FAR 52.236-14 Availability and Use of Utility Services

Clause Federal Acquisition Regulation Apr 1984 version

Facts

Citation
FAR 52.236-14
Type
Clause
Current version
April 1984
Prescribed in
FAR 36.514
Proposed changes
1
Text as of
FAC 2026-01
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this clause.

Text

As prescribed in 36.514 , insert the following clause in solicitations and contracts when a fixed-price construction contract or a fixed-price dismantling, demolition, or removal of improvements contract is contemplated, the contract is to be performed on Government sites when the contracting officer decides (a) that the existing utility system is adequate for the needs of both the Government and the contractor, and (b) furnishing it is in the Government’s interest. When this clause is used, the contracting officer shall list the available utilities in the contract.

Availability and Use of Utility Services (Apr 1984)

(a) The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. Unless otherwise provided in the contract, the amount of each utility service consumed shall be charged to or paid for by the Contractor at prevailing rates charged to the Government or, where the utility is produced by the Government, at reasonable rates determined by the Contracting Officer. The Contractor shall carefully conserve any utilities furnished without charge.

(b) The Contractor, at its expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of each utility used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.

(End of clause)

Proposed changes

Proposed rule Published Comments
Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 14, 28, 36, and 52 91 FR 59534 · FAR Case 2026-010, Docket No. FAR-2026-0010, Sequence No. 1 Closed Oct 19, 2026No final rule found

Quick answers

What is FAR 52.236-14?

FAR 52.236-14 is a clause of the Federal Acquisition Regulation, titled "Availability and Use of Utility Services".

What is the current version of FAR 52.236-14?

The current version is dated April 1984.

Where is FAR 52.236-14 prescribed?

It is prescribed in FAR 36.514, Availability and use of utility services.

Are changes to FAR 52.236-14 proposed?

One proposed change has no final rule yet.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract