FAR 52.232-28 Invitation to Propose Performance-Based Payments
Solicitation provision Federal Acquisition Regulation Mar 2000 version
Facts
- Citation
- FAR 52.232-28
- Type
- Solicitation provision
- Current version
- March 2000
- Prescribed in
- FAR 32.1005(b)(1)
- Alternates
- Alternate I
- Last amended
- 65 FR 16276 Effective Mar 27, 2000
- Text as of
- FAC 2026-01
- Official text
- acquisition.gov
Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this solicitation provision.
Text
As prescribed in 32.1005(b)(1), insert the following provision:
Invitation to Propose Performance-Based Payments (Mar 2000)
(a) The Government invites the offeror to propose terms under which the Government will make performance-based contract financing payments during contract performance. The Government will consider performance-based payment financing terms proposed by the offeror in the evaluation of the offeror’s proposal. The Contracting Officer will incorporate the financing terms of the successful offeror and the FARclause, Performance-Based Payments, at FAR 52.232-32, in any resulting contract.
(b) In the event of any conflict between the terms proposed by the offeror and the terms in the clause at FAR 52.232-32, Performance-Based Payments, the terms of the clause at FAR 52.232-32 shall govern.
(c) The Contracting Officer will not accept the offeror’s proposed performance-based payment financing if the financing does not conform to the following limitations:
(1) The Government will make delivery payments only for supplies delivered and accepted, or services rendered and accepted in accordance with the payment terms of this contract.
(2) The terms and conditions of the performance-based payments must-
(i) Comply with FAR 32.1004;
(ii) Be reasonable and consistent with all other technical and cost information included in the offeror’s proposal; and
(iii) Their total shall not exceed 90 percent of the contract price if on a whole contract basis, or 90 percent of the delivery item price if on a delivery item basis.
(3) The terms and conditions of the performance-based financing must be in the best interests of the Government.
(d) The offeror’s proposal of performance-based payment financing shall include the following:
(1) The proposed contractual language describing the performance-based payments (see FAR 32.1004 for appropriate criteria for establishing performance bases and performance-based finance payment amounts).
(2) A listing of-
(i) The projected performance-based payment dates and the projected payment amounts; and
(ii) The projected delivery date and the projected payment amount.
(3) Information addressing the Contractor’s investment in the contract.
(e) Evaluation of the offeror’s proposed prices and financing terms will include whether the offeror’s proposed performance-based payment events and payment amounts are reasonable and consistent with all other terms and conditions of the offeror’s proposal.
(End of Provision)
Alternate I (Mar 2000)
Alternate I (Mar 2000). As prescribed in FAR 32.1005 (b)(2), add the following paragraph (f) to the basic provision:
(f) The Government will adjust each proposed price to reflect the cost of providing the proposed performance-based payments to determine the total cost to the Government of that particular combination of price and performance-based financing. The Government will make the adjustment using the procedure described in FAR 32.205(c).
Federal Register history
| Final rule | Published | Effective |
|---|---|---|
| Federal Acquisition Regulation; Progress Payments and Related Financing Policies |
Sections cited
- FAR 52.232-32 Performance-Based Payments
- FAR 32.1004 Procedures
Quick answers
What is FAR 52.232-28?
FAR 52.232-28 is a solicitation provision of the Federal Acquisition Regulation, titled "Invitation to Propose Performance-Based Payments".
What is the current version of FAR 52.232-28?
The current version is dated March 2000.
Where is FAR 52.232-28 prescribed?
It is prescribed in FAR 32.1005(b)(1), Solicitation provision and contract clause.
When was FAR 52.232-28 last changed?
The most recent final rule on record is "Federal Acquisition Regulation; Progress Payments and Related Financing Policies" (65 FR 16276), published Mar 27, 2000 and effective Mar 27, 2000.
Are changes to FAR 52.232-28 proposed?
No proposed rule from the last 3 years is waiting on a final rule.
On GovTribe
Follow the rules behind federal contracts
- Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
- Solicitations, awards and government files in one search
- Ask GovTribe AI about the rules that apply to a contract