed?
It is prescribed in FAR 36.522, Preconstruction conference.
Are changes to FAR 52.236-26 proposed?
One proposed change has no final rule yet.
On GovTribe
Follow the rules behind federal contracts
- Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
- Solicitations, awards and government files in one search
- Ask GovTribe AI about the rules that apply to a contract